Just thought I'd let anyone caught up in the problems caused by emergency engineering work at Sway (Between Bornemouth and Brockenhurst) yesterday afternoon and evening that according to my train manager this was caused by a platform that was liable to collapse.

 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

HST Power

Established Member
Joined
25 Nov 2010
Messages
3,704
Just thought I'd let anyone caught up in the problems caused by emergency engineering work at Sway (Between Bornemouth and Brockenhurst) yesterday afternoon and evening that according to my train manager this was caused by a platform that was liable to collapse.


A collapsing platform? :roll:What do they make them out of, rubber? :)
 

Blindtraveler

Established Member
Joined
28 Feb 2011
Messages
10,544
dont think phil sayer can say collapsed platform, wonder what was broadcast! In all seriusness though, good the health and safety boys are onto it nice and quick!
A collapsing platform? :roll:What do they make them out of, rubber? :)



 

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,099
Location
Near where the 3 ridings meet
If the platform is anything like the WYPTE platforms such as Crossflatts.
The timber platforms are supported on paving slabs bedded on ballast. No concrete.
If the ballast is removed for any reason the platform support is likely to move causing the platform to subside or move.
We had to Relay and reballast through this platform a number of years back and we struggled to get the sleeper width without disturbing the platform footing.
It was impossible to get the full specification width dig due to having to leave existing ground in place as support.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,257
No, Sway is a fairly conventional solidly built brick, concrete and tarmac type.

Little obvious reason for it to give way, unlike the many prefabricated platforms in the 'SR' which stand on rotten concrete posts...
 

wintonian

Established Member
Joined
15 Jan 2010
Messages
4,889
Location
Hampshire
I don't know what SWT are doing to their stations at the moment but a few weeks ago Winchester ticket office fell through the floor, well apparently there is a sizable crater anyway and the ticket office has been temporally relocated since.
 