I thought summer next year was being discussed, rather than this year?Does anyone know if the Aldgate junction renewal/remodelling is still expected to go ahead later this year?
I thought summer next year was being discussed, rather than this year?Does anyone know if the Aldgate junction renewal/remodelling is still expected to go ahead later this year?
A blockade is very likely to go ahead, I suspect due to the complexity of the works. Summer 2027 has been pencilled in for a few years now.Or could the District, H&S and Circle sections be worked on independently?
So the standing wait is eliminated by going slower in the first place - genius!There are features such as coasting ("gentler" ATO running) that can be used to make sure the trains arrive at desired times/slots (eg for crossing moves in Aldgate Area) The Signalling control system system (which now has a much better overview of the service) can have Train regulation facilities to dynamically recommend/adjust the above.
I know this comment is tongue-in-cheek, but on a serious note it does take more energy to get a train moving from a complete stop than to keep it going at a slower speed (static vs dynamic friction). And in addition, as everyone will be aware from being in traffic jams on the road, there are inevitable delays associated with getting a queue of stopped vehicles moving (as each has to wait for the one in front to actually start moving before setting off), and its much better if everyone just drives more slowly but keeps moving!So the standing wait is eliminated by going slower in the first place - genius!![]()
I know this comment is tongue-in-cheek, but on a serious note it does take more energy to get a train moving from a complete stop than to keep it going at a slower speed (static vs dynamic friction). And in addition, as everyone will be aware from being in traffic jams on the road, there are inevitable delays associated with getting a queue of stopped vehicles moving (as each has to wait for the one in front to actually start moving before setting off), and its much better if everyone just drives more slowly but keeps moving!
If a train is running out of turn, isn't this something that should at least have been flagged to the signaller at the time it was first decided to route them out of turn? That is surely the point at which the signaller should be thinking about the consequences.Wha often ends up happening in practice is one of these things
* the system slows down one train that is running early, but doesn’t take into account that the train behind is running late and is out-of-turn. So the late train gets even later. Either the signaller spots this and makes an intervention (sometimes too late to be effective), or it gets missed and you get a lumpy service.
I can see the logic for delaying a train arriving early at a junction where it is going to be held for a conflict, but not just to delay it arriving early at a station. Arriving early at a station is a benefit to those passengers getting off, and as you say can also help if the station stop is longer than normal.* the “early” train is regulated so that it doesn’t arrive early, then there’s a delay at the station for whatever reason (perhaps a wheelchair being loaded), and it then ends up departing late.
If the signaller does a reformation, it is surely up to the signaller to think of the consequences.* the signaller does a reformation for whatever reason which then results in the system working towards the timings for the reformed train. So you can then end up with something ridiculous like the train running at 20mph until someone notices and makes an adjustment.
If a train is running out of turn, isn't this something that should at least have been flagged to the signaller at the time it was first decided to route them out of turn? That is surely the point at which the signaller should be thinking about the consequences.
If the signaller does a reformation, it is surely up to the signaller to think of the consequences.
You seem to be saying that many of the problems are down to the signallers not managing the system properly?
This weekend was apparently a "backup" for the 4LM 4 day testing closure about a month ago and not necessary (required testing for that stage completed?) so has been used for track work ( grinding /tamping) which should improve ride smoothness.No - the closure this weekend is for rail grinding, unrelated to 4LM works
Thanks for the infoNo - the closure this weekend is for rail grinding, unrelated to 4LM works
SMA10/12 still on for commissioning 13/14 June 2026.TfL Board Papers for the March 18 Meeting have 2 Milestone Dates for the Four lines Modernisation:
SMA 10 and SMA 12 Go-Live target 30th September, SMA 9 Go-Live target 30th November.
Is that one of the roads they use to turn trains round short of Wimbledon when there is serious late running?One consequence is that Parsons Green 21Rd will be unavailable after that weekend until January 2027, due to ‘limited clearance issues’.
Is the noted speed increase the only improvement?SMA10/12 commissioning 13-14 June 2026:
Earl's Court Control Centre decommissioned; District Line movements Fulham Broadway-NR boundary (including Parsons Green sidings) transferred to Hammersmith Service Control Centre. Wimbledon ASCC will no longer control movements NR boundary-East Putney platforms.
Piccadilly Line Control Room will no longer control District Line train movements Barons Court-Stamford Brook.
Tripcock testers at Earl's Court platforms 1-4 will be decommissioned, equipment bagged. Speed of trains passing through lifted from 12mph to 19mph.
New tripcock testers were installed at Turnham Green in April 2026.
Parsons Green 21 siding, out of use until early-2027.
District Line 13 June; entire Line suspended until approx-10.00. After approx-10.00 service Embankment-Upminster every 5min only.
after approx-13.00 Upminster-Richmond every 10min, Upminster-Ealing every 10min, Edgware Road-Parsons Green every 10min, Tower Hill-Parsons Green every 10min. (*trains will run empty Barons Court-Stamford Brook and Fulham Bdwy-Parsons Green.
District Line 14 June; until approx-09.30 Upminster-Richmond every 10min, Upminster-Ealing every 10min, Edgware Road-Parsons Green every 10min (*trains will run empty Barons Court-Stamford Brook and Fulham Bdwy-Parsons Green.
After approx-09.30 Upminster-Richmond every 10min, Upminster-Ealing every 10min, Edgware Road-Parsons Green every 10min, Tower Hill-Parsons Green every 10min. (*trains will run empty Barons Court-Stamford Brook and Fulham Bdwy-Parsons Green.
After approx-21.30 Upminster-Richmond every 10min, Upminster-Ealing every 10min, Edgware Road-Parsons Green every 10min, Tower Hill-Earl's Court/Olympia every 10min. (*trains will run empty Barons Court-Stamford Brook and Fulham Bdwy-Parsons Green.
Circle Line 13 June; entire Line suspended until approx-10.00. After approx-10.00 Hammersmith-Tower Hill pfm.2 every 10min. After approx-13.00 normal Saturday service resumes.
H&City Line 13 June; entire Line suspended until approx-10.00. After approx-10.00 normal Saturday service resumes.
MET Line 13 June; until approx-10.00 no service Harrow-on-the-Hill-Aldgate. After approx-10.00 normal Saturday service resumes.
Piccadilly Line 13 June; until approx-13.00 no service Hyde Park Corner-Acton Town. After approx-13.00 normal Saturday service resumes but trains will stop additionally at Turnham Green.
Piccadilly Line 14 June; trains will stop additionally at Turnham Green.
Not sure how many trains you have been on to appreciate the non-stopping speed improvement?Is the noted speed increase the only improvement?
Does the above stuff about East Putney effectively mean LU signalling extends onto the NR maintained infrastructure, ie there’s an overlap between the track maintenance boundary and the signalling boundary? Or have I misunderstood?
The track maintenance boundary is down at Wimbledon. The entire branch track, plus civils and associated assets (eg. fencing) is maintained by LU.Does the above stuff about East Putney effectively mean LU signalling extends onto the NR maintained infrastructure, ie there’s an overlap between the track maintenance boundary and the signalling boundary? Or have I misunderstood?
When is the next opportunity for the commissioning?SMA10/12 commissioning postponed.
Unknown what impact this will have on services this weekend.
TfL status email just recieved confirms the works are postponed and says they will work to run as much of a service as possible.Unknown what impact this will have on services this weekend.
Planned works affecting the Circle, District, Hammersmith & City and Metropolitan lines on Saturday 13 June have been postponed due to last minute technical issues.
We are working hard to restore as much service as possible but unfortunately, we will not be able to restore a full service in the morning.
What's the reason? The email I got mentioned "last minute technical issues"SMA10/12 commissioning postponed.
Unknown what impact this will have on services this weekend.
What's the reason? The email I got mentioned "last minute technical issues"