The implication of any delay in announcing the grant of an Order seems to be that the Chord itself cannot be completed on time. What does that do to plans for franchises, timetable-changes, etc?
Greenfield is almost always easier.
In what respect do you refer to in your quote above, as the "almost" word seems to imply a certain reservation.
NR doesn't seem to have got up to speed on any of the electrification projects (except possibly in Scotland).
Greenfield is not really a blank canvas despite a lack of pre-existing obstacles, as there might not be sufficient information on the structural viability below the grass and additional work might be needed to join your greenfield site up to anything useful.
There appears to be some confusion over the use of the word "Greenfield" here...
I think the original post was referring to 'greenfield sites' for building, rather than the Greater Manchester village of the same name.
Wasn't aware of that station...
(Checks map)
That's quite far away from Ordsall.![]()
Neil Palmer said:20/02/2015 at 18:08
There were previous complaints of losing rail access to the museum. Looking at the top picture in the article you wonder why they didn't include a flat crossing like at Newark to maintain access?
Or indeed as the Welsh Highland have constructed to cross the NR Line in North Wales.
This would then form a 6 track approach into Victoria from the West, the lower two being those that could terminate into a new set of bays around the former Exchange site, accessed by the long platform 3, and possibly a new entrance on the other side for the stopping services to Liverpool.
Has the new plan for the use of the former Exchange Station site for buildings now been scrapped?
There is no chance or any west facing bays at Vic. The exchange side is now totally dug up with a multistory and towerblock being built on it!
One still wonders why NR or whoever decides what is to be done doesn't just do a proper job in the area in the first place.
Take the line from Deansgate and put a double slip (term?) in at low level, with the lines from Victoria passing through a three way divergence, then loop round the land that is still empty above the Ordstall Lane area that people claim is to be developed for so many years but I've seen nothing. One can then curve at a much more gentle curve and pass through Salford Central in the current platform areas.
The Victoria to Liverpool route can be raised up on a viaduct on the current viaduct (a'la' DLR) to pass over the whole new Ordsall Lane Jcn area for Vic - Liverpool services.
This would then form a 6 track approach into Victoria from the West, the lower two being those that could terminate into a new set of bays around the former Exchange site, accessed by the long platform 3, and possibly a new entrance on the other side for the stopping services to Liverpool.
Drawing to come as this is hard to explain.
Well that solves that idea
It was discounted by Hub long ago because the trains you want to terminate in these platforms have to cross the layout from Crescent and the 8-car provision puts the connection too far west to be a practial design.
But what if in the future trains from Piccadilly via Ordsall Chord needed to terminate at Vic without blocking through platforms? This can never happen now. Where is future proofing for growth? So short sighted as always.
Please make it to scale in 3D with acceptable CWR radii and 1 in 100 gradients between Ordsall and Central, but keeping the functionality at Ordsall Lane Junction - you'll soon find out why your idea doesn't work.
There is no chance or any west facing bays at Vic. The exchange side is now totally dug up with a multistory and towerblock being built on it!
It isn't that simple. The Chord will be very busy, heavily curved, canted (I think) and at a different level. Even if you raised the MOSI connection and convinced everyone that two or possibly four square diamonds in the main line were a good idea, you still have a problem with the cant ...
... and then you might never be able to get a path out, though it is highly likely that it would have to be used only under a possession, for signalling reasons.
How much is the height difference between the MOSI and Ordsall Chord? Can the Chord not just pass (bridge) over or is it a metter of insufficient height?