Eesh, just looked at the files, an 18mb consultation response!!??
There was no need to tack on a 30 page appendix of graphic heavy consultation leaflet evidence to a 400 page text document, they could easily have been in a seperate appendix file.
Design and Access statement, modifications from the initial consultation proposal to mitigate MOSI concerns.
1. Existing track and contaminated ballast of the 'Pineapple Line' will be removed and replaced with appropiate materials to allow a walking route associated with the Ordsall Chord pedestrian arrangements.
2. On completion of the Ordsall Chord the area covered by the Grade 1 and Grade 2 listed railway and bridges will be reinstated in such a way as to allow a walking route through the Grade 1 listed station building.
3. The condition of the arches below the viaduct will be assessed with a view to repointing the brickwork and giving the space over to MOSI use.
4. The existing tarmacadam surface on the Liverpool Road access ramp upto rail level will be replaced with flagstones if required.
5. Network Rail will make every effort to provide 60 car parking spaces for MOSI staff during construction, the roads will be well signposted to assist the 65% of museum vistors that arrive by car.
(suggests also that there may be other 'benefits' to MOSI from Network Rail that dont require planning permission)
Few more Mitgation commitments in the Environmental Statement.
6. Sections of railway within the site will be reinstated to maintain a working steam exhibition which will demonstrate to the public a working freight operation.
7. Network Rail will fund a survey of the travelling crane operation in order to support the working freight demonstration
8. The future use of arches north of Water Street will be considered for Network Rail or MOSI
So does that indicate that while the passenger railway ride will disapear a new freight exhibit with a moving crane will be created?