I know the Midland Pullman went that way of course and was supposed to be the fastest timing (not sure if that was ever or simply at that point in time), but weren't many services still running on the WCML during the electrification works simply they were slowed down by various p'way slacks and consequent extensions to journey time with recovery margins for engineering?
Manchester services went via the Midland (service doubled from 2-hourly to hourly).
Birmingham/Wolverhampton services went via High Wycombe (a similar doubling).
Other services (which included then-normal trains to places like Workington/Perth/Colne/Birkenhead) ran sort-of normally, but subject to diversions.
Stoke had one train a day (Euston-Stockport).
I suppose there might have been about 4tph long distance out of Euston on average, plus sleepers/postal/parcels at night.
Some trains ended up at St Pancras (via Nuneaton/Wigston), Marylebone (via Calvert) or even Kensington Olympia at times, particularly sleepers.
Unlike the more recent WCRM, there was no attempt to keep weekday trains to a normal or decent schedule.
You would randomly be sent via Northampton, Bescot, or slow line all the way, any day of the week.
I think the resignalling phase was worse than the wiring, with cycles of detonators/stop for pilot/crawl through the area with hand signalling/drop pilot/speed up again.
And all behind lumbering class 40s with 13+ on, rarely exceeding 75mph before the next bout of disruption.
Steam was still around too, you might get a Duchess on some services.
I think there were something like 45 minutes of recovery time in the schedules south of Crewe.
This was for the period 1961-66, with things speeding up a bit when the wires reached Nuneaton.
Places like Stoke and Coventry had almost a decade without decent services to/from London.
Once the electrification was complete, the hammers fell on the diversion routes which had done so much to keep services going.
It spelt the end for the GW through the West Midlands, the Midland via Matlock, and the whole of the GC route beyond Aylesbury.