So, given all of these announcements, once all the new stock has arrived, what will run where and roughly what amount of 185's will be released?
2018 - Liverpool-Newcastle and Manchester Airport-Newcastle will go over to 68+LHCS, replacing a tranche of 185s.
2018 - Manchester-Preston-Glasgow goes over to CAF EMUs, replacing 10x350s (running via Bolton by then).
2018 - Liverpool-Preston-Glasgow starts with CAF EMUs (new service).
2019 - AT300s start running Liverpool-Newcastle (to be extended to Edinburgh Dec 2019) and Manchester Airport-Newcastle.
This allows 68+LHCS to run Liverpool-Scarborough and Manchester Airport-Middlesbrough, which releases another tranche of 185s.
All this is going to be a gradual transition, taking maybe a year for each route.
So it will be into 2020 before all this is in place.
Key infrastructure changes:
Dec 2017 - Ordsall Chord is planned to be in service
Dec 2019 - Extra platforms at Manchester Piccadilly and remodelling at Oxford Road (dependent on planning approval and construction timetable).
It's not clear what legs AT300s will work electrically, but potentially Liverpool/Airport-Stalybridge and York-Newcastle-Edinburgh.
There may be some additional interim rolling stock to boost capacity before the new trains show up.
185s should be released from late 2018 into 2020, and will be staying on Manchester-Hull and TP South, and will run the Leeds stoppers via Guide Bridge.
That's my take on the plans, anyway.