In the most recent Mersey Tart blog, he has spotted a map at Aigburth station with Liverpool Baltic on it.

The map has been printed with Liverpool Baltic station already on it... the sticker covering it keeps being ripped off,



IMG_9769.JPG
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Kite159

Veteran Member
Joined
27 Jan 2014
Messages
22,755
Location
West of Andover
In the most recent Mersey Tart blog, he has spotted a map at Aigburth station with Liverpool Baltic on it.





IMG_9769.JPG
It makes sense as the signage would have been replaced when Headbolt Lane opened to include references to Baltic but covered over, saves replacing the signs again if that station ever gets built
 

Phillipimo

Member
Joined
5 Jan 2013
Messages
236
Location
Portsmouth
Planning application submitted for Golborne station.
Basic 2 platform station on the WCML fast lines with a footbridge with lifts linking the station to both sides of the town.
To be served by a 1tph service between Wigan and Manchester Victoria (And beyond).

Application A/24/98015/MAJOR on the Wigan planning portal.

Subject to local authority and government approvals, work could start on site in 2026 – and the new station open in 2027.
TfGM is working with Wigan Council and Greater Manchester Combined Authority on the £32 million station plans.

Attached is a pdf 3D visual.
 

Attachments

  • document-22544012.pdf
    2.4 MB · Views: 37
Last edited:

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
I have updated Newsham to 'early 2025', January is bing rumoured.

The following have been allocated codes:
Beaulieu Park [BPA]
Balgray [BGY]
Liverpool Baltic [LVB]
Surrey Canal [SCE] (is listed on Realtime Trains as Surrey Canal Road)
Wellington (Somerset) [WLQ]
 

Phillipimo

Member
Joined
5 Jan 2013
Messages
236
Location
Portsmouth
Liverpool Baltic planning application is now available to view.


24F/2999

Includes significant public realm improvements by completely remodelling nearby roads to be more friendly.
A lot of work has gone into fire safety and compliance which will go someway towards the cost (Some features still not compliant and work ongoing according to fire strategy document).
One regular and one evacuation lift and stairs on each platform, in addition to stairs and escalators.
Designed to be futureproof to future ridership.
Mentions of projected passenger numbers of 4 million per year rising to possible 8m.

The station thread is locked so posting here.
 

AndyHudds

Member
Joined
17 Jun 2012
Messages
601

A video on the new Elland Station, although not an official one, shows some nice renders and plans and some context to the area. Not often you get a video on a proposed new station. Seemingly a contractor has been appointed.
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
I have moved Okehampton Interchange into the top part of the #1 table. According to the linked discussion work has commenced on site.
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
If the original table at the start is still being updated I'd add that Hairmyres station is now opening in May 2025, not December.
Is there a source for that please?

UPDATE

Gave the search engine a big nudge, found a couple of links, station due to open on completion of a 16 week engineering works block.
 
Last edited:

s55823ewj

Member
Joined
28 Jun 2024
Messages
40
Location
Greater Glasgow Region
Probably the 18th of May, as that's when the works finish up. The existing Hairmyres station will close permanently on the 25th of January. https://www.networkrailmediacentre....-for-16-week-gbp-140m-electrification-upgrade

East Kilbride-Glasgow line to close for 16-week £140m electrification upgrade
From January 2025, engineers will be working around-the-clock for 16-weeks to deliver major engineering works as part of the project to electrify the railway between East Kilbride and Glasgow.

The project, which is being delivered by Network Rail and is part of a Scottish Government investment in the line, will help to decarbonise rail services as well as improve reliability for passengers.

Once complete, in December 2025, the investment in the line will see:

  • Electrification of the railway from Glasgow to East Kilbride
  • A new station at East Kilbride
  • A new station with two platforms and accessible footbridge at Hairmyres
  • A new footbridge at Busby station
  • Improved access at Giffnock, with a new accessible footbridge
  • A new station entrance at Clarkston.
To help deliver these vital improvements, from Saturday 25 January until Sunday 18 May no trains will run on the line between East Kilbride and Thornliebank stations while work is carried out to the track, bridges and overhead line equipment along the route.

This critical period in the electrification project will also see 22km of new overhead power cables installed and the lengthening of the double-track between East Kilbride and Hairmyres.

The existing track will also be lowered at locations near Busby, Clarkston and Giffnock stations so that overhead line equipment can be accommodated under some bridges on the route.

Gerry McQuade, Network Rail capital delivery director, said: “This programme of extended engineering works is a critical point in the delivery of the electrification of the East Kilbride line.

“Closing the railway is never an easy decision, but the engineering work taking place over these 16 weeks can only be done when no trains are running. This approach allows the completion of these major works in the most efficient, fastest way.

“We do appreciate the impact this will have both on those living closest to the line and to our passengers. We hope that by advising people three-months ahead of the work starting, this raises awareness and allows people the time to consider alternative travel arrangements.”

Mark Ilderton, ScotRail service delivery director, said: “The works being carried out by Network Rail are absolutely critical in the latest phase of the project to electrify the railway on the East Kilbride line.

“Unfortunately, during the 16-week closure, we will be unable to operate trains to and from East Kilbride, and an alternate transport plan will help to make sure customers are still able to travel.

“In the coming weeks, we will communicate the plan through all our customer information channels, including where replacement buses will operate, and the other routes available for customers.”

Damian Briody, Transport Scotland’s head of rail projects and technical services, said: “This announcement marks the build-up to the latest phase of progress on the East Kilbride electrification project.

“Whilst any disruption to passengers is unwelcome, we acknowledge the careful consideration which has gone into delivering the significant improvement works taking place during the closure.

“It is welcome that Network Rail and ScotRail have listened to passengers in planning these works and that they will continue to work closely together to ensure these passengers can make informed journey planning choices.”

Throughout the works, no train services will run to East Kilbride. To help minimise disruption for passengers, a replacement bus service will be in place during this period.

At the same time as the 16-weeks of work finishes, in May 2025, the new Hairmyres station is scheduled to open to the public. The overall electrification project will be completed in late 2025.

Information on the bus replacement service will be available in the coming weeks and customers advised to check at www.scotrail.co.uk or via www.nationalrail.co.uk when planning their journeys over this period.

For the latest information and updates on our works, follow on X (Twitter) @NetworkRailScot or visit www.scotlandsrailway.com
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
As per posts in the linked thread, Newsham has been suggested as being complete in February. More vague dates for the remaining Northumberland Line stations are also given - all in 2025.
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,093
Location
West Wiltshire
Looks like something is about to happen with Charfield, which got planning permission in 2023, as local council are holding a drop in session 15:00 - 19:00 today ahead of enabling works starting next month

February to July 2025​


Enabling works for construction of the new station will start in February and continue to July 2025. This includes the following activities:
  • realignment of Little Bristol Lane to allow for future station construction
  • preparation of the proposed station forecourt as a temporary compound for rail works
  • improving track drainage and realignment of trackside cabling
  • vegetation clearance
The station proposals obtained planning permission in March 2023. The general arrangement drawing shows planning approval.
View our factsheets for further information about the enabling works, traffic management and granted planning permissions.
You can view the most up-to-date general frequently asked questions (FAQs) and our construction FAQs.

 
Last edited:

Severnia333

Member
Joined
20 Jan 2025
Messages
63
Location
Bristol
Looks like something is about to happen with Charfield, which got planning permission in 2023, as local council are holding a drop in session 15:00 - 19:00 today ahead of enabling works starting next month



Good to see progress being made. Apparently there was talk of Charfield happening just after Cam and Dursley opened/reopened in the 90s!
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
Cardiff Parkway has received planning permission. Refer to the linked thread or read all about it here on the BBC News site.

Plans to build a new mainline railway station in eastern Cardiff have been approved by Wales' first minister.
Eluned Morgan confirmed she was granting planning permission in a letter sent to Cardiff Parkway Developments.

== Doublepost prevention - post automatically merged: ==

Just noticed that I hadn't amended Henbury to 'planning application submitted', it was submitted some time ago!
 
Last edited:

JRT

Member
Joined
11 Nov 2020
Messages
385
Location
Bradford
A BBC report enigmatically describes how Rotherham Council are potentially seeking to buy land to facilitate a new main station in the town
BBC News - Rotherham Council plans to buy land for new train station
Rotherham Gateway.
No indication of the actual location.
 
Last edited:

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
Rotherham Gateway.
No indication of the actual location.
Appears to be off Forge Way, based on the canal basin in the background of the second picture in the recent BBC article. Also appears to be much the same distance from the centre of town as the old Rotherham Masborough - taking into account actual routes on the ground rather than the flying crow.

== Doublepost prevention - post automatically merged: ==

Hopefully good news on the Portishead scheme. Mentioned in the previously linked to speculative thread and a new NON SPECULATION thread here. The latter now linked to from #1. Potential opening dates revised from 2026 to 2027.
 
Last edited:

rikufryderyk

New Member
Joined
1 Mar 2024
Messages
3
Location
London
Hi, could you please consider adding Beam Park on to the list? Below i have pasted the link to IanVisit’s article about the new planning application being submitted:
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
Hi, could you please consider adding Beam Park on to the list? Below i have pasted the link to IanVisit’s article about the new planning application being submitted:
It's on my close watch list along with Cheadle (Stockport) and Waterbeach. Beam Park was due to open in May 2022, Cheadle in 2025 and Waterbeach in 2021.
 

rikufryderyk

New Member
Joined
1 Mar 2024
Messages
3
Location
London
Two days ago, multiple news reports came out online that the opening date for Newsham has been pushed back to Mid-March, with a specific day TBC. Please update the table, as people who haven’t heard about this update will be in anticipation of going to the opening at the end of February, which is no longer viable.

Below I have pasted in the links to two different articles announcing the news. ️
Photographs attached are my own work.

Northumberland Gazette:


Chronicle Live:
https://www.chroniclelive.co.uk/news/north-east-news/northumberland-line-station-to-open-31056715
 

Attachments

  • IMG_6709.png
    IMG_6709.png
    1.6 MB · Views: 43
  • IMG_6710.png
    IMG_6710.png
    1.6 MB · Views: 43

windjabbers

Member
Joined
5 Jan 2014
Messages
95
Location
Cambridge
Various reports in the media that Cambridge South opening will now be in 'early 2026'

NR have updated their website to say that:-


Not clear why the new date but have herd they need another Xmas close down to do more work in the signalling. But dont know if that is the case.

BW DC
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
Two days ago, multiple news reports came out online that the opening date for Newsham has been pushed back to Mid-March, with a specific day TBC. Please update the table, as people who haven’t heard about this update will be in anticipation of going to the opening at the end of February, which is no longer viable.

Below I have pasted in the links to two different articles announcing the news. ️
Photographs attached are my own work.

Northumberland Gazette:


Chronicle Live:
https://www.chroniclelive.co.uk/news/north-east-news/northumberland-line-station-to-open-31056715
The first link says February!
Anyone anticipating going to an opening based upon "A completion date of February is now being suggested", needs to await official statements before making irreversible arrangements, as the date has slipped a couple of times already. Which is true of most of the stations in the table. Some considerably.

Various reports in the media that Cambridge South opening will now be in 'early 2026'
Both updated.
 

Baxenden Bank

Established Member
Joined
23 Oct 2013
Messages
4,744
As I will be unable to update the table tomorrow, I have jumped the gun with Newsham. First public train is listed as 0612 (0600 from Ashington to Newcastle) tomorrow morning (Monday 17th).
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,979
Location
London
Haven't seen anything posted in here yet about Brabazon? Did a search and also for MetroWest but couldn't find it (mods can delete if I've missed something!)


Work has started on a new train station in the city which is set to open in autumn 2026. Dan Norris, the Mayor of the West of England, visited the Brabazon development on Friday (March 14) as work started.

Brabazon is the new neighbourhood for Bristol being built on the historic former Filton Airfield. The new station will serve the new urban community, and the planned 19,500-capacity YTL Arena Bristol.

Once complete, potentially as soon as autumn 2026, the station should connect Brabazon to Bristol Temple Meads in less than 15 minutes. BAM, which constructed Ashley Down station - which opened last year - is building the station.
 