They‘ve already tried that…Yes the irony that to solve Bradford’s economy is to knock the centre down
They‘ve already tried that…Yes the irony that to solve Bradford’s economy is to knock the centre down
Which one is that? They were both there (having been moved slightly north) when I drove to/from BDQ today.Slightly off topic, but can anyone let me know where 01507 has gone to please, or has it been scrapped?
Off topic but can i ask What 01507 is?Slightly off topic, but can anyone let me know where 01507 has gone to please, or has it been scrapped?
Not off topic - there have been for many years two diesel shunters stored at Crossley Evans, one of which is 01507.Off topic but can i ask What 01507 is?
Presume you mean preservation?I've been informed by a reliable source that Venom is destined for presentation. I'm afraid I can't give any further details!
Correct on both counts!Presume you mean preservation?
It's left the site now.
I am having some difficulty understanding this. The traditional mantra is that electric trains need less maintenance than diesel. Logically more electric trains should reduce the need for maintenance facilities. Yet here we have the TPU (which electrifies York to Manchester) paying for an increase in such facilities. I also seem to recall that one of the benefits of shifting the main tracks at Neville Hill in a southerly direction was to allow the facilities at the Depot to be extended. Similarly the comment re Neville Hill not being centrally located is strange when most of the electric fleet probably runs into Leeds at least once per day.The application says: “It has been a long-term ambition of the rail industry to seek improved depot and traincare facilities for the electric fleet serving the Wharfedale and Airedale lines, as the facility currently at Neville Hill is near capacity and is not located centrally to serve the routes.
The East end of Leeds is highly congested. Using valuable paths just to shift in an empty unit is a poor use.I am having some difficulty understanding this. The traditional mantra is that electric trains need less maintenance than diesel. Logically more electric trains should reduce the need for maintenance facilities. Yet here we have the TPU (which electrifies York to Manchester) paying for an increase in such facilities. I also seem to recall that one of the benefits of shifting the main tracks at Neville Hill in a southerly direction was to allow the facilities at the Depot to be extended. Similarly the comment re Neville Hill not being centrally located is strange when most of the electric fleet probably runs into Leeds at least once per day.
I am having some difficulty understanding this. The traditional mantra is that electric trains need less maintenance than diesel. Logically more electric trains should reduce the need for maintenance facilities. Yet here we have the TPU (which electrifies York to Manchester) paying for an increase in such facilities. I also seem to recall that one of the benefits of shifting the main tracks at Neville Hill in a southerly direction was to allow the facilities at the Depot to be extended. Similarly the comment re Neville Hill not being centrally located is strange when most of the electric fleet probably runs into Leeds at least once per day.
Scheduled maintenance is still regularly required as well as stabling, CET emptying, external washing, interior cleaning, unscheduled repairs etc….I am having some difficulty understanding this. The traditional mantra is that electric trains need less maintenance than diesel. Logically more electric trains should reduce the need for maintenance facilities. Yet here we have the TPU (which electrifies York to Manchester) paying for an increase in such facilities. I also seem to recall that one of the benefits of shifting the main tracks at Neville Hill in a southerly direction was to allow the facilities at the Depot to be extended. Similarly the comment re Neville Hill not being centrally located is strange when most of the electric fleet probably runs into Leeds at least once per day.
Looking at Realtime trains for the morning peak (assumed as 0730 to 0900), then the only EMU ECS working is at 0859 to Neville Hill. Hardly worth spending £100m to remove.The East end of Leeds is highly congested. Using valuable paths just to shift in an empty unit is a poor use.
Neville Hill will be shut for a considerable period due to TRU works. Obviously the replacement diesel stabling points at Holbeck and Cobra Sidings will be useless for EMUs. If you're going to build stabling sidings under OHLE with CET and maintenance capabilities you might as well use it as a proper depot.
Which then frees up space at Neville Hill (which is currently full) to service the remaining diesel and incoming bimode fleet.
I think you'll find @Neptune knows what he's talking about.Looking at Realtime trains for the morning peak (assumed as 0730 to 0900), then the only EMU ECS working is at 0859 to Neville Hill. Hardly worth spending £100m to remove. As for the closure of Neville Hill "for a considerable period due to TRU works" that is a nonsense itself. I cant recall any such closures ever being necessary elsewhere. But happy to be corrected.
It’s not just being built to remove that train though. East Leeds is congested all day and especially so at the start and the end of the day when there are multiple moves on and off depot mixed in with passenger services.Looking at Realtime trains for the morning peak (assumed as 0730 to 0900), then the only EMU ECS working is at 0859 to Neville Hill. Hardly worth spending £100m to remove.
It is not nonsense and just because you’ve never recalled it ever being necessary elsewhere before doesn’t mean it isn’t happening.As for the closure of Neville Hill "for a considerable period due to TRU works" that is a nonsense itself. I cant recall any such closures ever being necessary elsewhere. But happy to be corrected.
Undoubtedly could change, though it might also mean the civil engineers agreeing to less maintenance time.Probably should be in the speculation or timetable threads, but...
Wondering if after the new depot is open, the Sunday timetable could be altered to provide an earlier Shipley – Ilkley service for early DalesBus connections? (at present we have to wait for the train from Ilkley to go back). Or maybe starting trains from Bradford Forster Square rather than waiting for trains to come in from Leeds, Ilkley and Skipton?
Only the 2 Doncaster units don’t pass through Shipley each day but they are only on that route for 2 days at a time before rotating back onto the NW triangle. It will also mean that the units that currently stable at Bradford and possibly even Ilkley will be able to stable more securely at Shipley TCC instead. The current Bradford - Carnforth 158 will be able to stable there too saving another path from Leeds - Bradford.
More than 8 will be able to be stabled there. Bear in mind the 331’s will be 3 car units (for instance 2 x 331’s will fit on a shed road).Looking at the planning application it looks like 8 EMUs will fit at Shipley depot at any given time, given that there usually seem to be something between 6-10 East EMUs not in traffic each day, and most of those are presumably at Neville Hill with a couple at Skipton, then surely the stabling at Bradford and Ilkley will need to continue as currently?
More than 8 will be able to be stabled there. Bear in mind the 331’s will be 3 car units (for instance 2 x 331’s will fit on a shed road).
The BDQ units will almost certainly stable on the depot whilst the Ilkley units could, although if they remain stabled at Ilkley for operational reasons that would also make sense.
Less units will be sat around through the day when the Bradford - Ilkley/Skipton services go back up to 2tph.
(Bradford City Council planning application 23/03622/SCR)Planning application said:a maintenance hall, bulk storage area, two-storey office and welfare block, this approximately 148.5 m x 41.9 m building will comprise a steel-framed portal building and will extend 14.55 m (to top of parapet) above the four sets of track contained within it (each track being able to accommodate a four-car EMU)
Plus the stabling sidings across both sides of the site. A depot is more than just the shed building.Which is reflected in measurements shown on the drawings suggesting a track length of 106m within the shed, which makes for 4x 26m, and certainly not 6x 23m.
Plus the stabling sidings across both sides of the site. A depot is more than just the shed building.
Sorry I misread that one as I was thinking of the stabling road lengths at the time.I was replying to your statement that "for instance 2 x 331’s will fit on a shed road" - the planning application clearly states otherwise.
I’ve just been looking at the plans on our system and the plan is for 12 units to stable overnight at Shipley TCC (6x3 car, 6x4 car). There is room for more if required but it’s unnecessary the vast majority of the time as Skipton BRCS will contain the bulk of the fleet overnight. 2 will stay at Ilkley, 2 at Leeds but none will go to Neville Hill at all in the current plan.The four stabling roads at the Shipley end of the site appear to be very similar length, theres an underframe wash road and thats it, so even at maximum capacity I can't see how more than 9x 3 or 4 car units can possibly fit on the site.
Sorry I misread that one as I was thinking of the stabling road lengths at the time.
I’ve just been looking at the plans on our system and the plan is for 12 units to stable overnight at Shipley TCC (6x3 car, 6x4 car). There is room for more if required but it’s unnecessary the vast majority of the time as Skipton BRCS will contain the bulk of the fleet overnight. 2 will stay at Ilkley, 2 at Leeds but none will go to Neville Hill at all in the current plan.
Units are planned on Shipley TCC through the day for maintenance swaps.
Hope this helps clear a few questions up.
I mean that clarifies what you meant, but I still don't see how 12 units can be stabled on this site.
Attached has 8 red lines for shed/stabling, 1 yellow for the underframe clean which gives you really a surge capacity of 9...
Also, seems a bit odd that none go to Neville Hill at all, given Shipley isn't going to have a wheel lathe.
Can each siding and the shed only hold one unit each or can they hold two each?
Hmm.
(Bradford City Council planning application 23/03622/SCR)
Which is reflected in measurements shown on the drawings suggesting a track length of 106m within the shed, which makes for 4x 26m, and certainly not 6x 23m.
Well that’s the official unit plan for when it opens. I trust the person implicitly who has done the detailed work on this (since the start of the planning for this around 3 years ago).I mean that clarifies what you meant, but I still don't see how 12 units can be stabled on this site.
Attached has 8 red lines for shed/stabling, 1 yellow for the underframe clean which gives you really a surge capacity of 9...
They will go there for the wheel lathe but it isn’t in the LTP plan as you don’t need a unit up there every night (waste of a path most likely lost due to lack of regular use). It will be a VSTP move, most likely planned around one of the maintenance spares.Also, seems a bit odd that none go to Neville Hill at all, given Shipley isn't going to have a wheel lathe.