A report scheduled to be published by MPs tomorrow (Tuesday, October 29) is expected to warn that the £3.55 billion Thameslink rail project might not be delivered on time.
The House of Commons’ public accounts committee questioned the Department for Transport’s handling of the north-south cross-London project which is due for completion in 2018.
The committee's report is expected to point out that the DfT's award of a £1.6 billion private finance contract for new trains for Thameslink was delayed by more than three years and that despite the need for the Thameslink upgrade being identified as far back as 1989, passengers will now be waiting until the early 2020s to get the benefit.
It is understood the report will criticise the department's approach to letting the franchise to operate the new service because it was not joined up with the rest of the Thameslink programme, highlighting weaknesses in the department's programme management capability.
The committee is concerned about the department's skills and capacity to complete Thameslink by 2018, alongside its ambitious wider portfolio of programmes and projects.
Not sure if there's anything there that's not already obvious, but it's always interesting when it's officially pointed out for the statutory record. I would expect the report to be available on Parliament's website tomorrow - I will post a link if able, or someone else might kindly do so if they find it first.
The House of Commons’ public accounts committee questioned the Department for Transport’s handling of the north-south cross-London project which is due for completion in 2018.
The committee's report is expected to point out that the DfT's award of a £1.6 billion private finance contract for new trains for Thameslink was delayed by more than three years and that despite the need for the Thameslink upgrade being identified as far back as 1989, passengers will now be waiting until the early 2020s to get the benefit.
It is understood the report will criticise the department's approach to letting the franchise to operate the new service because it was not joined up with the rest of the Thameslink programme, highlighting weaknesses in the department's programme management capability.
The committee is concerned about the department's skills and capacity to complete Thameslink by 2018, alongside its ambitious wider portfolio of programmes and projects.
Not sure if there's anything there that's not already obvious, but it's always interesting when it's officially pointed out for the statutory record. I would expect the report to be available on Parliament's website tomorrow - I will post a link if able, or someone else might kindly do so if they find it first.