When is the MML electrification due to start and when will the cables arrive at Leicester
I'm new to this thread. Does anyone please have a link where I can find the spec for the MML electrification works (e.g. bridge alterations, timescales etc) as the project develops and progresses?
Is there an official Network Rail update site as well as this thread?
Thanks in advance for any help.
You can find the milestones on page 50 of the CP5 Enhancements Delivery Plan (quarterly update just published: http://www.networkrail.co.uk/publications/delivery-plans/control-period-5/cp5-delivery-plan/ ).