There aren't any because they can't be accommodated in the daytime timetable - because there is no Up passing loop.There arent any 60moh freights from Nuneaton to MML south, except overnight.
There aren't any because they can't be accommodated in the daytime timetable - because there is no Up passing loop.There arent any 60moh freights from Nuneaton to MML south, except overnight.
Half hourly Bedford to Leeds train. Is that a serious proposal.
There aren't any because they can't be accommodated in the daytime timetable - because there is no Up passing loop.
What happened to the wonder train that was going to install a cable run every night on thr GWML?Frankly is the only way to slash costs per km is to go back to the ECML and space the masts out as far as possible and secondly close the line north of Leicester whilst the OLE is constructed and effectively build it as a 'greenfield' site for several months and route passengers to WCML / ECML and no bus replacement.
Frankly is the only way to slash costs per km is to go back to the ECML and space the masts out as far as possible
secondly close the line north of Leicester whilst the OLE is constructed and effectively build it as a 'greenfield' site for several months
There are standard contract models where if the contract comes in under budget the contractor and client share the gain, and if it goes over they share the pain. If done properly this should incentivise both parties to work together for the lowest total cost. I'm not an expert on NR contracting but I believe they do use something of this sort.It's that kind of saving which NR should be aiming to price into their contracts at the tender stage by inviting tenders which don't unnecessarily restrict the contractor to having to work inefficiently. Easy to say, more difficult to do, if you are NR and are hide bound by track access agreements and process dogma.
Didn't notice any enabling works north of Wigston so presumably the piling team has been all but disbanded.
Yes and where costs can be reduced and the benefit shared it does incentivise cost reduction.There are standard contract models where if the contract comes in under budget the contractor and client share the gain, and if it goes over they share the pain.
Brilliant, many thanks for posting. So clear to see the progress and the sketchy bits. Not far for completion.A cab ride between Bedford and Leicester which looks fairly recent has just appeared on YouTube.
Almost all the piling and most masts look to be in along with a significant amount of overhead as far as Wigston.
Didn't notice any enabling works north of Wigston so presumably the piling team has been all but disbanded.
K
See
Some piling skills are very railway specific. Such as not piling through buried signsl cables. We saw what happened on the GWML when non-railway piling teams got involved ....The ‘piling team’ are generally doing piling in non railway environments as well, so theyll still be workign snd will retain their experience.
Precisely. Most of the costs issues seem to me to derive from the Treasury procurement rules, and a lack of appreciation that it is client behaviour and practice that needs to change to drive down costs on your supply chain.would not save costs which are are priced-in at the tender stage because the tender documents are unnecessarily restrictive on the contractor being able to work efficiently.
Some piling skills are very railway specific. Such as not piling through buried signsl cables. We saw what happened on the GWML when non-railway piling teams got involved ....
Some piling skills are very railway specific. Such as not piling through buried signsl cables. We saw what happened on the GWML when non-railway piling teams got involved ....
it is client behaviour and practice that needs to change to drive down costs on your supply chain
When I say Piling I incuded all the rail specific plant as well as there trained operators. Criminal if its lost and plant and expertise has to be reactivated later at huge cost.The ‘piling team’ are generally doing piling in non railway environments as well, so theyll still be workign snd will retain their experience.
Im old enough to remember when the ECML electrifcation reached, but stopped at Hatfield. However BR civil engineer managed to keep the piling going until the full ECML was eventually authorised. Strange to see mile after mile of mast foundations.
I thought the piling method was introduced on the ECML electrification scheme? When did the concrete foundations reduce? North of Peterborough?I guess you mean Hitchin. Piling on the ECML north of there was done up to Huntingdon on BRs own authority, based on a nod and a wink from DfT that electrification to Leeds and Newcastle was going to be authorised.
All concrete foundations, of course.
Yes - IIRC it was Stoke Tunnel northwards that reaped the rewards of piling, and then only for single-track masts (e.g. pairs of STCs). Headspans, in the main, remained 'planted'.I thought the piling method was introduced on the ECML electrification scheme? When did the concrete foundations reduce? North of Peterborough?
The bit I should have added is that it wasn't cabled 2 weeks ago, so progress.Harborough
Modern Railways for November has an article on EMR on pp. 56-61. On page 58 it says EMR and NR are working to determine the locations of balises.We were told balaises were not going to be used due to the changing swap over locations. There will just be reminder boards for us drivers to adhere to.
harboroughfm.co.uk
Only SPC3/34 (next to Braybrooke ATFS) I believe, but that's due to start imminently.So, are there any bridges left (south of Wigston South junction) which still require replacement or raising, and where the work hasn't yet started?
Thanks, very informative!Only SPC3/34 (next to Braybrooke ATFS) I believe, but that's due to start imminently.
SPC3 bridges 42, 35, 28E, 28, 25, 24, 19 (done way back), 18, 10, 9, 8 (done way back), 7, 3 and possibly 2 have all had work to modify/demolish the bridge completed or underway.
SPC3 bridges 40, 39, 28D and 15 have all had track lowering completed or are in the midst of track lowering works.
SPC3 bridges 39, 38, 16B and possibly more are using surge arresters.