MML Electrification: progress updates

Status
Not open for further replies.

Helvellyn

Established Member
Joined
28 Aug 2009
Messages
2,567
Not seen it mentioned but at the weekend the old platform 4 brickwork at Wellingborough was demolished and removed. Not sure if extra clearance is required to reinstate the fourth track or it is just easier to build the platform from scratch.

Also looks like a site office and compound for the Wellingborough works is going up beyond where the reinstated platform 4 will be.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Not seen it mentioned but at the weekend the old platform 4 brickwork at Wellingborough was demolished and removed. Not sure if extra clearance is required to reinstate the fourth track or it is just easier to build the platform from scratch.
It’s highly likely it is being moved back. The planning drawings mentioned a few weeks ago showed P4 is completely new construction. There’s also a fairly significant amount of widening out to realigned tracks on the south end of P3 as well.
 
Joined
24 Jun 2014
Messages
442
Location
Derby
It would be a massive spend, and potentially conflicting with proposed Leicester remodelling work to add signal overlaps and perhaps a new platform - though none of that is approved yet as far as I know.

I guess it depends upon what is meant by "massive".

In post 2914, I mentioned that Ian Walmsley had reported that, at the recent IMechE Conference, it had been reported that the Cardiff Intersection Bridge solution could be used at Leicester; in the RIA Electrification Cost Challenge report, it records that these works cost less than GBP1m.
 
Joined
24 Jun 2014
Messages
442
Location
Derby
Is it correct to presume that the OHLE being installed on the MML will be able to cope with 2x5-car EMUs running at 125mph on a regular basis, irrespective of the daily frequency of the multiple EMU unit trains using the route?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Is it correct to presume that the OHLE being installed on the MML will be able to cope with 2x5-car EMUs running at 125mph on a regular basis, irrespective of the daily frequency of the multiple EMU unit trains using the route?
Yes. From what I can see, the new OLE is independently tensioned catenary & contact wires. The existing Mk3b OLE south of Bedford uses equalising plates (i.e. 1 set of balance weights tensions both wires), which means both are at the same tension (11kN for Mk3b). The new UKMS wiring uses 12kN in the catenary, and 15kN in the contact - the same as on the WCML (where UK1 equipment is installed) and on the GWML.

The greater tension means that multiple pantographs will be able to run without a significant risk of the front pan's carbon-contact interface oscillation compromising the rear pan's current collection.
The lower tension south of Bedford means that 125mph operation with multiple pans is out of the question unless they are sufficiently spaced - this was also partly the reason why 12-car 319s were restricted to 75mph (while 700s, 377s and 387s could do 100mph). The 319s were mainly fitted with heavier Stone Faiveley AMBR pans, which caused more oscillation than the lighter, aerofoil-equipped Brecknell Willis HS pans fitted to the Electrostars & Desiro Citys.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Rumours are circulating that Wellingborough Up Yard is due to receive some upgrades as part of the electrification work. These, allegedly, are:
  • A new connection to the Slow Lines at the northern end of the yard
  • Electrification of the first two (i.e. westernmost) sidings in the yard, which will be used by Network Rail
I hope this means that electrically hauled freight might make an appearance on the MML! It does, of course, play into the hands of bi-modal locos, as the main freight routes from the MML south of Wellingborough are unelectrified (Marston Vale, Dudding Hill, the Tottenham Curve (to the GOBLIN)).
 

Roast Veg

Established Member
Joined
28 Oct 2016
Messages
2,319
What are the major flows into and out of that yard? Do they pass through enough electrified railway to make it worthwhile?
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
What are the major flows into and out of that yard? Do they pass through enough electrified railway to make it worthwhile?
GBRf currently operate all flows from the yard, which mainly come from quarries (Cliffe Hill, Mountsorrel, Rylstone, Tunstead, Whatley), thence supplying railheads at Elstow (Bedford), Luton Crescent Rd, Radlett Lafarge, Cricklewood, Ferme Park (Hornsey - ECML) and Acton Yard (GWML).

Currently, the lack of wires on those routes mentioned above would make an AC-only loco pointless, but the non-wired distances are probably short enough to warrant a bi-modal loco hauling freight over those routes in the short term, as well as shunting within the terminals if OLE can't be accommodated.

However, NR may have different plans for the yard if they take it over - what they are remains to be seen.
 

InTheEastMids

Established Member
Joined
31 Jan 2016
Messages
1,382
Electrification of the first two (i.e. westernmost) sidings in the yard, which will be used by Network Rail

This is consistent with my observation in Post 2806 that additional hardware has been attached to the outside of (I think) the 4-track portals here.
 

philjo

Established Member
Joined
9 Jun 2009
Messages
3,010
Presumably this could also be used for planned or emergency stabling/turnback for EMUs - either the Corby services or Thameslink.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,599
Location
Nottingham
I can't see anything being done for freight, so I assume it's stabling for overnights or emergencies. I believe the yard is currently in a temporary state and what is now its headshunt becomes the Up Slow.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
NR orginally planned to wire the link between the T&H and MML but it was shelved on gounds of cost.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,229
Before Kettering. The costs of the T&H job went up.
It seems to have been pulled during 2015. You’ll possibly recall it was discussed a few times in the Goblin wiring thread, eventually I found that it’s last official mention was in the Jan 2015 CP5 delivery plan, then it had disappeared when the plans restarted after the Hendy review.
 

westcoaster

Established Member
Joined
4 Dec 2006
Messages
4,490
Location
DTOS A or B
Back from a week's holiday here is the current state of play at Wellingborough.
 

Attachments

  • IMG_20190803_135516.jpg
    IMG_20190803_135516.jpg
    3.2 MB · Views: 135

Jozhua

Established Member
Joined
6 Jan 2019
Messages
1,891
Hi all! Found a petition asking for government to electrify all UK rail:

https://petition.parliament.uk/petitions/259903

Wether it is a realistic goal, would be worth signing to show people we care about rail electrification on both the MML and in the rest of the country.
 
Last edited:

DogsOnTrains

Member
Joined
6 Aug 2019
Messages
5
It’s highly likely it is being moved back. The planning drawings mentioned a few weeks ago showed P4 is completely new construction. There’s also a fairly significant amount of widening out to realigned tracks on the south end of P3 as well.
How long will the new platforms 3+4 be at Wellingborough? 12 car train long?
 

londonmidland

Established Member
Joined
22 Dec 2009
Messages
2,347
Location
Leicester
I can’t give a specific location but between Kettering and Wellingborough, the signals in the way of the fourth track are being replaced with new overhead signal gantries, which are being erected.
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
I can’t give a specific location but between Kettering and Wellingborough, the signals in the way of the fourth track are being replaced with new overhead signal gantries, which are being erected.
Would that be Harrowden Junction, by any chance? There's definitely an extant gantry that needs a-choppin'.
 

WymoWanderer

Member
Joined
18 Dec 2017
Messages
115
Location
Between BDM and WEL
Been away for a couple of weeks and a bit of progress around Wymington, North Bedfordshire.
  • Wires are now up on the fast lines as far as I could see to the South of the village. To the North of the village the wires end where the deviation starts.
  • New signal / telecom cabinets installed on the fast line
  • Local power distribution lines running over the fast lines have been removed and presumably buried
  • Notification of temporary closure of the footbridge over the slow lines just at the Northern entrance of the Sharnbrook tunnel. Work is schedled for 2 months for waterproofing and parapet height raising.
  • New works depot located near said footbridge
Now disused power line mast following cable burial.
y4m7g_cOxQn_1PIGSezJz85X9KsyE7popogRUR3x2-7MyvUKWUNRZT5BBB9pTNW8jNTnMGmVdLbootmnKeJav8-HYTpNoyikz_q2EYbbnQTxue59vBPUxg86xiQwWv3x2RC5MFUB6jvz9IyYsYaXzLTOxstgaGV5mVdYwqOcO2Lrg8vrkb1J_ZPHp-jC8hnZqOIpVcKlyCON6LoXcNfQZy48w


New comms / signalling cabinets
y4mZMgocL-f8d1mQElZ3ZVHB-ko7cU0E2strF0lsseF4PMQaeYYArmdyoqCjj-yi2iNd0t-PMjbnSCKRnffbeK47qIY8qbx68Sp05xysHSGyixWwhwtms4tOgpZSwKSQtxwsPbgjjI-h-prTgFba10wMNaIiJ1QdtLHrMK7GwegcrMXX6a_ZCMaAEZQ6tjbdU8fAdq1T_ZH_iHLUI89PxFvNQ


Start of OHLE wires on fast lines
y4mY2HPuefIO4AwHuGVV-JEqgnd2-z0Ra8e03TRYVyGmTQTr2oYG-XeBpcHsmVy34sKUu7tHUBbQzjfEv4JX05tFZhbkB8g--Cm7BCiuUSv0Tm8oW6Dix7VRsNpm_-mLxXWnTibsJoLbjPuEJmQQmd86nMulsxftNKROd3wSMeQwXg4TIcPWG472-GxEZ4Xao82HcWgzkPsKBtkIGjlb8WD6A

y4mHpxChkQ0afR21lolPzeUJoAfGda-Xz5uKOKpkrdbn9w_HyTw68kP_-rVVvKbRno6FVTaPM7uwKAynvmA1up7LFxfkmUgf3f9GMlG46lXosJz9dFSl2T1sl0GzwtnB0tIolNpevd3RPwabGx0D9stab7zUyhqCc7RUfb_a8Cwu1yQ3HgVdMMOC-diLpVb1DVY1ZGmqXihxtL-UpBpKIRYUg


Close up of OHLE wires
y4mVVhMm93XtkmNmXlqdTKZ4-t1qGLk_26uOOnoRYw4_KsOojLj01t7vziWAFhq1fbUiCXkHq_OiXAgTA4HVE3sfT-VMihB78bMG5iEvRXv0EXnnSiVhnk1_wx0tBqe3OWAFqqd2xmcXYLwqURZuqKcbPRgc3ggtlA-735WKvRoghRvzINXaB-x-ZFSWOMrJP6UgPe0UgCkxmN2jGAkybRObQ


Fast lines looking South toward Souldrop
y4mQNutRqBl37OH1_O8MAASfHkNwA_cwExqNeJM2j0CxdGL2-oG5a2WBJ4JJFPDSnAGXvBQJ16Krsup-tF9gpNkPt8YmSLVDU38oTfRsPN9O23LBOZwmCzMWZgEzDPzRD-8jjJbmuYcsixAfVgp32dY1_Ayn5iimDsdZxdKMBtl9_32cdzauDaHfoQrq2eve1uUsIfn5NUfw2gGf4N7YPkJRw


Fast lines looking North toward Irchester
y4mI16W6xH7spTg3Y_d54OWx3IuBfmMSDHzKcA6uwmcXWvyylVQ7IzWFyf-XpAN9YRfailc6_pYCXKPjG-bW5KIT4LH9WMig-Ac6dMhxPdE8KiScg7AJwuEcYOPOx17qNzCeR0drrjkOUUPKZUAJYrfdr7CnXMSs2AwoE7dlzYEn_vtpkFqxIpxqPaDXwMjhMF6R8ll8CHtvYaQWeiddV-LMw


Footbridge temporary closure
y4m8cZZLlmEhu_2k8QMliTynWhMoKKNE_oN1JvDNfSHsEvzhyo1Itnf2PyeI4pxg2Fxzq5LVh4QDnaMfyvL89R6K6BRc7QyXuLj2nMG2qeAkTB3wH_tgIw01SDyb8n4jjCtu3qO-ZKHqn1dXeXFAyMykqkBrAjz5NqTGzaoT4HP18AeCYE2Pf6hW7uGaCI_X5_lXuByYbTPDWDIU5uH7fga2A

y4mXpWwWQHYxKTR_tJQFDfxF4bKCvexFut6scD1jNX6u0Qc8mnm5Abxgz5g10YlqrCIGsYUli8yDsHrCdRLKcK_P4Ci1-DRZlAqYPOtTyJaUVZhxuSP6_5MwQhiMOCeE2v9NU0CQWpCPno-xeWm08GEfVG1Hs2x0xsqmQaRjvN5U1qdFuTzvFhWqoGSgLQzOgj4BYEOlYiee3VWQfm6UlBhgw

y4mOQr7DW_fPiPTy-kK7mv0ZTlLs1qvi8en3bieS2mEZzBHwmhpwK-vr_MFahbiFwJyCTpP4TjefTyz8LYmhhvHRAusd_ZCoReUefHXVCcPA5xYhY1gKzxWKMHb0yd14G-gNCK6K4RTUtcdK8bZBueZHG7Cd7978jgFz7lKMg53Ss_YXfexZl_53aZpuNoKNzOwC5eUYSCPQasX5R_CUtX5jg


More OHLE
y4mN33z09OpBKqweowFXlbEEOTEQLWvIw8H1uYvLMtHhBn9a597nRrlFauOK3ZxArlalHGD-wkrbqZUJUnQR7gRMw7JHAel977dxyjLfO8E4lNThPH-8dT-vLDQjTaZ070dWq1wtHgGzhnrvL-oAMK8WdoJAog-rgS9XL1O3x-XbKKRlaX_F84yZjGlFEgIfJwOF2qR6GL2Yphdo9WbVSut4A

y4mtqtCu72YmmYA61DL3nN3RrCYiuh3TdVOx9k1lS6PWjCcPQiZIzEROF2wL0PjPKVpRnLl3kTc2KMl-9mmXJXKKEihm_hoUqTOeEL9iMEjaIQTFy-dxYuiqYbcnXXO8PB5PJztVGWsP5_8XgH3I-wHIw79A2tAEWkUDTGq_SQ99_Wazw8URgVUgZeBZrQqtFnryhHCWYkQhYFAHNI3KY0GNg

y4mfoTCM4ZHvOUhNW4fRZ_T4t8P2iKM6_GthrfyJ5m_Y_Qqwq6IdeEK_xPzzX8bNS2reyuB2DtecF3iRkQ4LNNefTriRc7RQDkJqdASdwTbPwTRpQCtb3EabgG6w8IpKaxTrLX2as__1ot0MREKmlr8r4YPi04r5ll07bLk1wy6KtBdDrgqjOGm48W5BCZ2nZBlc3yXH-cWIX8OSn3dB92b8A
 

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Been away for a couple of weeks and a bit of progress around Wymington, North Bedfordshire.
  • Wires are now up on the fast lines as far as I could see to the South of the village. To the North of the village the wires end where the deviation starts.
  • New signal / telecom cabinets installed on the fast line
  • Local power distribution lines running over the fast lines have been removed and presumably buried
  • Notification of temporary closure of the footbridge over the slow lines just at the Northern entrance of the Sharnbrook tunnel. Work is schedled for 2 months for waterproofing and parapet height raising.
  • New works depot located near said footbridge
Now disused power line mast following cable burial.
y4m7g_cOxQn_1PIGSezJz85X9KsyE7popogRUR3x2-7MyvUKWUNRZT5BBB9pTNW8jNTnMGmVdLbootmnKeJav8-HYTpNoyikz_q2EYbbnQTxue59vBPUxg86xiQwWv3x2RC5MFUB6jvz9IyYsYaXzLTOxstgaGV5mVdYwqOcO2Lrg8vrkb1J_ZPHp-jC8hnZqOIpVcKlyCON6LoXcNfQZy48w


New comms / signalling cabinets
y4mZMgocL-f8d1mQElZ3ZVHB-ko7cU0E2strF0lsseF4PMQaeYYArmdyoqCjj-yi2iNd0t-PMjbnSCKRnffbeK47qIY8qbx68Sp05xysHSGyixWwhwtms4tOgpZSwKSQtxwsPbgjjI-h-prTgFba10wMNaIiJ1QdtLHrMK7GwegcrMXX6a_ZCMaAEZQ6tjbdU8fAdq1T_ZH_iHLUI89PxFvNQ


Start of OHLE wires on fast lines
y4mY2HPuefIO4AwHuGVV-JEqgnd2-z0Ra8e03TRYVyGmTQTr2oYG-XeBpcHsmVy34sKUu7tHUBbQzjfEv4JX05tFZhbkB8g--Cm7BCiuUSv0Tm8oW6Dix7VRsNpm_-mLxXWnTibsJoLbjPuEJmQQmd86nMulsxftNKROd3wSMeQwXg4TIcPWG472-GxEZ4Xao82HcWgzkPsKBtkIGjlb8WD6A

y4mHpxChkQ0afR21lolPzeUJoAfGda-Xz5uKOKpkrdbn9w_HyTw68kP_-rVVvKbRno6FVTaPM7uwKAynvmA1up7LFxfkmUgf3f9GMlG46lXosJz9dFSl2T1sl0GzwtnB0tIolNpevd3RPwabGx0D9stab7zUyhqCc7RUfb_a8Cwu1yQ3HgVdMMOC-diLpVb1DVY1ZGmqXihxtL-UpBpKIRYUg


Close up of OHLE wires
y4mVVhMm93XtkmNmXlqdTKZ4-t1qGLk_26uOOnoRYw4_KsOojLj01t7vziWAFhq1fbUiCXkHq_OiXAgTA4HVE3sfT-VMihB78bMG5iEvRXv0EXnnSiVhnk1_wx0tBqe3OWAFqqd2xmcXYLwqURZuqKcbPRgc3ggtlA-735WKvRoghRvzINXaB-x-ZFSWOMrJP6UgPe0UgCkxmN2jGAkybRObQ


Fast lines looking South toward Souldrop
y4mQNutRqBl37OH1_O8MAASfHkNwA_cwExqNeJM2j0CxdGL2-oG5a2WBJ4JJFPDSnAGXvBQJ16Krsup-tF9gpNkPt8YmSLVDU38oTfRsPN9O23LBOZwmCzMWZgEzDPzRD-8jjJbmuYcsixAfVgp32dY1_Ayn5iimDsdZxdKMBtl9_32cdzauDaHfoQrq2eve1uUsIfn5NUfw2gGf4N7YPkJRw


Fast lines looking North toward Irchester
y4mI16W6xH7spTg3Y_d54OWx3IuBfmMSDHzKcA6uwmcXWvyylVQ7IzWFyf-XpAN9YRfailc6_pYCXKPjG-bW5KIT4LH9WMig-Ac6dMhxPdE8KiScg7AJwuEcYOPOx17qNzCeR0drrjkOUUPKZUAJYrfdr7CnXMSs2AwoE7dlzYEn_vtpkFqxIpxqPaDXwMjhMF6R8ll8CHtvYaQWeiddV-LMw


Footbridge temporary closure
y4m8cZZLlmEhu_2k8QMliTynWhMoKKNE_oN1JvDNfSHsEvzhyo1Itnf2PyeI4pxg2Fxzq5LVh4QDnaMfyvL89R6K6BRc7QyXuLj2nMG2qeAkTB3wH_tgIw01SDyb8n4jjCtu3qO-ZKHqn1dXeXFAyMykqkBrAjz5NqTGzaoT4HP18AeCYE2Pf6hW7uGaCI_X5_lXuByYbTPDWDIU5uH7fga2A

y4mXpWwWQHYxKTR_tJQFDfxF4bKCvexFut6scD1jNX6u0Qc8mnm5Abxgz5g10YlqrCIGsYUli8yDsHrCdRLKcK_P4Ci1-DRZlAqYPOtTyJaUVZhxuSP6_5MwQhiMOCeE2v9NU0CQWpCPno-xeWm08GEfVG1Hs2x0xsqmQaRjvN5U1qdFuTzvFhWqoGSgLQzOgj4BYEOlYiee3VWQfm6UlBhgw

y4mOQr7DW_fPiPTy-kK7mv0ZTlLs1qvi8en3bieS2mEZzBHwmhpwK-vr_MFahbiFwJyCTpP4TjefTyz8LYmhhvHRAusd_ZCoReUefHXVCcPA5xYhY1gKzxWKMHb0yd14G-gNCK6K4RTUtcdK8bZBueZHG7Cd7978jgFz7lKMg53Ss_YXfexZl_53aZpuNoKNzOwC5eUYSCPQasX5R_CUtX5jg


More OHLE
y4mN33z09OpBKqweowFXlbEEOTEQLWvIw8H1uYvLMtHhBn9a597nRrlFauOK3ZxArlalHGD-wkrbqZUJUnQR7gRMw7JHAel977dxyjLfO8E4lNThPH-8dT-vLDQjTaZ070dWq1wtHgGzhnrvL-oAMK8WdoJAog-rgS9XL1O3x-XbKKRlaX_F84yZjGlFEgIfJwOF2qR6GL2Yphdo9WbVSut4A

y4mtqtCu72YmmYA61DL3nN3RrCYiuh3TdVOx9k1lS6PWjCcPQiZIzEROF2wL0PjPKVpRnLl3kTc2KMl-9mmXJXKKEihm_hoUqTOeEL9iMEjaIQTFy-dxYuiqYbcnXXO8PB5PJztVGWsP5_8XgH3I-wHIw79A2tAEWkUDTGq_SQ99_Wazw8URgVUgZeBZrQqtFnryhHCWYkQhYFAHNI3KY0GNg

y4mfoTCM4ZHvOUhNW4fRZ_T4t8P2iKM6_GthrfyJ5m_Y_Qqwq6IdeEK_xPzzX8bNS2reyuB2DtecF3iRkQ4LNNefTriRc7RQDkJqdASdwTbPwTRpQCtb3EabgG6w8IpKaxTrLX2as__1ot0MREKmlr8r4YPi04r5ll07bLk1wy6KtBdDrgqjOGm48W5BCZ2nZBlc3yXH-cWIX8OSn3dB92b8A
Lovely set of shots there! Looks like the Fasts are now wired all the way from Souldrop to the Irchester end of the Deviation.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,593
Fully aware of this fact, but some pressure on the DaFT to actually fufill some electrification projects would be useful!

You misunderstand how government works.

Firstly, they won’t even be aware of it until it has 10k signatures.
Secondly, even if it gets past that number, it will land on the desk of a middling official in the DfT who will very quickly provide a short reply explaining why such a proposal is completely impractical and unaffordable, and that the Department carefully considers cases for electrification put to it.

It would cause precisely no pressure on the DfT at all.
 
Status