I have a bit of a health and safety question here.

As I understand that the wiring in place between Wavertree to Earlestown is now apparently live, does there have to be signs 'Danger Overhead Live Wires ' in place near public footbridges?

There is a footbridge just a couple of minutes walk from my home and on the other side of the tracks, there is a primary school and many of the children there use the footbridge.

Just saying.

Probably not if it is a non-station overbridge; there are several bridges over the ECML near where I live and none of them have notices aimed at bridge users.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Ploughman

Established Member
Joined
15 Jan 2010
Messages
3,099
Location
Near where the 3 ridings meet
Signs need to be in place before the system is powered up.

Normal practice, as stated earlier, for all staff to treat OHLE as live at all times unless you hold or have seen the signed piece of paper that tells you it is turned off.
 

mcnw35282

Member
Joined
27 May 2014
Messages
242
Location
Sin Tellins
Does the wiring need to be continuous? I thought the buildings at edge hill and Huyton quarry were feeder stations? They'll energise in sections won't they?
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,906
Location
North
Following very welcome reports (and a photo) re Sankey Viaduct and Rainhill I have added ten pictures here:

https://www.flickr.com/photos/127646831@N03/sets/72157648494725811/

Thank you for more interesting photos of portals. I would have thought removing shrubbery from the stonework of Sankey Viaduct would be high on the priority list?

Headspan wires on the ECML were strung complete between trains. At Rainhill the top headspan wire only has been strung. I wonder why?
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Thank you for more interesting photos of portals. I would have thought removing shrubbery from the stonework of Sankey Viaduct would be high on the priority list?

Headspan wires on the ECML were strung complete between trains. At Rainhill the top headspan wire only has been strung. I wonder why?

I'm glad you find them interesting.

I have been told that Planning Consent has been given for the whole viaduct to be shotblasted and a contract has been let. The end product should be spectacular, ie rid of nearly two centuries of muck, graffiti and vegetation.

I use the term 'shotblasted' as a layman, it might be sandblasted, gritblasted or wiped with a feather duster, possibly even down rather than up.

I'm afraid I don't understand what you mean by 'strung complete between trains.'

Kind regards

Dave
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,906
Location
North
I'm glad you find them interesting.

I have been told that Planning Consent has been given for the whole viaduct to be shotblasted and a contract has been let. The end product should be spectacular, ie rid of nearly two centuries of muck, graffiti and vegetation.

I use the term 'shotblasted' as a layman, it might be sandblasted, gritblasted or wiped with a feather duster, possibly even down rather than up.

I'm afraid I don't understand what you mean by 'strung complete between trains.'

Kind regards

Dave

Yes it was a bit ambiguous.

The complete headspan, usually for four tracks, was built up as one unit with the correct offset for that pair of uprights, on a warehouse floor then rolled up like a swiss roll and transported to site. Here it was unrolled and strung between the uprights in between passing trains without a possession in literally a matter of minutes.

The return cable had already been fitted on the outside of the uprights before the headspans were fitted. The catenary and contact wires were fitted later.

I hope it is clearer this time?
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Yes it was a bit ambiguous.

The complete headspan, usually for four tracks, was built up as one unit with the correct offset for that pair of uprights, on a warehouse floor then rolled up like a swiss roll and transported to site. Here it was unrolled and strung between the uprights in between passing trains without a possession in literally a matter of minutes.

The return cable had already been fitted on the outside of the uprights before the headspans were fitted. The catenary and contact wires were fitted later.

I hope it is clearer this time?

Thank you for this full and interesting description.

I don't know why they've gone about it differently at Rainhill, but would wonder if it is to do with things you mention such as:

assembling in a factory and transporting: excellent when you are doing loads and loads over a long section of railway, maybe not when there are four only?

slipping it in in between trains without a possession: would modern standards allow this above a well used station?

Cheers

Dave
 

budge

Member
Joined
23 Sep 2014
Messages
20
In response to the earlier question about the lines being energised.
Indeed all the residents between Lea Green and St Helens Junction received a letter stating the wires would be live as from 31/12/14.

Working in a different industry from rail but nonetheless an industry that does adhere to H&S guidelines. One would always assume a power line is on unless not only a piece of paper tells you it's off but also it is tested as off.

From my own perspective if they say the lines are on ...they're on!:)




Hi All
Just some updated information (although this may be common knowledge to others on this forum) from Network Rail
My home backs on to the Manchester / Liverpool Railway and just received a letter stating that the section (Ref Bootle Branch Jn to Earlstown East Jn, DSE ,1m 78ch to 14m 75ch)
Liverpool - Newton-le - Willows(Chat Moss route) will be energised as of 31st December 2014

25Kv 50hz

FYI

Regards...


Budge
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Yes it was a bit ambiguous.

The complete headspan, usually for four tracks, was built up as one unit with the correct offset for that pair of uprights, on a warehouse floor then rolled up like a swiss roll and transported to site. Here it was unrolled and strung between the uprights in between passing trains without a possession in literally a matter of minutes.

The return cable had already been fitted on the outside of the uprights before the headspans were fitted. The catenary and contact wires were fitted later.

Was there any procedure for making the signalling system treat the section as occupied?
 

UrbanWorld

Member
Joined
26 Dec 2014
Messages
106
This may sound daft to those in the know, is the Liverpool to Wigan line being electrified now and scheduled to be operational at the same time as the Liverpool to Manchester line?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
This may sound daft to those in the know, is the Liverpool to Wigan line being electrified now and scheduled to be operational at the same time as the Liverpool to Manchester line?

Yes, it's 80% finished - all of it was supposed to be done by last month.
Just the bit in the middle through St Helens Central to do, and connecting up at both ends to the main lines.
For a while it was further advanced than the main line, but has evidently been de-prioritised in the last few weeks.
I should think it will take maybe a month to finish after the main line.
 

DJH1971

Established Member
Joined
10 Jun 2012
Messages
1,751
Location
St Helens, Merseyside
Yes, it's 80% finished - all of it was supposed to be done by last month.
Just the bit in the middle through St Helens Central to do, and connecting up at both ends to the main lines.
For a while it was further advanced than the main line, but has evidently been de-prioritised in the last few weeks.
I should think it will take maybe a month to finish after the main line.

It's the Carr Mill Viaduct holding things up a bit.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
and scheduled to be operational at the same time as the Liverpool to Manchester line?

It was, until the recent admission that the December 2014 schedule would not be met. There is no official published revised opening date for either line, but February has been talked about for Liverpool to Earlestown. The Wigan line may be a bit later. Similarly Ordsall Lane junction to Manchester Victoria.

Incidentally, I wonder what will happen to the supposedly quarterly updates to the CP5 Enhancements Delivery Plan, given that the last one was six weeks late? It might be simpler to skip one, but will the ORR allow that?
 
Last edited:

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
It's the Carr Mill Viaduct holding things up a bit.

There's about 2-3 miles of wiring to do Ravenhead-Carr Mill, and the first half mile of the branch from Huyton Jn.
Carr Mill viaduct has its masts up and just needs a couple of booms added for it to be wirable.
Then there's the one missing mast south of Carr Mill, and the final few hundred yards up to Springs Branch to wire (with a few masts needed at the junction as well).
 
Last edited:

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,906
Location
North
Was there any procedure for making the signalling system treat the section as occupied?

Not that I could see as a lineside observer but there must have been to allow all four tracks to be obstructed for up to ten minutes.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I don't think there are many places on current electrification projects where headspans will be used. Rainhill station is the only one I've heard of. So it probably isn't worthwhile to go to great lengths to achieve efficient ways of putting them up, as it was on WCML north or ECML where there were hundreds of them.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
I don't think there are many places on current electrification projects where headspans will be used. Rainhill station is the only one I've heard of. So it probably isn't worthwhile to go to great lengths to achieve efficient ways of putting them up, as it was on WCML north or ECML where there were hundreds of them.

There are a couple approaching Manchester Victoria (over 4+ tracks).
 

UrbanWorld

Member
Joined
26 Dec 2014
Messages
106
Yes, it's 80% finished - all of it was supposed to be done by last month.
Just the bit in the middle through St Helens Central to do, and connecting up at both ends to the main lines.
For a while it was further advanced than the main line, but has evidently been de-prioritised in the last few weeks.
I should think it will take maybe a month to finish after the main line.
Thanks. So the Liverpool to Wigan and Liverpool to Manchester lines should be full operational on electric in March - we hope. But with 4 electric train sets?
 
Last edited:

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,263
Not that I could see as a lineside observer but there must have been to allow all four tracks to be obstructed for up to ten minutes.

Peter Semmens' book on the electrification of the ECML explains that on long sections with automatic signals there were local switches added so that the wiring teams could set the relevant signals to red while the prefabricated headspans were run across the tracks. The basic idea was that they'd connect everything to the mast on one side first while trains ran, and as and when the timetable allowed they'd protect themselves for just enough time to pull the other end of the headspan round over the tracks, and then raise it and tension it using ropes and pulleys.

Just 'speed read' the relevant chapter on how the wires were put up, and it strikes me that many procedures would not pass a modern risk assessment.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
For reasons I don't really understand, the first wires up through Rainhill were the catenary wires (running through from completed wiring either side).
Normally the mast wiring (earth/return, AT) goes up first, then the over-track wires.

The ECML approach gets you completed headspans, but you still have to wire lengthways when you have enough spans for a full wire run.
Rainhill is only a 4-headspan run in a long run of portals/cantilevers.

They also have a habit of putting the catenary/contact wires up without connecting them to the registration arms (which sometimes are not even there!).
There are quite long stretches of wiring with only temporary connections to masts to keep them up.
So "wires up" has to be qualified a bit.
Earlestown for instance at the moment is a curious mix of finished, half-finished and missing wiring.
And all done in variously dark, wet and frosty conditions. Impressive.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,906
Location
North
Peter Semmens' book on the electrification of the ECML explains that on long sections with automatic signals there were local switches added so that the wiring teams could set the relevant signals to red while the prefabricated headspans were run across the tracks. The basic idea was that they'd connect everything to the mast on one side first while trains ran, and as and when the timetable allowed they'd protect themselves for just enough time to pull the other end of the headspan round over the tracks, and then raise it and tension it using ropes and pulleys.

Just 'speed read' the relevant chapter on how the wires were put up, and it strikes me that many procedures would not pass a modern risk assessment.

I watched the headspans being strung on the section between Thirsk and Pilmoor. It was not obvious how the workers were protected from passing trains. I assumed by radio communication but thank you for explaining.
 

8A Rail

Established Member
Joined
6 Dec 2012
Messages
1,351
Location
Mars
Thanks. So the Liverpool to Wigan and Liverpool to Manchester lines should be full operational on electric in March - we hope. But with 4 electric train sets?
The original idea is to have 3 Class 319's on the Liverpool Lime St - Manchester Airport service first and that remains the case. Other NR services will convert in time as and when they receive the other refurbished Class 319's. Patience please.
 

DJH1971

Established Member
Joined
10 Jun 2012
Messages
1,751
Location
St Helens, Merseyside
The original idea is to have 3 Class 319's on the Liverpool Lime St - Manchester Airport service first and that remains the case. Other NR services will convert in time as and when they receive the other refurbished Class 319's. Patience please.

Which should be later this year.
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,215
Location
Bolton
The original idea is to have 3 Class 319's on the Liverpool Lime St - Manchester Airport service first and that remains the case. Other NR services will convert in time as and when they receive the other refurbished Class 319's. Patience please.

Yeah, you don't deserve a usable rail service until an unspecified period of time after the date when changes were promised...
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,904
Location
Mold, Clwyd
What are the stations that would prevent 8 car length trains?

If you are talking between Lime St and Manchester, oddly only Patricroft and Eccles can handle 8-car (20m) trains.
On the Wigan line, only St Helens Central.
Some platforms are on a list for extension, but only up to 6 cars.
They are currently all odd lengths from 4 upwards, with no consistency.
 