Mark Wild, the new CEO of HS2 Ltd, has made some pointed remarks to the Public Accounts Committee of the Commons in a hearing today.
Among them is a claim that HS2 started up the construction too early, and awarded contracts that left much risk with HS2 rather than the contractors.
He said that the project was "out of synchronism" and needed a new baseline programme.
That suggests the whole line might not be ready on the current dates (2029-33).
www.theguardian.com
In other submissions to the committee, it appears that space for more platforms than the six currently specified might be created in the new Euston project, to allow for future growth.
The full PAC hearing can be found on the parliament web site:
Among them is a claim that HS2 started up the construction too early, and awarded contracts that left much risk with HS2 rather than the contractors.
He said that the project was "out of synchronism" and needed a new baseline programme.
That suggests the whole line might not be ready on the current dates (2029-33).
HS2 boss blames failure to control costs on rush to start work
Mark Wild says ‘fundamental reset’ needed, as Department for Transport admits it has no final cost estimate
Speaking at a House of Commons public accounts committee hearing, Wild said HS2 had “systemic and enduring problems”, including contracts that passed the risk on to HS2 Ltd rather than the supply chain, and was still working to plans from 2019 rather than “an assured baseline that can be properly measured against”.
Wild said: “Construction started way too early. The rush to start before mature design consents was really, in retrospect, a mistake.” He added that HS2’s “activities are all out of synchronism – we must form a new baseline programme”.
In other submissions to the committee, it appears that space for more platforms than the six currently specified might be created in the new Euston project, to allow for future growth.