A new video from Cuemaster of the Canterbury Road Vent shaft:
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

27105

Member
Joined
11 May 2023
Messages
15
Location
Mid-Devon
Only just discovered this interesting thread.
Please keep posting reports for the Euston TBM's progress.
 

absolutelymilk

Established Member
Joined
18 Jul 2015
Messages
1,609
Another week's progress (to September 25) shows Madeleine at 4316m to go (+50m), and Karen at 4545m (+137m).
Both TBMs are past Queen's Park station and are advancing under Albert Road just south of the WCML.
Madeleine appears to be about 60m short of the Canterbury Works vent shaft site, maybe the reason for slowing.
Karen, moving at almost 20m/day, is now only 230m behind.
As of 2nd October,
Madeleine now at 4,155m to go (161m, or 23m per day)
Karen now at 4,417m to go (128m, or 18m per day)
 
Last edited:

bib

Member
Joined
15 Nov 2021
Messages
250
Location
East Midlands
Came across a couple of timelapses of the TBMs being assembled and the stub tunnels being excavated, from last summer
 

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,842
Location
Croydon
Thanks for those videos @bib

One thing I noticed more than once is what appears to be a concrete floor being dug up and a (thicker) one being laid in its place. Is this a temporary surface being replaced with stronger to support the assembly of the TBM ?.
 