Indeed. Yes please.Only just discovered this interesting thread.
Please keep posting reports for the Euston TBM's progress.
As of 2nd October,Another week's progress (to September 25) shows Madeleine at 4316m to go (+50m), and Karen at 4545m (+137m).
Both TBMs are past Queen's Park station and are advancing under Albert Road just south of the WCML.
Madeleine appears to be about 60m short of the Canterbury Works vent shaft site, maybe the reason for slowing.
Karen, moving at almost 20m/day, is now only 230m behind.
That puts Madeleine at the Canterbury Road ShaftAs of 2nd October,
Madeleine now at 4,155m to go (161m, or 23m per day)
Karen now at 4,417m to go (128m, or 18m per day)