It's just the formatting - km/h or км/ч is universal, using a division symbol (/).Surely hour isn't an SI unit.
It's just the formatting - km/h or км/ч is universal, using a division symbol (/).Surely hour isn't an SI unit.
So what happens when a future government 30 years down the line announces a new project to connect HS2 to Scotland? You are now building a 400ish mile route and the bottom half is forever constrained because no one futureproofed it.
And what gain is there overall? The longest distance of a potential high speed line in the UK being talked about is London-Scotland, around 400 miles (I don't think anyone's suggesting a direct Plymouth-Aberdeen high speed line). Assume a 320kph top speed over that distance (allowing 40km at each end to accelerate up to speed and decelerate down from that speed). That gives you a journey time of 2h15.
Now take the top speed up to 360kph, and you get a journey time of 2h04 - a saving of a whopping... 11 minutes!
That assumes there are no intermediate stops (which would limit the gains of higher speed running), AND also assumes that a 360kph alignment is feasible through the terrain of North of England and Scottish Borders - which it almost certainly isn't. None of the early-doors concepts to extend HS2 to Scotland were talking about running at those kinds of speeds.
Bear in mind that the purpose of building a high speed line to Scotland would be to transfer the large number of Scotland-London flights to rail. The rule of thumb is that you need to get below a 3 hour rail journey to take out air travel. So saving a few minutes to get the journey down from 2h15 to just over 2 hours doesn't really seem to have much of a point.
It reads like the savings were purely down to only needing to test to 320km/h which reduces the risk of issues cropping up because this is a much more conventional speed for HSR. No mention by the minister of saving on the actual infrastructure itself.Savings on this scale seem surprising given alignment is set and civils so advanced. The biggest area must surely be in replacing slab track with ballasted track where suitable. Not sure your going to save anything on OLE and signalling. So perhaps just a UK gauge version of a Frecciarossa could save time and type testing but Hitachi/Alstom will want compensation.
I fear this, like all the other HS2 estimates, will progressively turn out to be fiction as well. Why will this be accurate when all the other ones have not been? Of course the project leader will tell the minister what they want to hear. Maybe next week, with talk of a reshuffle, it will be a different minister and starting yet again. But when it comes to starting again with contracts which have already been let for infrastructure and rolling stock, you can bet the suppliers have no thoughts about reducing what they quoted for. Variations are only for increasing margins. We can descope what we are supplying, but miraculously it will cost the same. And the areas for saving have already been done (we started 7 years ago) and will have to be scrapped.Mark Wild’s initial and provisional estimate is that a specification at reduced speeds could save in the low billions
I read somewhere that on the TGV the difference in electricity consumption, and so cost, was massive, way more than the revenue benefit. Power to overcome air resistance goes with the cube of speed, hence a doubling of power to get from 100mph to 125mph, which I have also seen quoted.Where's the step change that makes 320kph okay and 360kph not?
I would love to know - no one has ever been keen to talk about the costs in land purchase, historic site clearance and so on of doubling the minimum curve radius (horizontal and vertical), resulting in a railway which cannot go round but must plough through everything (this is a much more crowded landscape than much of France). How many of the things which had to be tunnelled or screened could have been avoided altogether with a slightly lower speed alignment?How much extra did building to a 400km/h alignment cost compared with a 200km/h alignment?
I read somewhere that on the TGV the difference in electricity consumption, and so cost, was massive, way more than the revenue benefit. Power to overcome air resistance goes with the cube of speed, hence a doubling of power to get from 100mph to 125mph, which I have also seen quoted.
I would love to know - no one has ever been keen to talk about the costs in land purchase, historic site clearance and so on of doubling the minimum curve radius (horizontal and vertical), resulting in a railway which cannot go round but must plough through everything (this is a much more crowded landscape than much of France). How many of the things which had to be tunnelled or screened could have been avoided altogether with a slightly lower speed alignment?
Crossrail was dogged with issues but that's all forgotten about now, it's a roaring success.I believe the HS2 project will similarly enter the historical memories, and will still be discussed long after a lot of us on here are no longer around.
No, it will quickly become part of the essential infrastructure of the country and the cost will be forgotten by everyone apart from economists and civil engineers. Why am I so confident about this? Because it's happened time and time and time again. Here, in no particular order, is a non-comprehensive list of some UK engineering projects which massively overran:I am going to make a prediction, the Beeching cuts of the early 60s are still talked about today, over 60 years later. I believe the HS2 project will similarly enter the historical memories, and will still be discussed long after a lot of us on here are no longer around.
I agree, perhaps as much about de-risking opening than saving vast amounts of money. If it is primarily testing, then there's nothing stopping them coming back and doing the work to increase the maximum speeds at some later date. However it is quite easy to look at GB rolling stock introductions and come up with a plausible Armageddon scenario, especially if there's any further delay to completing the infrastructure.It reads like the savings were purely down to only needing to test to 320km/h which reduces the risk of issues cropping up because this is a much more conventional speed for HSR. No mention by the minister of saving on the actual infrastructure itself.
Agree in particular about high speed rail. Although yesterday's news on Tempsford makes EWR a bit harder to cancel.This means that it is very unlikely that future politicians from any of the main parties would sign off on another large rail project in the foreseeable future
I accept that Crossrail overan, badly, but how much scope was removed, i.e. start scope v delivered scope. To me its this that lets HS2 down badly. The curtailment to a London Birmingham route with little propect of the original Manchester and Leeds final desinations being reached in any forseeable timeframe is a real let down.Crossrail was dogged with issues
People move on, because there's no point harping on about a sunken cost - and there are new dafter ideas to complain about.[..]
Projects tend to be remembered for their cost overruns only if they subsequently didn't get utilised - e.g. Concorde, Humber Bridge, Dounreay. HS2 will be heavily used once opened.
Crossrail was dogged with issues but that's all forgotten about now, it's a roaring success.
No, it will quickly become part of the essential infrastructure of the country and the cost will be forgotten by everyone apart from economists and civil engineers. Why am I so confident about this? Because it's happened time and time and time again. Here, in no particular order, is a non-comprehensive list of some UK engineering projects which massively overran:
Channel Tunnel
Jubilee Line Extension
Edinburgh Tram
Wembley Stadium
WCML route modernisation
AGR NPP programme
Heathrow Express
The original 1830s WCML
The original 1840s Great Western ML
Projects tend to be remembered for their cost overruns only if they subsequently didn't get utilised - e.g. Concorde, Humber Bridge, Dounreay. HS2 will be heavily used once opened.
It's worth pointing put that some in that list were private sector projects, so not involving public money (notably the Channel Tunnel, and all the Victorian lines).No, it will quickly become part of the essential infrastructure of the country and the cost will be forgotten by everyone apart from economists and civil engineers. Why am I so confident about this? Because it's happened time and time and time again. Here, in no particular order, is a non-comprehensive list of some UK engineering projects which massively overran:
Channel Tunnel
Jubilee Line Extension
Edinburgh Tram
Wembley Stadium
WCML route modernisation
AGR NPP programme
Heathrow Express
The original 1830s WCML
The original 1840s Great Western ML
Projects tend to be remembered for their cost overruns only if they subsequently didn't get utilised - e.g. Concorde, Humber Bridge, Dounreay. HS2 will be heavily used once opened.
I'm not so sure. The Channel Tunnel/Eurostar was meant to be even more spectacular, but has fallen a long way short of the promised mass transport from Britain to Europe, being progressively scaled back in service provision and being sold off to a series of operating partners all of whom have got into the hands of financial investors who find that a limited service at high fares makes a bit more return than the mass market service originally touted. There are quite a number in Kent who will say that the onetime NSE services into London were better for them than today's High Speed HS1 operation.Oh yeah I'm convinced that within a couple of years of it opening there will be article after article talking about how amazing it is to be able to get between London and Birmingham so quickly and efficiently and why on earth haven't we built further to Manchester and Leeds. It's going to be a roaring a success (on it's dedicated infrastructure) and everyone is going to be clamouring for extensions.
I was contrasting the long term view of projects which went vastly overbudget but were deemed to have 'worked', compared to projects that also went vastly overbudget and were unsuccessful in operation. It's really only the latter that cost overruns are remembered for.It's worth pointing put that some in that list were private sector projects, so not involving public money (notably the Channel Tunnel, and all the Victorian lines).
You might also add Concorde, London's "3rd airport" and any number of defence and energy projects.
There were also white elephants like TSR2 and Blue Streak (and, until recently, the Bletchley flyover).
140 miles of double track railway. Similar to what Mr Brunel did from London to Bristol. Is that really beyond us now?So was the problem with HS2 that it is too big a project ?.
I'm not so sure. The Channel Tunnel/Eurostar was meant to be even more spectacular, but has fallen a long way short of the promised mass transport from Britain to Europe, being progressively scaled back in service provision and being sold off to a series of operating partners all of whom have got into the hands of financial investors who find that a limited service at high fares makes a bit more return than the mass market service originally touted. There are quite a number in Kent who will say that the onetime NSE services into London were better for them than today's High Speed HS1 operation.
It seems so going on current evidence! As dispiriting as it is to see.140 miles of double track railway. Similar to what Mr Brunel did from London to Bristol. Is that really beyond us now?
More pertinently is Robert Stephenson's original London & Birmingham Railway to the still-standing old terminus at Curzon St.140 miles of double track railway. Similar to what Mr Brunel did from London to Bristol. Is that really beyond us now?
I know what you mean but I doubt anyone would say that HS1 should never have been built nor regret its building? Plus the reasons for it's being less successful than hoped surely have more to do with the general failure of Eurostar itself to be quite as successful as hoped (for the well trod reasons of budget airlines coming along, Eurostar north of London never coming to fruition, the boarder formalities, etc etc) than the infrastructure itself. I'm not sure there's any particular reason to suppose that services on HS2 will face the same problems Eurostar did? Or are we expecting demand for long distance travel to dry up? As for it being sold off to private investors and the consequences that has had that seems like a classic short sighted political decision rather than failure of the infrastructure itself!
It shouldn't be, but experience generally, outside the rail industry is that even simple jobs seem to take an inordinate amount of time and as a result costs spiral.140 miles of double track railway. Similar to what Mr Brunel did from London to Bristol. Is that really beyond us now?
More pertinently is Robert Stephenson's original London & Birmingham Railway to the still-standing old terminus at Curzon St.
Initial estimates were £2.5 million, but it cost £5 million to build and open.
The original estimates excluded the Euston terminus, not unlike the current position, and the biggest overrun was in the construction of Kilsby Tunnel which cost £280K instead of the £120K estimate.
It took 5 years to build, from the approval of the parliamentary act in 1833 to staged opening between 1837-38.
The funding was mostly by Liverpool private investors.
Sobering thought.140 miles of double track railway. Similar to what Mr Brunel did from London to Bristol. Is that really beyond us now?
Some good points within this document, that applies to all projects https://assets.publishing.service.g...international-benchmarking-study-document.pdf. Many of the problems for HS2 are not HS2 specific - Hinkley Point C's budget doubled too.We seem to have lost the ability to deliver major infrastructure projects. I also don't its due to increasing health and safety, this should be offset by better machinery and better modelling before starting a job. I do think the complex commercial arrangements are not helping as there are armies of people on a major project trying to squeeze every change into an opportunity to increase profits.

Many thanks, that is a lot easier to read.Come on - give me a break as my yank friends would say!
saving speed mph minutes per mile seconds per mile 200 mile section minutes saved 10 6 360 20 3 180 30 2 120 60 1 60 90 0.67 40 120 0.50 30 2000.0 33.33 186 0.32 19.4 2129.0 35.48 200 0.3 18 271.0 4.52 225 0.27 16.0 400.0 6.67
That's certainly a problem. The project's huge demand for raw materials caused prices to rise. Could you realistically trim it back to anything smaller than Euston-Handsacre though? I don't see how.So was the problem with HS2 that it is too big a project ?.
Yes, there are few things I recognise from within my industry.Some good points within this document,