Not lot of evidence of work currently happening on parts of this section from the amount of vegetation that has grown on some of the spoil heaps
Potentially three higher level issues on progress or rather lack there off:
1. Cashflow limitations due to HMT/DfT Capex limits
2. The "DS" staffing contract issues (known to impact this area) and the temporary pausing reduction in work rate (publicly announced by the JV).
3. Focusing staff on the areas (or rather specific structures) that are most behind and on or near the critical path.
On a more local level in many places including this area:
a) there are still utility diversions to do (buried electric in this case based on the video) but many of the videos along the route show utility diversions are still needed (electricity typically done in summer).
b) lotsof spoil need to be moved along the alignment for medium or longer distances and this far easier to do when bridges are complete and haul tracks can travel along a clear-ish trackbed
Earth moving is comparatively cheap and quite a bit can be left till later when access along the route will often be easier.
In general there seems to have been issues with slow completion of structures north of the Chiltern tunnel hence the focus need to be on those structure but until relatively recently in many cases the two north civils JV seemed focused on completing some easy ear moving stuff far earlier than
now needed in reality in order to get paid, which given overall capex limits might have been slowing some other more critical items.
Also the contractor often don't appear to have focused on availability of plant to well (i.e. outside specialist items) and were often hire in vast amounts of new plant (or newish as it all has to be low emission by default unless there is a special dispensation) for the more simple tasks and this won't have been cheap given the shortage in the UK. Hinkley Point C and now Sizewell C* have also required vast amounts of the same new equipment (e.g. CAT 730 / Volvo A## off road haul trucks*, medium sized excavators and medium sized bull dozers.
* e.g. at the moment a stream of low loaders bearing equipment heading towards East Suffolk from the import port / import agent locations. Some of the trailers are even specifically built for moving CAT 730 / Volvo A## off road haul truck).
Hence optimising simpler plant equipment utilisation around more realistic build dates could yield some sensible savings in the short term and allow cash to be better focused elsewhere.
Similarly there has been a structures focus on bigger more complex /critical ones, e.g. leaving footbridges for the time being (foundation are well away from the line of route).
There may also have been some focus prioritising the alignment near the locations where track laying will start/be fed from (in this case 20+km from the nearest track laying start point).