Longish piece from the Observer on HS2 archaeology


HS2 may have been controversial, but it has also given rise to the biggest archaeological excavation in British history. With more than 100 digs, entire lost towns have been unearthed along the route – radically changing our understanding of the ancient past
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
HS2 Ltd has updated the position of TBM Dorothy at Long Itchington.
On February 28 it was at 170m (of the 1510m tunnel), an advance of 28m since February 14, or 2m/day.
No update on the Chiltern TBMs.
There doesn't seem to be a coordinated report of progress, but of course different contractors are involved.

Edit: another update for Dorothy was posted on March 7: 194m, or 3.4m/day in the last week.
Looks like they are posting progress weekly.
Still no update on the Chiltern TBMs since Feb 21/22.
 
Last edited:

chiltern trev

Member
Joined
28 Mar 2011
Messages
513
Location
near Carlisle
https://nationaltradesmen.co.uk/202...rking-on-hs2-leaves-sites-amid-cash-shortage/

Massive civil engineering contractor Road Bridge has stopped working on the flagship HS2 project after it is hit with cash issues the company which has a direct labour force of more than 1,600 people has refused to comment.​


Across HS2 sites on Thursday Roadbridge’s fleet of plant is being packed-up amid speculation of the company going into administration.


Many of the employees are also understood to have been let go at sites in Ireland and Scotland, the Limerick based Roadbridge has offices in England, Scotland and Wales and has been in business for more than 50 years.


Roadbridge has been seeking an investor in the business for some time with a deal with a “white knight” buyer understood to have collapsed earlier this week.


One source said: “Word has been doing the round for a while that Roadbridge were in trouble and suddenly today hundreds of workers at HS2 were told to go home.


“A lot of money is owed to suppliers on what is the country’s flagship civils job.


“All of the plant has been packed up to one side on the site and it looks like it will be on its way somewhere.”


Roadbridge owns one of the largest in-house plant fleets in Europe which is the company’s main asset.
 

Mikey C

Established Member
Joined
11 Feb 2013
Messages
8,234
Ironic that a major rail project is being badly hampered by the troubles at a contractor named Roadbridge ;)
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
HS2 Ltd has posted a media item on progress in the Chiltern Tunnels, confirming that TBMs Florence and Cecilia have reached the Chalfont St Peter vent shaft.
There's an embedded video which shows how the workers reach the TBMs using MSVs (multi service vehicles), and also the construction of cross-passages between the two tunnels.
HS2 this week confirmed that the two enormous 2,000 tonne tunnelling machines digging the high speed rail project’s tunnels under the Chilterns have completed the first stage, up to the ventilation shaft at Chalfont St Peter.
This major achievement means that a combined total of over 3.6 miles has now been dug by the two machines – named Florence and Cecilia – since they launched from the southern end of the tunnels last summer.

The MSVs look very swish and clever as people-movers underground - a bit like those strange mobile lounge pod things they use at Washington Dulles airport.
It seems the TBMs have been through a spell of maintenance, which explains the apparently slow progress recently.
There's no hint that the Roadbridge contractor failure is having any impact on the tunnelling, though I'm sure they wouldn't tell us anyway.

== Doublepost prevention - post automatically merged: ==


Edit:
HS2 Ltd has posted progress for the two Chiltern TBMs today (March 15), the first update for 3 weeks.
Florence is at 2996m (+100m), and Cecilia is at 2923m (+436m).
Presumably they are both now at/past the Chalfont St Peter vent shaft.
 
Last edited:

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,991
Location
Surrey
I read it as the forecast outturn remaining within the range of landing under £44.6m.
OK thats correct within funding envelope at they 5.4B of contingency within that amount but over the last six months, ie since last report issue, HS2 have eaten into this pot by another 0.9B (£0.5 billion from increase in contingency drawdown plus £0.4 billion from potential further cost pressures).

The minister then states

Whilst these pressures are manageable within the target cost given the remaining contingency, I am nonetheless concerned at the rate of their increase. I expect HS2 Ltd to maintain its focus on delivery to the target cost.
Also HS2 have made efficiencies against rolling stock contract (lets see how that plays out) so the situation would have been worse. Also like Crossrail NR is already bleeding them for more funding up another 0.2B this report to deal with interfaces at Old Oak and Euston.

So still plenty of headroom but we are barely a year into full construction so could easily get consumed. In the round good though progress being made.
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,030
OK thats correct within funding envelope at they 5.4B of contingency within that amount but over the last six months, ie since last report issue, HS2 have eaten into this pot by another 0.9B (£0.5 billion from increase in contingency drawdown plus £0.4 billion from potential further cost pressures).

The minister then states


Also HS2 have made efficiencies against rolling stock contract (lets see how that plays out) so the situation would have been worse. Also like Crossrail NR is already bleeding them for more funding up another 0.2B this report to deal with interfaces at Old Oak and Euston.

So still plenty of headroom but we are barely a year into full construction so could easily get consumed. In the round good though progress being made.

A fair assessment, however even if HS2 costs a little more than the budget (say) 5% more then it'll be a draw in terms of claims from either side. Those opposed will be able to claim that it went over budget whilst those who support it will claim that the cost estimates that those opposed to it clung to where wildly wrong.

Even a 10% increase in costs would probably be small enough that future HS lines would find it easier to get built. As it's not hard to find cost estimates citing 20% or more than the budget.

That's not too say that HS2 shouldn't try to be within budget, just that it'll not be disastrous if there's some small overrun in costs.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
Modern Railways magazine, April issue, has, at the bottom of pages 54-55, a picture of the abutments under construction for the bridge that will carry East-West Rail over HS2 at Calvert.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,237
Modern Railways magazine, April issue, has, at the bottom of pages 54-55, a picture of the abutments under construction for the bridge that will carry East-West Rail over HS2 at Calvert.
And it’s pretty massive isn’t it. I don’t think gauge or wiring clearance will be an issue…
 

bnc2018

Member
Joined
14 May 2021
Messages
51
Location
Banbury, Oxfordshire
Was on a cycle yesterday and happened (complete coincidence of course) to parallel the HS2 route for a bit. First photo is looking towards Aylesbury from Blackgrove road just north of Waddesdon. Second and third are looking south and north along the old GC line between Quainton and Edgott, and then the fourth and fifth are of the EWR overbridge at Calvert mentioned in #1211, first side on and then further along the road looking along the route. I'm guessing there's a passing loop here because the abutments are really far apart. In the end I got a puncture from a pothole just outside the entrance to the Calvert worksite which has dampened my enthusiasm for all the construction a bit!
 

Attachments

  • IMG_20220323_144353.jpg
    IMG_20220323_144353.jpg
    2.2 MB · Views: 302
  • IMG_20220323_152031.jpg
    IMG_20220323_152031.jpg
    2.3 MB · Views: 294
  • IMG_20220323_152045.jpg
    IMG_20220323_152045.jpg
    2.9 MB · Views: 295
  • IMG_20220323_153839.jpg
    IMG_20220323_153839.jpg
    3.4 MB · Views: 289
  • IMG_20220323_154237.jpg
    IMG_20220323_154237.jpg
    1.1 MB · Views: 292

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,636
I'm guessing there's a passing loop here because the abutments are really far apart.

just the two tracks on HS2 underneath the EWR bridge.

however at the road bridges east and west of there, there are link lines from HS2 to the infrastructure maintenance depot which will be based at Calvert, so those road bridges will be long.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
More TBM progress from HS2 Ltd:
Florence on Mar 23: 3212m (+216m since Mar 15, 27m/day)
Cecilia on Mar 23: 3131m (+208m since Mar 15, 26m/day)
Dorothy 346m on Mar 25 (+116m since Mar 15, 11.6m/day)

All these rates are significantly higher than anything previously reported, so they seem to be getting a move on.
Cecilia is only 81m behind Florence in the Chiltern tunnels.
 

Yindee8191

Member
Joined
16 Mar 2019
Messages
181
More TBM progress from HS2 Ltd:
Florence on Mar 23: 3212m (+216m since Mar 15, 27m/day)
Cecilia on Mar 23: 3131m (+208m since Mar 15, 26m/day)
Dorothy 346m on Mar 25 (+116m since Mar 15, 11.6m/day)

All these rates are significantly higher than anything previously reported, so they seem to be getting a move on.
Cecilia is only 81m behind Florence in the Chiltern tunnels.
Does this mean that the two Chiltern TBMs have finished their maintenance break at the first shaft?
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Does this mean that the two Chiltern TBMs have finished their maintenance break at the first shaft?
Yes it looks like it.
I'm not sure the data is reliable though, the recent rates look "too high" to me, maybe the date stamps are off.
The next update will give a better guide. Maybe there will be pauses at each shaft site.
The average since the start is 10-11m per day, which is rather less than the predicted 15m/day.

I see from a recent RAIL article that Dorothy, the TBM at Long Itchington, is of a different design to cope with local geology, and the design is important for the longer (3.5km) Bromford tunnel needed further north.

== Doublepost prevention - post automatically merged: ==


Edit:
Another Chiltern TBM update for Mar 29, only 6 days since the last:
Florence: 3342m (+130m)
Cecilia: 3253m (+122m).
So these TBMs are maintaining progress of 20m+ per day.
It gets them both past the "2-mile" point of the 10-mile tunnel.
 
Last edited:

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
I see from a recent RAIL article that Dorothy, the TBM at Long Itchington, is of a different design to cope with local geology, and the design is important for the longer (3.5km) Bromford tunnel needed further north.
I think most TBMs are custom designed for the geology they will be going through.
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
More Chiltern TBM progress for April 11:
Florence 3452m
Cecilia 3413m
Progress has slowed from the recent high rates, but Cecilia is now only 39m behind Florence.

At Long Itchington, where progress is reported more frequently, Dorothy was at 462m on April 8, or about one third through its 1.5km bore.
It is also boring at a much faster rate than previously (17m/day).
 

The Ham

Veteran Member
Joined
6 Jul 2012
Messages
12,030
I've started a new thread on the potential reintroduction of cycle facilities alongside HS2:


I mention it here as it's talking about repurposing the construction access roads, so in theory could already be started to be built!
 

DaveHarries

Established Member
Joined
12 Dec 2011
Messages
2,569
Location
England
Roadbridge is officially no more. I wonder who will take on the HS2 work but whoever it is I hope the now former employees of Roadbridge are able to get back into work soon.

Dave
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,037
Location
West Wiltshire
There is quite an interesting article on how a number of big construction projects are going wrong and being delayed because software development wasn’t commenced early enough, and it uses Crossrail as one of its examples.

I am copying it here, into HS2 thread, because although comments are being made about digging tunnels etc, not hearing anything about the software needed to run tunnel safety systems, or the signalling etc. This seems to be a repeat of Crossrail (which we all know ended up 3-4 years late as working software wasn’t ready)

For Crossrail the project started in 2008, by 2012 all the reporting was on digging the tunnels with nothing about the software needed to make the trains run and control the safety systems when it opened, wasn’t until 2015 that this started to cause concerns.

The article uses a number of diagrams, so not going to quote text without being able to include the illustrating diagram that it refers to


HKA is a global consultancy in risk mitigation with multi-disciplinary expertise
 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Progress reports on TBM positions seem to have become weekly, although on different dates for the two current projects.
On April 25 Florence was at 3850m and Cecilia at 3767m in the Chiltern tunnels.
Both are making very good progress at about 25m/day.

Dorothy is at 710m in the first Long Itchington tunnel, close to the half-way point.
Progress has increased seemingly to something like 40m/day here.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,472
Location
Preston Lancs
Progress reports on TBM positions seem to have become weekly, although on different dates for the two current projects.
On April 25 Florence was at 3850m and Cecilia at 3767m in the Chiltern tunnels.
Both are making very good progress at about 25m/day.

Dorothy is at 710m in the first Long Itchington tunnel, close to the half-way point.
Progress has increased seemingly to something like 40m/day here.
Nice steady progress is good.
 

city dweller

Member
Joined
17 Apr 2019
Messages
104
Bridge demolition taking place to clear the route for HS2.

FRqg2rsXMAAdCw8


 

LNW-GW Joint

Veteran Member
Joined
22 Feb 2011
Messages
21,902
Location
Mold, Clwyd
Impressive.
As I understand it from the videos:
That's a new bridge on the Stechford-Aston line where it crosses the Midland route, largely replacing the former viaduct.
HS2 towards Curzon St will run under the southern half of this bridge (Midland line runs under the northern half).
A connection from the HS2 rolling stock depot at Washwood Heath will be in there somewhere too, to the east of the new bridge.
 

Nicholas Lewis

Established Member
Joined
9 Aug 2019
Messages
7,991
Location
Surrey
Evening Standard from 3 days ago had an item that HS2 want to use lorries now to deliver Euston materials and not rail adding 25k road movements into the area to save money. HS2 say they will have to payout too much compensation to operators but given its all govt cash now this is a pathetic excuse and doesn't do the industry any favour nor enhance HS2 going about saying we will be the greenest railway ever.
 

city dweller

Member
Joined
17 Apr 2019
Messages
104
That's a new bridge on the Stechford-Aston line where it crosses the Midland route, largely replacing the former viaduct.
HS2 towards Curzon St will run under the southern half of this bridge (Midland line runs under the northern half).
A connection from the HS2 rolling stock depot at Washwood Heath will be in there somewhere too, to the east of the new bridge.

Aston Church Road Overbridge is also due to be replaced at some point.

1651410729293.png


1651411113972.png
 