Obviously I only expect a VERY ballpark number.
I was just pondering what kind of numbers we are talking about if the UKG/Treasury said
”We accept rolling electrification, we accept your list of priorities, and rather than fund individual projects we will fund the equivalent of X wiring teams (design, infrastructure, wiring, the lot) for ten years and it’s up to you Network Rail to get the most out of them, and keep them working”.
Would Network Rail create its own in such a situation or carry on using contractors?

The second part is based around a hypothetical that the number of teams the government was willing to fund was more than currently exist (at a sensible price). Could they create an “electrification academy” like the tunnelling one in East London and increase the supply in a couple of years? I am guessing that design is the tricky one for that - would that be a postgrad “apprenticeship” type deal?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,679
Location
Northampton
Would Network Rail create its own in such a situation or carry on using contractors?
Would depend entirely on the amount of funding, how long it was secured for, and the cost of the contractors vs in-house.
The second part is based around a hypothetical that the number of teams the government was willing to fund was more than currently exist (at a sensible price). Could they create an “electrification academy” like the tunnelling one in East London and increase the supply in a couple of years? I am guessing that design is the tricky one for that - would that be a postgrad “apprenticeship” type deal?
Yes, in theory. Might need to be more than just a couple of years though.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,988
Network Rail has its own wiring team.

As it happens the cost of wiring teams is a tiny fraction of the cost of electrification though. You also need bridge replacement teams, station teams, heavy civils teams, signalling teams, foundation teams, track teams, utilities teams, power and distribution teams, design teams, community relations teams, and so on.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
It depends what you call a ‘team’.
I guess I mean the annual cost of one rolling project.
ie you could have one project rolling through GWR schemes, one rolling through Midland Main Line, one doing freight etc etc.
I‘m only asking in terms of politician scale amounts, round hundreds of millions maybe.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,988
I guess I mean the annual cost of one rolling project.
ie you could have one project rolling through GWR schemes, one rolling through Midland Main Line, one doing freight etc etc.
I‘m only asking in terms of politician scale amounts, round hundreds of millions maybe.

Well, it depends on various things. How much signalling / civils / station / track works need doing. And the long lead item in all of this is power supply. 3 years absolute minimum, often 5+.

The thing is that all the non-electrification works - which can make up more than half the cost of an electrification project - are usually delivered by the teams that deliver that type of work normally.
 

Meerkat

Established Member
Joined
14 Jul 2018
Messages
9,276
Well, it depends on various things. How much signalling / civils / station / track works need doing. And the long lead item in all of this is power supply. 3 years absolute minimum, often 5+.

The thing is that all the non-electrification works - which can make up more than half the cost of an electrification project - are usually delivered by the teams that deliver that type of work normally.
So what do you tell the minister to ask from the Treasury?
we keep hearing ‘need rolling electrification programme to keep the teams together’
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,988
So what do you tell the minister to ask from the Treasury?
we keep hearing ‘need rolling electrification programme to keep the teams together’

The treasury will never buy a rolling electrification programme.

You ask for projects on a case by case basis. Starting with the MML. After a few (and it’s not far away) the Network benefits of electrification start to come through, particularly for Cross Country and freight.

Incidentally, you never “tell” the minister to ask for anything. You offer him (or her) advice, and allow him (or her) to choose.
 

XAM2175

Established Member
Joined
8 Jun 2016
Messages
3,471
Location
Glasgow
So what do you tell the minister to ask from the Treasury?
we keep hearing ‘need rolling electrification programme to keep the teams together’
The closest you'll probably come to this is the approach currently used north of the border; Transport Scotland give Network Rail an overall budget and a list of projects and their priorities and then tell them to crack on with as much as they can.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
The closest you'll probably come to this is the approach currently used north of the border; Transport Scotland give Network Rail an overall budget and a list of projects and their priorities and then tell them to crack on with as much as they can.
I would love to think the UK government would follow Scotland's example here, but I don't think it's likely, at least not so long as the present government is in power.
 