HS2 set to abandon complete rebuild of Euston
PLANS to rebuild Euston station in London to accommodate HS2 are set to be scaled down, partly in response to determined opposition in the London Borough of Camden.
Government-owned developer HS2 Ltd said that under its latest proposals Euston will not be completely rebuilt. Instead, the station would be extended by the addition of High Speed platforms in time for the opening of the first section between London and Birmingham in 2026.
HS2 revealed that it had found 'most of the benefits for Euston could be achieved without having to knock down and rebuild the entire station'.
It explained: 'Further work on design and engineering has found the project can deliver wide-ranging opportunities and improvements on time but without the disruption caused by lowering all of the platforms into the ground, and in doing so achieve best value for money for taxpayers.
'This option, developed partly in response to concerns from the community about the potential disruption caused by redevelopment that would have taken more than a decade, would obviate the need to rebuild all the existing platforms. This would lead to less disruption for passengers as the station could continue to operate mostly as normal rather than having to move services from old platforms to new ones while platforms are being progressively demolished and rebuilt.'
However, HS2 also emphasised that 'the proposals would still see the station revitalised for passengers and with potential for new homes, offices and shops above. Completing construction by 2026 will unlock the line-wide benefits as soon as practicable'.
The new proposals, to be included in the draft environmental statement for the first phase of HS2 which is due to be published for consultation within the next couple of months, suggest that Euston will now keep most of its present domestic platforms. However, some will be lengthened and their total will come down from 18 to 13. There would also be 11 new High Speed platforms on the western side of the site.
Other developments would include a new, combined concourse and façade, better connections with the Underground including a new Underground ticket hall, a sub-surface pedestrian link between Euston and Euston Square Underground stations and new east-west pedestrian routes across the station. However, the announcement does not mention the possible need to make longer-term provision for Crossrail 2, which could include a new subsurface station linking Euston with St Pancras and King's Cross.
HS2 Ltd chief executive Alison Munro said: HS2 will be an engine for growth. In response to community concerns about the potential disruption caused by the redevelopment of Euston station, and following more work done by our engineers to find the best way to deliver best value for taxpayers, we have identified an option that delivers great opportunities for the area while minimising the potential effects on local communities in Camden and on passengers.
We are looking at an option which would see new platforms built as part of an integrated, redeveloped station with a combined concourse, new western entrance and improved facilities across the integrated terminus.
Economic work done as part of Camden Councils plan for the area has demonstrated that there is a case for major redevelopment with the potential for commercial investment, and we want to look at these opportunities with Camden. We also realise the importance Camden Council places on over-station development, and our proposal for Euston enables this, with potential for future homes, businesses and open space.
Whatever option is adopted, Euston would be the gateway to the Midlands and North with improved facilities for passengers and better connections with the Underground