Progress Report 09/07/22
So, ahead of the 5 week closure of the line between Kirkby and Rainford, preparatory work seems to have started on the current bridge(s) over County Road. Some demolition work has begun on the middle pier supporting the current single track bridge deck(s)...I believe the middle pier is being removed completely and a new deck will span the entire gap with a view to "assisting with any future plans to widen County Road". Time will tell I guess.
The footpaths leading to the former underpass have now been fully filled in on the Southcroft Drive side of the site and new footpaths are being laid level with Headbolt Lane. I'm guessing they'll be doing the same on the station side of the site.
Foundations fully dug and concrete laid for ticket office platform. Still nothing on Northwood side platform.
So, ahead of the 5 week closure of the line between Kirkby and Rainford, preparatory work seems to have started on the current bridge(s) over County Road. Some demolition work has begun on the middle pier supporting the current single track bridge deck(s)...I believe the middle pier is being removed completely and a new deck will span the entire gap with a view to "assisting with any future plans to widen County Road". Time will tell I guess.
The footpaths leading to the former underpass have now been fully filled in on the Southcroft Drive side of the site and new footpaths are being laid level with Headbolt Lane. I'm guessing they'll be doing the same on the station side of the site.
Foundations fully dug and concrete laid for ticket office platform. Still nothing on Northwood side platform.