Had a look today for any progress, for my own benefit.
For anybody else who may be interested:
Maidenhead trackwork and wires look complete.
Plat 5 loop fully wired, including crossover to Plat 4.
Turnback finished.
Stabling sidings track and wires look good, still other work going on and sleeper blocking access.
Wires finish at MP25 and there is then a gap on all lines to approximately MP25 3/4.
UR/DR then wired to approximately MP28 3/4.
UM/DM wired until just before MP30. However, approximately 1 mile of the UM is catenary wire only, MP28 3/4 to MP29 1/4.
Twyford, portal still missing east of the station.
Plat 2,3 & 4 canopy work.
Road bridge parapet work.
New signal off Reading end of the DR platform. Bagged over.
There appears to be two mast bases covered over on plat 4. I don't know if they will be used, I'm guessing they are for the wires coming off the Henley branch connection (if ever done).
Wires start again after MP31 1/2 (west of Loddon viaduct).
Twyford West crossovers part wired, Relief to Relief.
DM/UM wired to approximately MP34 3/4 Kennet loop area. Section of DM which had the contact wire removed, has now been replaced.
DR/UR wired the same except, UR section of catenary wire only coming out of the west end of Sonning Cutting.
DR couple of sections with no wires from east of Warren Road bridge to where the old Sonning sidings were.