I believe the location where what Crossrail calls its Outer West Package contract area ends is Ruscombe junction, about five miles west of Maidenhead, so that would seem to be a likely candidate for the point where Amey takes over responsibility for the wiring work.
I've had a look but can't find the exact mileage, but it has to be somewhere between 29m and 31m based on the survey work which was done for both projects.
The electrical system doesn't quite match the catenary, but that was changed very early on when it become clear electrification was going beyond Maidenhead.