SpacePhoenix
Established Member
- Joined
- 18 Mar 2014
- Messages
- 5,491
How often do pantograph assemblies get swapped out in general?
Well Brecknell-Willis pantographs have been in regular use on routes where pantographs are raised and lowered up to 20 times per day, (think classes 319, 377, 378, 387 & 395), so unless the original plans for those on the class 800s assume a service action more than once per week, they should last between maintenance operations for the early part of their lives.
How often do pantograph assemblies get swapped out in general?
I'm not sure we have had services which require pan up/down more than once on a single journey though.
Maybe for a period on NLL services (3rd rail at the west and east ends, AC in the middle) before they were cut back to Stratford.
Let's hope the first service wiring is Stockley-Didcot and not some discontinuous sections in between.
We can also look forward to pan up/down at speed on the Didcot avoiding line - just like Dollands Moor used to be on Eurostar.
I'm not sure we have had services which require pan up/down more than once on a single journey though.
Maybe for a period on NLL services (3rd rail at the west and east ends, AC in the middle) before they were cut back to Stratford.







Another one of the cost inflation issues described by the rail press is the need to handle two pantographs up on the length of a train.
Is that really something not handled a while ago?
https://www.google.co.uk/imgres?img...d=0ahUKEwiTxMqG-9nJAhWLaxQKHbiTA60QMwhBKBYwFg
Another one of the cost inflation issues described by the rail press is the need to handle two pantographs up on the length of a train.
Is that really something not handled a while ago?
https://www.google.co.uk/imgres?img...d=0ahUKEwiTxMqG-9nJAhWLaxQKHbiTA60QMwhBKBYwFg
Won't they just use the design used on the Javelins?
Won't they just use the design used on the Javelins?
One assumes NR is keen to keep these reports up to date, especially as they involve local consultation. With that in mind, the Filton bank planned activities are not exactly zooming ahead it would appear. The renewal /replacement of the viaduct over Stapleton Road onwards over the River Frome and M32 will be a major job, for instance.
Won't they just use the design used on the Javelins?
I wonder how much all this strengthening of the equipment is actually costing.
After 100mph rated Mark 3 equipment was approved for use with 125mph with relatively minor upgrades on the East Coast and despite what people like to claim it isn't really that unreliable.
This enormous expenditure on serviceable equipment stinks of gold plating.
Yes i do wonder how things are progressing, on the surface not alot appears to have happened regarding the Filton Bank.
Can anyone help me with the following?
I am led to believe the re-quadrupling of Filton Bank may not include the reinstatement of two extra platforms on Stapleton Road and Lawrence Hill. This implies a total segregation between express and stopping services and will store up problems for the future of local trains, express
trains and the development of Stapleton Road railway station as Bristols second station and as a Bristol Temple Meads relief. The implication is that local trains will not be able to stop at these local mainline stations if the local track is closed for maintenance. Do local services miss out these stations and join the Severn Beach line? Can local trains access the express tracks? Will the points at Narroways Junction cross all four lines? It will be difficult to explain that despite the increase in the capacity of Filton Bank in case of track maintenance local trains will
have to be bustituted because they cant stop at Stapleton Road and Lawrence Hill due to an omission of extra platforms at these stations. Due consideration must be given at least to Stapleton Road being rebuilt with four platforms to allow local trains to call when the local tracks are closed for engineering work and even be used as Bristols relief station.
Your help is appreciated as always.
Can anyone help me with the following?
I am led to believe the re-quadrupling of Filton Bank may not include the
reinstatement of two extra platforms on Stapleton Road and Lawrence
Hill. This implies a total segregation between express and stopping
services and will store up problems for the future of local trains, express
trains and the development of Stapleton Road railway station as Bristols
second station and as a Bristol Temple Meads relief. The implication is
that local trains will not be able to stop at these local mainline stations if
the local track is closed for maintenance. Do local services miss out
these stations and join the Severn Beach line? Can local trains access
the express tracks? Will the points at Narroways Junction cross all four
lines? It will be difficult to explain that despite the increase in the
capacity of Filton Bank in case of track maintenance local trains will
have to be bustituted because they cant stop at Stapleton Road and
Lawrence Hill due to an omission of extra platforms at these stations.
Due consideration must be given at least to Stapleton Road being rebuilt
with four platforms to allow local trains to call when the local tracks are
closed for engineering work and even be used as Bristols relief station.
But Lawrence Hill and Stapleton Road stations will not get back their redundant platforms. The reason for this is they want to realign the track at the back of these stations, for trains to travel faster. But I question whether this is right. The same thing happened at Pangbourne on the Great Western main line which serves trains from Reading and Oxford. Most of these services start or continue as semi-fast services between Reading and London Paddington and run twice an hour. Pangbourne has two platforms, on each of the relief (slow) lines, whilst the fast lines pass behind the station. This is the same set-up as Lawrence Hill and Stapleton Road station. But removing platforms at Pangbourne which served the fast lines has meant that when the relief lines are closed for engineering work local stopping services cannot call at Pangbourne and a replacement bus service is required.
I wonder how much all this strengthening of the equipment is actually costing.
After 100mph rated Mark 3 equipment was approved for use with 125mph with relatively minor upgrades on the East Coast and despite what people like to claim it isn't really that unreliable.
This enormous expenditure on serviceable equipment stinks of gold plating.
I really see no circumstances under which Stapleton Road would be a "relief station" anymore. The access simply isn't good enough - any engineering works which close Temple Meads would divert trains to Parkway, any works which close Parkway would divert trains via Temple Meads. The reason Stapleton Road stopped being Bristol's second station is precisely because trains could reverse easily once DMUs started operation, something which wasn't true with locomotive-hauled stock.
There are currently no plans for four platforms at Lawrence Hill or Stapleton Road - no platforms mean through trains can run faster; though local rail campaigners do want four platforms.
From http://www.bristolpost.co.uk/need-avoid-mistakes-Pangbourne/story-15828103-detail/story.html
Out of curiosity, what's the scope of F+F equipment being used beyond the GWML? Presumably with the lessons learned from this project it'll see the light of day elsewhere on the UK network - maybe on the MML?
Also, just a quick note of appreciation to Philip Phlopp. I've learned more about UK electrification in the last few months via his posts here than I've managed to find anywhere else via Google. Really fantastic.
Careful, Philip Phlopp might garotte you with a Mk3 headspan wire, or beat you over the head with a headspan foundation. You would probably be able to walk away though!![]()
Philip Phlopp said:The headspan foundations and masts can cope with a lightweight Series 1/GWML style lattice portal structure being fitted, provided the registration equipment isn't too heavy. That's more gold plating (or reliability modifications, as we call them in the real world) which will be coming to stretches of the ECML soon.
MML
--- old post above --- --- new post below ---
Headspan foundations are actually OK, it's the single track cantilevers which are pretty shocking (across the Fens in particular).
The headspan foundations and masts can cope with a lightweight Series 1/GWML style lattice portal structure being fitted, provided the registration equipment isn't too heavy. That's more gold plating (or reliability modifications, as we call them in the real world) which will be coming to stretches of the ECML soon.
Thanks again Philip.
Re the ECML mods, this is an expansion of the trial portals that were installed around Potter's Bar earlier this year?
That may be because of the dazzle it can reportedlly cause to drivers.The Series 2 system is a comprehensively re-engineered version of Mark 3b system (I saw it being referred to as Mark 3b with sunglasses on the other day)
I saw these photos from the Fens the other day, which perfectly show the issue there:
![]()
Single line working by Justin Perkins, on Flickr
![]()
Next stop Littleport by Justin Perkins, on Flickr
I saw these photos from the Fens the other day, which perfectly show the issue there:
![]()
Single line working by Justin Perkins, on Flickr
![]()
Next stop Littleport by Justin Perkins, on Flickr
A number of points
We can't afford two or three days of disruption on the GWML, CrossRail suspended west of Paddington, no Heathrow trains, no electric trains on the GWR routes, no Oxford services. Mechanically independent registration is not just desirable, it's absolutely vital for service provision on the GWML, it's as vital a step forward over headspans as four aspect light signalling was over home and distant semaphore signaling.
Also, just a quick note of appreciation to Philip Phlopp. I've learned more about UK electrification in the last few months via his posts here than I've managed to find anywhere else via Google. Really fantastic.
That's more gold plating (or reliability modifications, as we call them in the real world) which will be coming to stretches of the ECML soon.