I can't believe that, years after the contract for a given price was let to the contractors, there are still parts of the design not finished. How on earth can the contractors have quoted for the work?
In the case of Oxford I'm afraid it really isn't that simple, as the scope of the work needed in the area has been in a constant state of flux for several years. What looked like a fairly simple project to replace life-expired signals in the area and cater for Chiltern's London service plus the electrification got overtaken by the go-ahead for East West Rail, the resulting rethink on what sort of station you would then need to handle the extra trains, providing capacity for them around Oxford and down to Didcot, possible provision for a grade-separated junction at Oxford North, possible passenger services up the Cowley branch, etc, etc... wrestling with jelly would be easier.
Some sort of resignalling and track alterations will be needed early next year (last I heard was that a blockade was pencilled in for the February half-term to do this work) to allow Chiltern services to reach Oxford station anyway, with the new immunised signalling also allowing some sort of basic electrification to take place but there seem to be doubts about spending money on that wiring work now if the station is to undergo major rebuilding, resulting in a much-altered track layout, in the next few years.
This is something I can't understand was well. Main Lines for the high-intensity nonstops from Reading to Paddington. Reliefs for all-stations Crossrail. However are intermediate services going to be handled; if they think those from Maidenhead or Twyford are going to get on the all-stations Crossrail to London in the morning peak, think again. While if they start on the Reliefs and then get held up trying to cross to the Main further in, delaying the Crossrail behind, this will surely impact on Crossrail presentation at Paddington, which will need to be accurate to the fraction of a minute. It's no good saying that half Crossrail will start from Paddington and can fill in, for if the Reading is headed for Canary Wharf and Abbey Wood, while the following Paddington starter is for Shenfield, sending it off in advance will do nothing for handling the Canary Wharf morning peak.
Do you really think someone, somewhere within GWR/Crossrail/Network Rail has not thought of this by now? And worked out how they propose to deal with it? Even if they have not chosen to share the details with the world yet, several years in advance of Crossrail starting running... and not all Crossrail's trains will be all-stations anyway.
As far back as 2007, they said the following
Between Maidenhead and central London, it is assumed a mixture of Crossrail stopping patterns will operate in order to minimize journey times from outer stations and permit non-Crossrail services to operate on the GWML.
http://74f85f59f39b887b696f-ab65625...rary/document/a/original/a2servicepattern.pdf
And the Maidenhead station page on Crossrail's website, as well as citing a 37-minute off-peak timing to Paddington, cutting eight minutes off the Turbo timing, adds
There are some faster trains to Paddington at peak times.
Plus whatever GWR has in mind.