I was reading an article on rail magazine about why Grand Union sold their rights to Lumo, and this line seemed curious to me.

Initially, Grand Union wanted to use Class 222 diesel-electric multiple units, but Managing Director Ian Yeowart said these units would be unable to reach their 125mph top speed.

The ‘222s’ are not fitted with Automatic Train Protection (ATP), which is in use on the South Wales Main Line between Paddington and Chipping Sodbury.

Even if fitted with ATP, they would be limited to a maximum of 110mph, meaning they would have been unable to keep to the South Wales and Great Western Main Line timetables, which require 125mph running.

The part about ATP aside, why does he think they couldn't hit 125mph? That was their designed speed wasn't it? And they had better acceleration than the HSTs that were until recently used on the GWR mainline?
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

nickswift99

Member
Joined
7 Apr 2013
Messages
282
I was reading an article on rail magazine about why Grand Union sold their rights to Lumo, and this line seemed curious to me.



The part about ATP aside, why does he think they couldn't hit 125mph? That was their designed speed wasn't it? And they had better acceleration than the HSTs that were until recently used on the GWR mainline?
Is 125mph absolutely required? GWR run 387s along this route which are definitely not capable of 125mph.
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,976
Location
London
Is 125mph absolutely required? GWR run 387s along this route which are definitely not capable of 125mph.

Depends what pathing they have available, particularly between Paddington and Heathrow Airport Junction.
 

notadriver

Established Member
Joined
1 Oct 2010
Messages
3,737
They should get rid of ATP as they did on Chiltern. TPWS+ should suffice until the eventual fitment of ETCS.
But I understand why the WCML needs its TASS.
 

357

Established Member
Joined
12 Nov 2018
Messages
2,283
The statement says they would be limited to 110mph even if fitted with ATP.
That's the bit I don't understand.
That's the bit I'd lean towards being inaccurate journalism or a misunderstanding by the writer
 

43066

Veteran Member
Joined
24 Nov 2019
Messages
12,089
Location
London
They should get rid of ATP as they did on Chiltern. TPWS+ should suffice until the eventual fitment of ETCS.
But I understand why the WCML needs its TASS.

ATP has been hugely political on the GWML especially after Southall and Ladbroke.

Presumably this would be seen as too costly, as you’d then need to install TPWS where it isn’t currently in place?
 

Efini92

Established Member
Joined
14 Dec 2016
Messages
2,137
Because they don't have ATP.

The rest is most likely Rail being inaccurate as normal
Is atp a requirement to do 125? Crosscounty voyagers don’t have atp and do 125 between didcot and reading.
 

156444

Member
Joined
28 Aug 2020
Messages
251
Location
UK
Is atp a requirement to do 125? Crosscounty voyagers don’t have atp and do 125 between didcot and reading.
The Voyagers run on the relief lines between Didcot and Reading. I'd be surprised if they're doing 125 mph on the relief lines.
 

OrangeJuice

Member
Joined
4 Jun 2018
Messages
208
The Voyagers run on the relief lines between Didcot and Reading. I'd be surprised if they're doing 125 mph on the relief lines.
They do run on the mains occasionally, particularly if delayed as it enables them to overtake the Didcot stopper they would end up behind
 

Efini92

Established Member
Joined
14 Dec 2016
Messages
2,137
The Voyagers run on the relief lines between Didcot and Reading. I'd be surprised if they're doing 125 mph on the relief lines.
Not always, I’ve driven them on the main and did 125
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,263
The Voyagers run on the relief lines between Didcot and Reading. I'd be surprised if they're doing 125 mph on the relief lines.
That seems to have achieved’ railway myth’ status. It’s been explained many times they also run on the fast lines. It’s also stated as allowed in the sectional appendix - there’s a box on page 79 with an explicit approval for non-ATP fitted trains (not just Voyagers) to use the mains between Reading West and Didcot East Junctions.
 

HamworthyGoods

Established Member
Joined
15 Jan 2019
Messages
4,476
That seems to have achieved’ railway myth’ status. It’s been explained many times they also run on the fast lines. It’s also stated as allowed in the sectional appendix - there’s a box on page 79 with an explicit approval for non-ATP fitted trains (not just Voyagers) to use the mains between Reading West and Didcot East Junctions.

Reading to Didcot is fitted with TPWS Plus.
 

XCTurbostar

Established Member
Joined
13 Sep 2014
Messages
2,495
ATP and TPWS+ aside, did Adelantes have any issues reaching 125 on the section Ian quotes?
 

HamworthyGoods

Established Member
Joined
15 Jan 2019
Messages
4,476
ATP and TPWS+ aside, did Adelantes have any issues reaching 125 on the section Ian quotes?

Class 180s had no issues with 125mph operation on the GWML as they were ATP fitted (one of the reasons why their introduction into traffic was delayed).
 

Horizon22

Established Member
Associate Staff
Jobs & Careers
Joined
8 Sep 2019
Messages
10,976
Location
London
Can you provide a link? The Grand Union website I'm looking at has had no mention of it since its been sold: https://www.granduniontrains.co.uk/

The only mention appears to be in the "Cardiff to Edinburgh" section: https://www.granduniontrains.co.uk/cardiff-to-edinburgh

Services are currently planned to start with off-lease and refurbished Class 222 trains, which will later be replaced by new build bi-mode Hitachi trains. Discussions with the rolling stock leasing companies and the manufacturer have been on-going for some time.
 

D365

Veteran Member
Joined
29 Jun 2012
Messages
13,170
is it stated anywhere how many 222s are proposed by Grand Union?
 

ExRes

Established Member
Joined
16 Dec 2012
Messages
8,333
Location
Back in Sussex
I can't find any way to get into Grand Union Trains website either from the links on here, wiki or google
 

FlyingPotato

Member
Joined
23 Mar 2023
Messages
351
Location
Always moving
I can't find any way to get into Grand Union Trains website either from the links on here, wiki or google
Try this link

== Doublepost prevention - post automatically merged: ==

Works for me
 

ExRes

Established Member
Joined
16 Dec 2012
Messages
8,333
Location
Back in Sussex
Try this link

== Doublepost prevention - post automatically merged: ==

Works for me

Thanks @FlyingPotato but it's still a no for me, just keeps coming up " can't reach this page", I'll have to wait for the next one to come along ;)
 

superalbs

Verified Rep - Superalbs Travels
Joined
3 Jul 2014
Messages
2,846
Location
Kraków
I have saved the pages on the internet archive, if anyone is having trouble viewing the page online:
 

Fokx

Established Member
Joined
19 Jul 2019
Messages
1,603
Location
Liverpool
The above website isn’t real or affiliated with the TOC

The fact it uses images of a class 319 from Train Simulator and has a logo drawn on what appears to be Microsoft paint would be the obvious clues
 
Status
Not open for further replies.

Top