The entire project has been dogged by problems and delays
Firstly there were loads of objections as it was the first application by a "real" competitor to quite a lucrative route (the company that originally setup Hull Trains was invited to do so by GNER and the SRA)
However, all of these objections were met, except that of GNER
Once the Track Access was approved in principle, there was the problem of suitable rolling stock
The original plan was for HSTs, but those were no longer available
This caused a delay while other suitable rolling stock was sourced, seeing a proposal based on Class 67s and Mk3 coaches, until new Class 22x units were ordered and delivered
As a result, a revised Track Access application was submitted
Again, GNER objected, and at this stage the East Coast franchise renewal complicated matters
Once that had been resolved, EWS advised that they could no longer supply Class 67s, and GCT had to think out of the box about what rolling stock to use
The best alternative was to purchase their own, use it for 3 years whilst awaiting new rolling stock
That is stage GCT are now at, but the timetable for that was tight, VERY tight!
With a surplus of Mk3a/b coaches available, the best solution was to convert these to HST standard, with a reliable fleet of HST Power Cars
Once the new rolling stock arrived, these could then be cascaded to a new route