3.7 CP4+ ‘go-live’
On completion of (a) fault free running for the first three trains; (b) the trial operations programme and all other readiness activities; and (c) all required safety verification and assurance, the system will then be ready to be accepted by SPT for passenger operations.
To achieve the switchover to the new signalling system and new control room is a significant undertaking.
...
Subject to ANSTA’s successful completion of FFR and submission of all safety verification and assurance documentation, it is expected that this closure will be on Sunday 30 August 2026
Once switched over, this will mark achievement of Configuration Point 4+ (CP4+) and from Monday 31 August, the Subway system will be operating on the new signalling and telecommunication systems from the control room in the new Operational Control Centre.
3.8
Future Customer Experience
...
Platform Screen Doors installed at stations will come into passenger use once CP4+ goes live with up to six of these PSDs providing enhanced levels of passenger safety on our
system.
Following the PSDs at the first stations going into operation, the subsequent PSDs in remaining stations will be commissioned and brought into use immediately following their installation at each station.
The new passenger information system will be introduced and this will consist of automatic audio and visual announcements on the trains as well as at platforms and station concourses and visual information at station entrances. The system will provide consistent and reliable information about the service, including next train times, service changes as well as key safety and emergency messages.
Passenger Help Points in stations and on trains will also come into use when the new system goes live.
These will provide the facility for passengers to contact staff with any general queries or support in case of an emergency.
...
3.13 Programme review
The programme continues to be reviewed and updated. The current delivery estimates are noted below:
...
CPX: Introduction of new fleet to passenger service on legacy signalling system - June 2024 (achieved)
CP4+: New signalling system and Operational Control Centre ready for operation - 30 August 2026
CP5: Platform Screen Doors installed and operational at all stations - Q4 2026
CP6: Ready for Unattended Train Operation - Q1 2027