Freight train derailment in Dundee 28/9/15

Status
Not open for further replies.

Carntyne

Member
Joined
8 Jul 2015
Messages
1,026
6K31 was re-railed around 1515 today and was due to be moved off site. Assessment of the damage now starts!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

marks87

Established Member
Joined
23 Jun 2010
Messages
1,658
Location
Dundee
66603 is on the rear, moving back and forth with 56078 dropping the (no-longer) CWR into the 4ft and it looks like a crane is moving it off to the side. I'll upload some photos when my phone has synced.
 

marks87

Established Member
Joined
23 Jun 2010
Messages
1,658
Location
Dundee


Dropped rails in the 4ft.



Pile of rails at the side



56078



Off into the sunset



With 66603 at the other end
 
Last edited:

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,914
Those look to be very clean cuts on the rails?

Most look like the ends of the long rails and show signs of rust. Only two look like fresh cuts and look like they have been oxy-propane cut.

Cut into lengths like that I doubt they will be scrapped but will find their way to a depot for incorporation into things like points and crossings.
 

Trog

Established Member
Joined
30 Oct 2009
Messages
1,546
Location
In Retirement.
Most look like the ends of the long rails and show signs of rust. Only two look like fresh cuts and look like they have been oxy-propane cut.

Cut into lengths like that I doubt they will be scrapped but will find their way to a depot for incorporation into things like points and crossings.

My guess as to the rails likely fate would be closure rails for use by the local maintainers.
 

snakeeyes

Member
Joined
7 Jun 2011
Messages
214
yesterday I was traveling from Edinburgh to Aberdeen, I had to get off at Dundee and get the replacement bus to Carnoustie why was Broughty Ferry not used?
 

marks87

Established Member
Joined
23 Jun 2010
Messages
1,658
Location
Dundee
yesterday I was traveling from Edinburgh to Aberdeen, I had to get off at Dundee and get the replacement bus to Carnoustie why was Broughty Ferry not used?
Because there's no place to turn back at Broughty Ferry.
 

DarloRich

Veteran Member
Joined
12 Oct 2010
Messages
32,939
Location
Fenny Stratford
I ask because I know from experience that some sites can have rail dropped a year previous due to possession availability and other sites can be dropped one night and a start on installation the same shift.

Yes: the train looked loaded so clearly had not finished it round of deliveries. Therefore some sites might not get their rail unless another train can pick up the slack.
 

DelW

Established Member
Joined
15 Jan 2015
Messages
6,024
Just out of curiosity how much was the load of rails worth?

Since no-one with actual knowledge has come along yet, I'll make a round figures estimate!

In the newspaper photo from above, the rail stack is about 8 wide by 4 high, so 32 rails. I've no way of assessing the length, but allowing for about 1200 feet long, and 100lb/yard, the total weight would be around 570 tons.

Structural steel sections are around £400/ton, so assuming rails are produced in lower volume and need extra hardening etc. probably around £500 - £600 per ton, which would give a total value of around £300k - £350k.

Happy to be corrected by anyone who really knows the answer (or spots any errors above).
 

GB

Established Member
Joined
16 Nov 2008
Messages
6,560
Location
Somewhere
Since no-one with actual knowledge has come along yet, I'll make a round figures estimate!

In the newspaper photo from above, the rail stack is about 8 wide by 4 high, so 32 rails. I've no way of assessing the length, but allowing for about 1200 feet long, and 100lb/yard, the total weight would be around 570 tons.

Structural steel sections are around £400/ton, so assuming rails are produced in lower volume and need extra hardening etc. probably around £500 - £600 per ton, which would give a total value of around £300k - £350k.

Happy to be corrected by anyone who really knows the answer (or spots any errors above).

You will need to amend your estimate...the train was carrying 9x600ft rails.
 

marks87

Established Member
Joined
23 Jun 2010
Messages
1,658
Location
Dundee
The CWR train is now sitting in Dundee yard. It was getting attention from a crane at the back of 5 this evening (lifting the wagons for inspection, perhaps?).

 

Peter Mugridge

Veteran Member
Joined
8 Apr 2010
Messages
17,849
Location
Epsom
You will need to amend your estimate...the train was carrying 9x600ft rails.

Quick back of envelope stuff:

9 x 600ft = 5400ft.

That's 14% of 32 x 1200ft.

So about £42,000 to £49,000 assuming the prices DelW quoted are about right.
 

Trog

Established Member
Joined
30 Oct 2009
Messages
1,546
Location
In Retirement.
CWR usually comes in 709' lengths these days, the rail web sides look to be parallel so the rail is 113A at 113lb per yard.
 

DelW

Established Member
Joined
15 Jan 2015
Messages
6,024
You will need to amend your estimate...the train was carrying 9x600ft rails.

Thanks for the correction, it looked like many more in The Courier's photo but the perspective makes it diffcult to count with any certainty. Not as expensive as I thought then!
 