Could you see if there was any masts east of Cameron Bridge station, or closer to Leven?
There's still nothing east of the bridge over the River Leven at the Diageo plant.

== Doublepost prevention - post automatically merged: ==

Perhaps not the most exciting photos, but the site and compound of the new Mountfeurie bridge, just to the west of the Kirkland yard limits.
 

Attachments

  • 20250906_173153.jpg
    20250906_173153.jpg
    3 MB · Views: 119
  • 20250906_173159.jpg
    20250906_173159.jpg
    3 MB · Views: 118
  • 20250906_173202.jpg
    20250906_173202.jpg
    3.7 MB · Views: 119
Joined
20 Mar 2012
Messages
757
Where exactly is the feeder station at Thornton going to be located. Is it near to the triangle or near the currently disused Thornton yard? Can't seem to find any info on its final location.

Also, when wiring takes place. Do you rekon they Will end just short of Kinghorn/ladybank/Lochgelly or within/beyond the 3 stations as an overrun?
 

moffatcalum

Member
Joined
27 Apr 2024
Messages
30
Location
Burntisland, Fife, Scotland, UK
I could have been misled but I believe the new feeder is planned to be located directly next to Glenrothes SubStation between Collydean & Leslie to the North of Glenrothes.
There is visible evidence that work on site started over 2 years ago on Google Street View & Maps
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
I could have been misled but I believe the new feeder is planned to be located directly next to Glenrothes SubStation between Collydean & Leslie to the North of Glenrothes.
There is visible evidence that work on site started over 2 years ago on Google Street View & Maps
As a resident of Glenrothes, that substation is around 4km at the closest point to the line, and 6.6km from Thornton Junction. Not sure how that would work, unless I'm wrong.
Edit: I've just had a double check with recent planning permissions in that area, and there is no mention in any documents of either a feeder station or any electricity supply going to a railway, sadly.
 

fegguk

Member
Joined
11 Sep 2012
Messages
181
Location
Hawick
You would have thought that the rebuilding of the line would have been to 25kV specification but given the Northern limit, at the South end, is Bowbank Tunnel maybe not. That leaves c10km to recharge the batteries although energy demand on an Edinburgh journey will be reduced compared to Tweedbank direction. Of course they will specify what they want to achieve in BEMU specification but I wonder how much spare capacity the batteries need to retain to deal with operational issues.
The Bowshank tunnel was laid with slab track to have enough clearance for electrification. They claimed at the time that the whole Borders railway was built to enable electrification without having to rebuild structure along the line.
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
The Bowshank tunnel was laid with slab track to have enough clearance for electrification. They claimed at the time that the whole Borders railway was built to enable electrification without having to rebuild structure along the line.
Preparing the full line for full electrification, and then only going partial seems like a waste of time and resources… unless they go back eventually and fill in the gap.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
Preparing the full line for full electrification, and then only going partial seems like a waste of time and resources… unless they go back eventually and fill in the gap.
Whether it was a waste depends on if anything was rebuilt that didn't otherwise need to be. If a bridge needed to be reconstructed anyway, reconstructing it to Electrification clearances isn't a big change in the overall cost.
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,574
The Bowshank tunnel was laid with slab track to have enough clearance for electrification. They claimed at the time that the whole Borders railway was built to enable electrification without having to rebuild structure along the line.
Wasn't that in the days of 2.7m clearances though?
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
There's still nothing east of the bridge over the River Leven at the Diageo plant.

== Doublepost prevention - post automatically merged: ==

Perhaps not the most exciting photos, but the site and compound of the new Mountfeurie bridge, just to the west of the Kirkland yard limits.
Just to backtrack a little bit, was the addition of more masts on the section around Earlseat Junction? If so, then I’ll go down tonight or tomorrow and get some more drone footage.
 

AMD

Member
Joined
6 Dec 2017
Messages
770
There's a couple more at Earlseat, but no specific pattern as to the order they are going up in.
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,235
Well we have seen on other schemes "no apparent pattern too"
If they are doing what they can in the normal overnight access opportunities to begin with then doing the masts nearest to access points is a good strategy - this would also match the high rates of masts going up, the rate will drop the further from the access points they get.
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,455
Location
Preston Lancs
If they are doing what they can in the normal overnight access opportunities to begin with then doing the masts nearest to access points is a good strategy - this would also match the high rates of masts going up, the rate will drop the further from the access points they get.
You have stated perfectly what I was trying to say. Thank you
 

AMD

Member
Joined
6 Dec 2017
Messages
770
Today's mast total is 114.
Four have sprung up between Earlseat junction and the signal protecting it from the Fife line.
As a note, the main yard that the contractors are using is immediately east of Cameron Bridge station.
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
Today's mast total is 114.
Four have sprung up between Earlseat junction and the signal protecting it from the Fife line.
As a note, the main yard that the contractors are using is immediately east of Cameron Bridge station.
Great to hear we are in the triple digits now, they've absolutely SHOT up in the past month!

I wonder if the overheads will terminate just before the junction on this project, or they'll continue onto the mainline as a single overhead and then terminate.

Not actually any added information, but I'm assuming by the double concrete foundations on each side of Cameron Bridge station, that it will be a similar cantilever design to that at Reston, with the portal surrounding the station connected at both sides, with the two droppers in the middle?

EDIT: There seems to be a much larger number closer to Earlseat Jn, and the single line section between there and Thornton Junction has four masts up currently.

== Doublepost prevention - post automatically merged: ==

Here's a video showing the relevant masts on the Leven branch, near Earlseat Junction.

 
Last edited:

AMD

Member
Joined
6 Dec 2017
Messages
770
Masts are up east of Cameron Bridge!
16 have sprouted from Leven station to Kirkland yard and 16 just east of Duniface bridge.
Work has also started on the foundations of the new footbridge at Mountfleurie.
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
New fates of more bridges have been decided in the north of Fife.

Bennochy Road leading to the A925 in Kirkcaldy, is to be demolished and a new bridge to be built in its place. This is expected to begin between July 21st and October 20th of next year, and is to last around 245 working days. (Yikes!)

Thornton’s Main Street on the B9130 is also to be demolished and replaced, beginning between June 15th and September 14th of next year, and is to last an estimated 29 working days.

The date of modification of the over bridge in Coaltown of Balgonie has been moved from November-January start period now to between 05/01/26 and 31/01/26, for the same length of working days.

The bridge on Turnhouse Rd now has a narrowed down estimated start date, commencing between 08/11/25 and 12/12/25 for 37 working days.

Similarly is the Lennymuir bridge a couple hundred metres down the line, which is now to begin modifications between 04/10/25 and 14/10/25.

A new notice on Standingstane Road (Dalmeny) has also been published, stating: “Traffic management only, to facilitate works to create access road in farmers field for works on adjacent railway. Site times 07:00 - 18:00”. This will be to facilitate the bridge demolition happening on a (I think) private road.

The Kirkforthar Feus Road between Markinch and Ladybank is now to be closed for 20 working days between 02/03/26 and 29/04/26.

On a separate note, cable laying at Thornton North Jn has been narrowed down further with the start dates now being within a week of each other (17-25/11/25), and expected to now take only 15 working days rather than 20 odd.

That seems to be all for now, hope that gives people a better insight into NRs current work structure and views.
 

Deepgreen

Established Member
Joined
12 Jun 2013
Messages
7,458
Location
Gomshall, Surrey
This (almost) amused me this morning - a story about electrification showing a diesel train! Yes, I know most readers wouldn't know or care...
Screenshot_20250924_104522_Chrome.jpeg
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
This (almost) amused me this morning - a story about electrification showing a diesel train! Yes, I know most readers wouldn't know or care...
View attachment 188959
Ironic considering our electrification has also been stop-start. Fife electrification was paused numerous times since June of 2022, both for financial and "we don't know what to prioritise" reasons.
 

mcmad

Member
Joined
11 Mar 2015
Messages
1,072
but there has always been something for the team to be working on so it is a continuous pipeline, just flowing a lot slower than promised for financial reasons
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
Another medium sized update. It's probably not new news, but I've just found out so I may as well let others know.

On roadworksscotland.org, I've tallied up a total of 27 individual road work notices around the Glenrothes area, all relating to cables being laid by "SP Energy Networks" and relating to "25kV cables", which screams rail electrification in my opinion.
The vast majority of them are expected to begin in the next couple of months, and some have even started on the B921 "Kinglassie" road. And the latest project start dates are at Bankhead roundabout, which are between 26th of December to the 25th of March next year.

On a seperate note, I seen this post on Facebook by "Levenmouth Building a Railway" about an unrelated reason, where I noticed a pole next to the railway that looked noticeably thicker than the usual lampposts, and am just wondering whether it is an OHL mast?
Screenshot 2025-09-26 163744.png
 

TrainViation

Member
Joined
25 Jun 2025
Messages
292
Location
Glenrothes
In total agreement there; the one nearest the camera looks like a Portal Leg, judging by the hinge pin at the top.
Yes, thank you for confirming this. I'm assuming it'll be a similar sort of idea to that of Reston station, like this:
The_new_Reston_station_on_the_day_of_its_opening%2C_3._23-05-2022.jpg


Just found this too:
 

Attachments

  • 555458046_768790519255531_567242069108247071_n.jpg
    555458046_768790519255531_567242069108247071_n.jpg
    690.3 KB · Views: 57
Last edited:

59CosG95

Established Member
Joined
18 Aug 2013
Messages
6,853
Location
Beeston (Notts)
Yes, thank you for confirming this. I'm assuming it'll be a similar sort of idea to that of Reston station, like this:
The_new_Reston_station_on_the_day_of_its_opening%2C_3._23-05-2022.jpg


Just found this too:
Precisely. NWR has to use portals or TTCs above platforms (some places have used headspans, like Glasgow Queen St), and single track cantilevers are a no-no.
 