Farnworth Tunnel, for one thing.
Darwen for another.
Farnworth Tunnel, for one thing.
From what is freed up from Bolton having half the its normal level of services.
If that means destrenghtening selected services and using the units for strengthening other so be it.
Are new crossovers going to be installed at one or both ends of the tunnel for the single line working?
Both. One at Moses Gate and one just north of Kearsley.
Being one who is also interested in the financial aspects of such matters, what is the current cost budget for installing a crossover.
Anywhere between £300-£700k according to turnout speed.
Kearsley footbridge is up, drawing attention to the mysterious crossing...
By "mysterious crossing" do you mean the patch of new ballast about 20y north of the station? If so, it's a UTX (under track crossing), required to move the cable route into the Down bore before the temporary trap points, crossover and tunnel construction site.
Looking at Platform arrangements for June at MCV whilst attempting to work out the diagrams, it seems as if Man Vic-Clitheroe/Blackpool services will interwork. Does anyone know how many carriages will be put on these routes?
During the period of these tunnel works and associated matter, will any of the railway stations between Manchester and Bolton be closed with no services stopping at them, as I keep hearing "rumours" to that effect.
During the period of these tunnel works and associated matter, will any of the railway stations between Manchester and Bolton be closed with no services stopping at them, as I keep hearing "rumours" to that effect.
Looking at Platform arrangements for June at MCV whilst attempting to work out the diagrams, it seems as if Man Vic-Clitheroe/Blackpool services will interwork. Does anyone know how many carriages will be put on these routes?
That is a shame. I was expecting a four car DMU for Clitheroe services and a six car DMU for the Blackpool North services to max out the use of the available paths. I say four cars for Clitheroe as it maxes out the platform lengths.
Only three cars can be accomodated at Hall Ith Wood, Bromley Cross (despite there being a 4-car marker in the Up - it is only to get the back end of the train clear of the foot crossing), two cars at Entwistle, four cars (150) can just squeeze on at Darwen, and stations north of Blackburn were lengthened five years ago but can still now only just fit 153+156.
Stations north of Blackburn were lengthened five years ago but can still now only just fit 153+156.
Not quite close but this is what's happening at Kearsley on a weekday: http://www.realtimetrains.co.uk/search/advanced/KSL/2015/06/22/0000-2359?stp=WVS&show=all&order=wtt (Only services in Black are stopping and presumably all the replacement buses haven't been added yet.)
See Joseph_Locke's posts #83 & #86 in this thread, regarding temporary platform lengthening on the Blackburn/Clitheroe line.Only three cars can be accomodated at Hall Ith Wood, Bromley Cross (despite there being a 4-car marker in the Up - it is only to get the back end of the train clear of the foot crossing), two cars at Entwistle, four cars (150) can just squeeze on at Darwen, and stations north of Blackburn were lengthened five years ago but can still now only just fit 153+156.