Final report of the 'Northern Sparks' Electrification Taskforce.
To remind of previous publications
Review of electrification
http://www.railnorth.org/wp-content...ication-Task-Force-Baseline-Position-v5.0.pdf
Prioritisation methodology development
http://www.railnorth.org/wp-content...rification-Task-Force-Prioritisation-v5.2.pdf
List of all electrification schemes
http://www.railnorth.org/wp-content...ation-Strategy-Baseline-Review-of-Network.pdf
Final Report
http://www.railnorth.org/wp-content/uploads/2015/03/EFT_Final_Report_FINAL_web.pdf
For those who want to skip to the end.
Tier 1 (recommend immediate start to business case development for inclusion in next CP 2019-2024) 1450 single track km
Calder Valley (Full) 84
Liverpool to Manchester via Warrington Central 80
Southport/Kirkby to Salford Crescent 79
Chester to Stockport 75
Northallerton to Middlesbrough 73
Leeds to York via Harrogate 70
Selby to Hull 70
Sheffield (Meadowhall) to Leeds via Barnsley / Castleford & connections 68
Bolton to Clitheroe 67
Sheffield to Doncaster/Wakefield Westgate (Dearne Valley) 67
Hazel Grove to Buxton 66
Warrington to Chester 64
Tier 2, Considered for electrification post 2024 but light rail alternatives should also be considered. 950 single track km
Manchester to Sheffield and Manchester southeast local services 59
York to Scarborough 53
Bishop Auckland/Darlington to Saltburn and Sunderland 53
Barnsley to Huddersfield 50
Sheffield to Lincoln via Retford 49
Chester to Crewe 47
Burnley to Colne & Kirkham to Blackpool South 45
Knottingley to Goole 45
Tier 3, Should be electrified in the long term but in the short term perhaps modern diesel or alternative traction power improvements should be considered. 1600 single track km
Barrow to Carnforth 38
Pontefract to Church Fenton 38
Hull to Scarborough 38
Ormskirk to Preston 37
Carlisle to Newcastle 36
Skipton to Carlisle 35
Barton on Humber 34
Cumbrian Coast 32
Doncaster to Gilberdyke 32
Cleethorpes to Thorne (Doncaster) 26
Middlesbrough to Whitby 26
Skipton to Heysham 7
Tier 1 schemes have the largest economic impact on the wider economy, they also form a base significantly boosting the marginal cost of follow on schemes. They recommend they are progressed through design and costing immediately so as to be ready to break ground when other schemes finish in 2019/2020. Within this tier is Warrington to Chester however it only makes financial sense if North Wales electrification is progressed otherwise it would be diesel operated beyond some additional Chester-Manchester services.
Tier 2, the major scheme in this phase is South TPE and associated network in South East Manchester. Crewe to Chester would naturally form part of a wider scheme to electrify the WCML to North Wales and possibly HS2 at Crewe, other routes build on Tier 1 schemes to give 100% electrification for the City Regions, Liverpool, Manchester, Leeds and Sheffield. Some routes may well be suited to light rail electrification and we recommend this is looked at with some urgency in light of the Sheffield Tram-train trial.
Tier 3 include most of the long rural routes and some infill routes with limited services such as the Humber which could only be progressed once South TPE was done and should be looked at once the core network is programmed. Ormskirk to Preston and Moorthorpe/Castleford to York would not justify electrification on the basis of the current limited passenger service however perhaps examination should be given to increasing services. Ponterfract is important for freight and as a diversionary route.
To remind of previous publications
Review of electrification
http://www.railnorth.org/wp-content...ication-Task-Force-Baseline-Position-v5.0.pdf
Prioritisation methodology development
http://www.railnorth.org/wp-content...rification-Task-Force-Prioritisation-v5.2.pdf
List of all electrification schemes
http://www.railnorth.org/wp-content...ation-Strategy-Baseline-Review-of-Network.pdf
Final Report
http://www.railnorth.org/wp-content/uploads/2015/03/EFT_Final_Report_FINAL_web.pdf
For those who want to skip to the end.
Tier 1 (recommend immediate start to business case development for inclusion in next CP 2019-2024) 1450 single track km
Calder Valley (Full) 84
Liverpool to Manchester via Warrington Central 80
Southport/Kirkby to Salford Crescent 79
Chester to Stockport 75
Northallerton to Middlesbrough 73
Leeds to York via Harrogate 70
Selby to Hull 70
Sheffield (Meadowhall) to Leeds via Barnsley / Castleford & connections 68
Bolton to Clitheroe 67
Sheffield to Doncaster/Wakefield Westgate (Dearne Valley) 67
Hazel Grove to Buxton 66
Warrington to Chester 64
Tier 2, Considered for electrification post 2024 but light rail alternatives should also be considered. 950 single track km
Manchester to Sheffield and Manchester southeast local services 59
York to Scarborough 53
Bishop Auckland/Darlington to Saltburn and Sunderland 53
Barnsley to Huddersfield 50
Sheffield to Lincoln via Retford 49
Chester to Crewe 47
Burnley to Colne & Kirkham to Blackpool South 45
Knottingley to Goole 45
Tier 3, Should be electrified in the long term but in the short term perhaps modern diesel or alternative traction power improvements should be considered. 1600 single track km
Barrow to Carnforth 38
Pontefract to Church Fenton 38
Hull to Scarborough 38
Ormskirk to Preston 37
Carlisle to Newcastle 36
Skipton to Carlisle 35
Barton on Humber 34
Cumbrian Coast 32
Doncaster to Gilberdyke 32
Cleethorpes to Thorne (Doncaster) 26
Middlesbrough to Whitby 26
Skipton to Heysham 7
Tier 1 schemes have the largest economic impact on the wider economy, they also form a base significantly boosting the marginal cost of follow on schemes. They recommend they are progressed through design and costing immediately so as to be ready to break ground when other schemes finish in 2019/2020. Within this tier is Warrington to Chester however it only makes financial sense if North Wales electrification is progressed otherwise it would be diesel operated beyond some additional Chester-Manchester services.
Tier 2, the major scheme in this phase is South TPE and associated network in South East Manchester. Crewe to Chester would naturally form part of a wider scheme to electrify the WCML to North Wales and possibly HS2 at Crewe, other routes build on Tier 1 schemes to give 100% electrification for the City Regions, Liverpool, Manchester, Leeds and Sheffield. Some routes may well be suited to light rail electrification and we recommend this is looked at with some urgency in light of the Sheffield Tram-train trial.
Tier 3 include most of the long rural routes and some infill routes with limited services such as the Humber which could only be progressed once South TPE was done and should be looked at once the core network is programmed. Ormskirk to Preston and Moorthorpe/Castleford to York would not justify electrification on the basis of the current limited passenger service however perhaps examination should be given to increasing services. Ponterfract is important for freight and as a diversionary route.