You seem to have missed the words "will include". The list of eight was:
a. Not exhaustive - as should be obvious just looking at it and bearing in mind that none of the lines listed is a self-contained island operationally anyway
b. Not proscriptive. The DfT announcement began with the following line, which would be hard to surpass for vagueness so to suggest that the DfT was giving any kind of steer about any particular routes is reading too much into things from where I'm sitting. Especially when the terms of reference were as follows - taken from the report (page 49)
Whatever the wording, the initial list
was seen as prescriptive when the original press release was issued and there was an immediate reaction from local authorities, MPs and Rail User Groups (e.g, see
here). There was an Early Day Motion passed in the Commons requesting the Calder Valley line to be added to the list.
here.
Presumably someone higher up in the government got the message as a result of lobbying and the task force led by DfT/Network Rail quietly became a task force led by MPs/Rail North with TOC/NR/DfT involvement and its remit became to compare all lines in the North. This is what I meant by MPs/council leaders usurping the DfT/Network Rail. It appears that the DfT lost out because of their apparent arrogance in releasing a press release which could be read as we are going to set up a task force to look at this for a year, but we've already decided the results (perhaps I've been watching too much Yes Minister!).
See the report for the factors and here is a map showing the Rail North area, just in case you think they were looking at routes they shouldn't have - they actually ignored the northern bit of the Midlands for the report -
http://www.railnorth.org/wp-content/uploads/2013/12/Rail-North-Lines-and-stations.pdf
c. The task force had representatives from DfT and Network Rail on it, the following is from the terms of reference in the report. Reports like this do not appear without all-round agreement, it's not some sort of parliamentary committee where MPs who don't like a committee's findings issue a dissenting view, so the idea that the MPs and councillors imposed their will on DfT and NR is silly - as will probably be clear once the new Network Rail electrification study appears any time now.
I didn't mean to imply that the MPs/council leaders imposed their will on the results of the task force at all. IIRC the steering group only met 4 times and I don't suppose did much more than review the methodology to be used against their remit and requirements, progress and then the results (then wrote the introduction for the report). The work and the actual scoring (and therefore the results) and the writing of the report was carried out by the "officers" of the task force - from Rail North/ToCs/DfT and Network Rail.
--- old post above --- --- new post below ---
Look at the publically available GRIP process documentation. it is all there
I havent looked at the GRIP documentation in some time, but from what I recall its a fairly standard methodology for delivering projects and has
no relevance whatsoever to exercises like this, where the remit was to establish the priorities of the taxpayer who will be funding this investment.
Indeed the output of the study is a list of recommended projects that should go forward to the initial stages of the GRIP process.
You still haven't provided any insight as to how the DfT/Network Rail came up with the 8 lines they listed in their initial press release. However they drew up the list, it seems to have cost them the leadership of the task force. To me this is the very opposite of common sense, more like naivety.
--- old post above --- --- new post below ---
You still haven't provided any insight as to how the DfT/Network Rail came up with the 8 lines they listed in their initial press release. However they drew up the list, it seems to have cost them the leadership of the task force. To me this is the very opposite of common sense, more like naivety.
Okay, I'm replying to myself here but the quote below appears to summarise the main differences between the rail industry's methodology and that of the task force. Its not surprising that if you change the prime objective from diesel kms replaced per kms of electrification to impact on the regional economy, that results are different!
As a said before a change from the inward looking view of the rail industry to what taxpayers want for their investment.
Working Paper 2 said:
Network Rail (NR) have used the diesel kms replaced per km of electrification as their core indicator of priority in work for the Electrification RUS refresh. In that work they have continuously recalculated this for each route, as they progress down a ranked list, on the basis that electrification of higher ranking routes has already been carried out. This tends to improve the priority for some lines from lower down the list, where services also operate on the higher ranked routes, as the diesel kms replaced for each km of electrification needed for the lower ranked line is greater.
As noted earlier this indicator covers a broad range of issues. However it does not directly address the local objectives for the rail network in the North of England (as set out in the LTRS), which are:
- Supporting sustainable economic growth;
- Enhancing service quality, improving the appeal of rail and, by encouraging more rail use, reducing environmental impacts and carbon emissions; and
- Improving efficiency, reducing the cost per passenger and per tonne of freight carried.
To better, and more explicitly, address these objectives three separate prioritisation criteria are suggested:
- The primary criterion should be the impact on the regional economy. This should take into account both the immediate benefits from replacing diesel with electric traction on a like for like basis and also the more far reaching benefits of seeing electrification as a catalyst for the transformation of both the quality and frequency of many local services. This takes electrification as the enabler for all the wider changes that are needed - journey time improvements, frequency augmentation and quality enhancements – and so looks forward to the benefits against the current base which could accrue from this wider package of change as an indicator of priority.
- The diesel kms replaced per km of electrification (Impact on services) indicator is suggested as the secondary criterion, but at a more disaggregate level than has been hitherto reported by Network Rail. As noted previously, this will act as good proxy for a range of other indicators (including core environmental benefits) which capture the benefit derived by the North of England from electrification. It captures two of the core objectives – enhancing quality and improving efficiency – and so is a simple measure of the impact of the scheme on the rail service.
- Finally, the requirement for replacement of rolling stock which cannot be economically ‘life extended’ and the enhancement of the fleet is brought to bear, taking into account the options for cascading stock, either diesel or electric, from elsewhere. This criterion should also include consideration of the additional rolling stock capacity required on each line, both now and in the future, in line with the economic aspirations emerging from One North: A Proposition for an interconnected North and the current high levels of dissatisfaction with overcrowding.