East Kilbride/Barrhead electrification updates

Status
Not open for further replies.

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,492
Location
Moorpark, CA
Exactly - Surge Diverters (aka Surge Arresters) are precisely what those are.

For those who don't know what the purpose of the Surge Diverter, it acts as an insulator up to a set threshold (typically 300% of the supply voltage).
If that threshold is breached, it becomes a conductor, allowing current to flow safely to earth rather than arcing across the air gaps and damaging the bridge soffit.

Note the little doobry beneath the 2 insulators on the same stovepipe - this doobry is an "actuation counter", which clocks up the number of overvoltage events.
There should also be a "drop-out fuse" between the Surge Diverter and traction earth, but that doesn't appear to have been fitted at the time the picture was taken.

(This has been adapted from the excellent "Overhead Line Electrification for Railways" (6th Edition), Section 10.8.1, page 56; all credit to Garry Keenor)
Great summary, and easily understood by a retired Signal Engineer!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

Trackbasher84

Member
Joined
25 Apr 2023
Messages
13
Location
Glasgow
The runoff from Busby Junction seems to go most of the way to Thornliebank Bridge. This was built when the Barrhead route was electrified.

I'm not sure if it will be possible to isolate the East Kilbride branch from the Barrhead electrification. My understanding is that the branch will be fed from the Barrhead line which itself is fed from the upgraded feeder station at Eglinton Street via cables to the feed in point at Muirhouse North Junction. So, no further interventions required for the supply.

When I was at the opening ceremony for the Thornliebank Bridge on Tuesday, engineers were working on the twin track cantilever just before bridge (on the Busby Junction side of the bridge) which was not far from OHL that I assume is live.

A Sunday would be a good day to tie in the branch - there are no EMU Barrhead stoppers on a Sunday and so the Barrhead line could be isolated without an impact on the Glasgow - Barrhead - Kilmarnock services.
If anyone was working you can be assured it was dead, we don't allow work near adjacent live structures in this civilised country. Switching at various points along the new electrification.

== Doublepost prevention - post automatically merged: ==

Can’t be much left to do, connecting up at Busby junction?
Heard they're onto snagging works now but not due to be live until December at the earliest

== Doublepost prevention - post automatically merged: ==

Probably best to ask Gareth Dennis about any of this
 
Last edited:

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
New planning application at Clarkston station for path to the Goods Yard car park. Notably the path goes underneath the footbridge before meeting the car park.
Thanks for posting the link to the planning application for the new footpath (which I note is 130m in length). If it’s of interest, here’s an image from Google showing where the new path will pass underneath the footbridge and tie in with the existing path to/from the car park:-
 

Attachments

  • IMG_5704.jpeg
    IMG_5704.jpeg
    1,008 KB · Views: 115

apjsco

Member
Joined
24 Feb 2024
Messages
19
Location
Glasgow
If anyone was working you can be assured it was dead, we don't allow work near adjacent live structures in this civilised country. Switching at various points along the new electrification.

== Doublepost prevention - post automatically merged: ==


Heard they're onto snagging works now but not due to be live until December at the earliest

== Doublepost prevention - post automatically merged: ==

Probably best to ask Gareth Dennis about any of this
In terms of things left to finish: the new pedestrian footbridge at Giffnock Station was supposed to open last week, but it’s still not ready. There's been no official word on when it might reopen, and from what I can see walking past it daily, there doesn’t seem to be much happening on-site. A neighbour mentioned they heard from people working on site that the station works are about a month behind schedule, which is a bit surprising considering the weather's been mostly dry—so it seems like there might be other factors causing delays.

Living right beside the station, I really rely on that bridge to get around—especially for everyday errands and reaching Fenwick Road, since it's the main and well used connection from this side of town. Not having access has been a real hassle, especially on top of needing to find alternative ways to commute by train from Williamwood on packed trains. And with the Thornliebank Road bridge also having been out of action for a while (thankfully now reopened), local traffic has been a bit of a nightmare. My neighbours and I are definitely looking forward to seeing all these works finally wrapped up soon.
 

Attachments

  • IMG_4961.jpeg
    IMG_4961.jpeg
    598.5 KB · Views: 63
Last edited:

d9009alycidon

Member
Joined
22 Jun 2011
Messages
980
Location
Eaglesham
Attached notice being distributed via local Facebook groups etc. Doesn't specify whether services will operate from the new Hairmyers Station or not. Given that the Redwood Drive roadworks look a fair was from completion and the car park looks as if there is still a lot of work to do.
 

Attachments

  • FB_IMG_1746715418087.jpg
    FB_IMG_1746715418087.jpg
    166.3 KB · Views: 119

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
The last NR press release said that although the new station will be open ( I don't think the old Hairmyres could be) it was clear that much of the new car park ( which is a Council project ) would not be complete until the autumn
 

Xenophon PCDGS

Veteran Member
Joined
17 Apr 2011
Messages
35,385
Location
A typical commuter-belt part of north-west England
The last NR press release said that although the new station will be open ( I don't think the old Hairmyres could be) it was clear that much of the new car park ( which is a Council project ) would not be complete until the autumn
Noting what you say, how many car park spaces would be available when the new Hairmyres station opens?
 

alxndr

Established Member
Joined
3 Apr 2015
Messages
1,672
The last NR press release said that although the new station will be open ( I don't think the old Hairmyres could be) it was clear that much of the new car park ( which is a Council project ) would not be complete until the autumn
The platform edge at the old station was away when I was there a few weeks ago so it’s the new station or nothing. The new station itself looks largely complete, there’s just the mess either side.
 

kkong

Member
Joined
8 Sep 2008
Messages
1,125
The anticipated final cost of the East Kilbride Rail Enhancement project is now £143.7m.

Source: page 8 of the letter from the Director General of the Scottish Exchequer to the Scottish Parliament's Public Audit Committee.

Project: East Kilbride Rail Enhancement

Business case approved stages:

Project is part of the East Kilbride and Barrhead Rail Enhancement scheme.
The scheme will make rail services reliable, efficient, and attractive to passengers and support modal shift whilst progressing against the Scottish Government’s target to decarbonising the rail network.
The OBC outlined that total project cost was estimated to be £100 million to £120 million and that it was estimated to be operational in December 2024.
The FBC outlined that total project cost was estimated to be £139.8 million and that it was estimated to be operational in December 2025.

Progress at August 2024:
No change to FBC cost or timing since the last report.

Progress at February 2025:
No change to FBC timing since the last report.
The Anticipated Final Cost is now £143.7 million which is an increase to that at FBC and as previously reported.
This is mainly a consequence of Transport Scotland requiring to contribute towards the delivery of Hairmyres Station Car Park.
 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
Does anyone know if there are any plans for a retail unit in the new Hairmyers station?
 

InOban

On Moderation
Joined
12 Mar 2017
Messages
4,537
Interesting. Haimyres station car park drove the cost up.
I'm not sure that's true. The carpark was being funded by the Council but it can no longer afford the full cost so NR are paying some of the it. In a sense the ScoGov is bailing out the Council.
 

OB23Gone

Member
Joined
22 Aug 2022
Messages
186
Location
Glasgow
In terms of things left to finish: the new pedestrian footbridge at Giffnock Station was supposed to open last week, but it’s still not ready. There's been no official word on when it might reopen, and from what I can see walking past it daily, there doesn’t seem to be much happening on-site. A neighbour mentioned they heard from people working on site that the station works are about a month behind schedule, which is a bit surprising considering the weather's been mostly dry—so it seems like there might be other factors causing delays.

Living right beside the station, I really rely on that bridge to get around—especially for everyday errands and reaching Fenwick Road, since it's the main and well used connection from this side of town. Not having access has been a real hassle, especially on top of needing to find alternative ways to commute by train from Williamwood on packed trains. And with the Thornliebank Road bridge also having been out of action for a while (thankfully now reopened), local traffic has been a bit of a nightmare. My neighbours and I are definitely looking forward to seeing all these works finally wrapped up soon.
Was told today 10-May that Tue 13th would see access across the line available again. Fencing on platform 2 to be completly installed, some signage to be put up, some lighting to be installed, parts of platform tarmac to be attended to. Would imagine sone sprucing up works will also be required

== Doublepost prevention - post automatically merged: ==

Redwood Dr Was accessible From Eaglesham Road End on Friday 09-05-2025. Looks like the Greenhills Round-about will be being replaced with a Traffic Lights Controlled Junction (sorry if this is Old Hat). There were a couple of temporary lights sections set up on the road. The Traffic lights for the Station South Car Park are installed and look ready to go as soon as the car park becomes operational. Some Panoramic photos of the South Station side and car park. Also 1 of some works carried out to the Old Hairmyres Station Platform.

== Doublepost prevention - post automatically merged: ==

See we now have a New Junction on the EK Branch. Hairmyres East Jn where the line splits for the extended Loop and The New Hairmyres Station
 

Attachments

  • 1 Giffnock Station Stairways.jpg
    1 Giffnock Station Stairways.jpg
    571 KB · Views: 197
  • 2 Giffnock Sat 10-05-2025 Finishing Works.jpg
    2 Giffnock Sat 10-05-2025 Finishing Works.jpg
    726 KB · Views: 187
  • 1  Hairmyres Sth Car Park Entrance.jpg
    1 Hairmyres Sth Car Park Entrance.jpg
    650.5 KB · Views: 132
  • 2 Panorama 2.jpg
    2 Panorama 2.jpg
    480.5 KB · Views: 136
  • 3 Panorma 3.jpg
    3 Panorma 3.jpg
    403.6 KB · Views: 136
  • 4 Panorama 4 Fri 09-05-025.jpg
    4 Panorama 4 Fri 09-05-025.jpg
    511.5 KB · Views: 137
  • 5 Panorama 5.jpg
    5 Panorama 5.jpg
    462.7 KB · Views: 138
  • 6 Panorama 6.jpg
    6 Panorama 6.jpg
    458.4 KB · Views: 136
  • 7 Panorama Coach Turning.jpg
    7 Panorama Coach Turning.jpg
    536.1 KB · Views: 147
  • 8 Old Hairmyres Platform Works.jpg
    8 Old Hairmyres Platform Works.jpg
    554.6 KB · Views: 150
Last edited:

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,574
Something that just occurred to me: has the ‘old’ Hairmyres station been formally closed procedurally?
I don't think you need to issue a closure just to move the platforms a bit. Didn't happen in the case of Morley anyway
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,492
Location
Moorpark, CA
I don't think you need to issue a closure just to move the platforms a bit. Didn't happen in the case of Morley anyway
That’s what I had wondered about. Long time ago, but when Partick Hill was replaced by Partick (literally across the road), I think BR had to formally close Partick Hill.
 

takno

Verified Rep - Traksy
Joined
9 Jul 2016
Messages
6,574
That’s what I had wondered about. Long time ago, but when Partick Hill was replaced by Partick (literally across the road), I think BR had to formally close Partick Hill.
There does seem to be a degree of inconsistency. I'm not sure if there's a maximum distance, or rules about what lines it is on, or whether the change in name makes it more convenient. Hell, BR might even have managed to get somebody to cough up a grant or tax break for a new station which they couldn't get for a refurbishment.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,398
Location
Northampton
There does seem to be a degree of inconsistency. I'm not sure if there's a maximum distance, or rules about what lines it is on, or whether the change in name makes it more convenient. Hell, BR might even have managed to get somebody to cough up a grant or tax break for a new station which they couldn't get for a refurbishment.
I think there is a specified distance, and IIRC it's 400m or 1/4mile. I might be completely wrong though!
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,492
Location
Moorpark, CA
I think there is a specified distance, and IIRC it's 400m or 1/4mile. I might be completely wrong though!
The distance between ‘old’ and ‘new’ Hairmyres is generally quoted as 600m. Maybe there’s some sort of “get out” for what is essentially a relocation?
 

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
https://www.legislation.gov.uk/ssi/2025/81/made
Scottish Statutory Instruments

2025 No. 81​

Transport

The Railway Closure (Exclusion) (Hairmyres) Order 2025​

Made
19th March 2025
Laid before the Scottish Parliament
21st March 2025
Coming into force
18th May 2025
The Scottish Ministers make the following Order in exercise of the powers conferred by section 38(1)(c) of the Railways Act 2005(1) and all other powers enabling them to do so.

Citation, commencement and interpretation​

1.—(1) This Order may be cited as the Railway Closure (Exclusion) (Hairmyres) Order 2025 and comes into force on 18 May 2025.
(2) In this Order, “the station at Hairmyres” means the railway station situated adjacent to Eaglesham Crescent, Hairmyres, South Lanarkshire, G75 8SW.

Exclusion from application of section 30 of the Railways Act 2005​

2. The station at Hairmyres is excluded from the application of section 30(2) of the Railways Act 2005.
FIONA HYSLOP
A member of the Scottish Government
St Andrew’s House,
Edinburgh
19th March 2025

EXPLANATORY NOTE​

(This note is not part of the Order)
Section 30 of the Railways Act 2005 provides for a closure procedure where there is a proposal by a funding authority to close a station. Section 38 of that Act enables the exclusion of stations from that procedure and article 2 of this Order excludes the station at Hairmyres, in the local government area of South Lanarkshire, from the procedure. The station at Hairmyres is being relocated as part of the East Kilbride Enhancement Project.
No Business and Regulatory Impact Assessment has been prepared for this Order as no impact upon business, charities or voluntary bodies is foreseen.
A Childs Rights and Wellbeing Impact Assessment has been prepared and can be viewed at https://www.legislation.gov.uk.
(1)
2005 c. 14.
(2)
Section 30 was amended by S.I. 2015/1682 and S.I. 2018/631.
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,492
Location
Moorpark, CA
Basically, it’s “We don’t have to formally close it, and here’s why”. Fair enough. Some common sense for once!
 

d9009alycidon

Member
Joined
22 Jun 2011
Messages
980
Location
Eaglesham
The order states "no impact to businesses". Quite sure the owners of the shop on the old station platform would dispute that. Wonder if they have been offered any compensation as they are bound to suffer a significant drop in trade
 

apjsco

Member
Joined
24 Feb 2024
Messages
19
Location
Glasgow
Giffnock footbridge now opening SUNDAY
Surprise, surprise! I’m not sure what’s gone wrong at Giffnock station, but I’d be genuinely surprised if they manage to pull things together in time for Sunday’s reopening. The site is in disarray, and progress has been noticeably slower compared to the rest of the project. Large crates of Stannah equipment have been sitting untouched at the Forres Avenue site entrance since march.
 

deerokus

Member
Joined
30 Sep 2024
Messages
45
Location
Glasgow
Yes I'd be very surprised if it's open by then, it doesn't look close to finished, there were guys still working on the bridge today when I went past.
 

hux385

Member
Joined
25 Apr 2023
Messages
178
Location
Edinburgh
There are some testing runs happening along the line today with 156s according to RealTime Trains. I assume this is for staff training with the new platform layouts in particular at Hairmyres?
 

Southsider

Member
Joined
10 Aug 2015
Messages
937
There are some testing runs happening along the line today with 156s according to RealTime Trains. I assume this is for staff training with the new platform layouts in particular at Hairmyres?
They’ve been going up and down all morning, a two, a four and a six car. Oddly, they seem quieter than before.
 