I don’t know if you ever experienced it in a 1st generation DMU: it was worse…..

== Doublepost prevention - post automatically merged: ==


Biggest problems I see from my non-civil engineering perspective are Clarkston Toll (major road) and Thorntonhall (right next to the station). Everything else should be relatively straightforward including getting rid of redundant bridges (I think a couple near Hairmyres were removed recently). Beyond Hairmyres, the bridges are modern and shouldn’t present any clearance issues.
The fact that there are two, low, arched bridges either end of Clarkston station is an interesting problem. No simple diversion routes for large vehicles if they’re replaced, track lowering would require platform lowering.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,689
Location
Scotland
The fact that there are two, low, arched bridges either end of Clarkston station is an interesting problem. No simple diversion routes for large vehicles if they’re replaced, track lowering would require platform lowering.
You don't happen to know what the local rainwater drainage is like? Is lowering even an option?
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
As I've said several times before, for the B767 the obvious solution is to realign it onto a new bridge.
 
Joined
14 Mar 2021
Messages
211
Location
Glasgow
At Barrhead station, the temporary road traffic signals have been removed (they were there when a low loader was parked outside the station on Paisley Road).

There is a new foundation on the Carlibar Road (main entrance) side of the station.

The short term parking bay that was used for the Rail Replacement Bus is now fenced in and in use as a temporary compound. Apparently, the bus contractor was not informed of this decision and so they need to change their pick up and drop off point, otherwise their coaches obstruct the road.


Barrhead Station Electrical Substation.jpgBarrhead Station new foundation.jpg
 

kaysha

Member
Joined
24 May 2023
Messages
36
Location
Falkirk
I don’t know if you ever experienced it in a 1st generation DMU: it was worse…..
Yes I did! When I started work in 1975 and used the train to get to work I think it took the thick end of 1/2 hour to travel the short distance from Glasgow to Clarkston. If travelling outwith the rush hour the bus was always quicker and more frequent. It was only one train an hour and no Sunday service then.
 

MadMac

Established Member
Joined
13 Jun 2008
Messages
1,498
Location
Moorpark, CA
The fact that there are two, low, arched bridges either end of Clarkston station is an interesting problem. No simple diversion routes for large vehicles if they’re replaced, track lowering would require platform lowering.
The one at the Busby end doesn’t look as if a period of closure would present that much of a problem, leading to housing with other ways in. Clarkston Road would be a difficult matter with no easy diversion around it. Like others, I’m surprised that there’s been little information out there as yet.
 

sannox

Member
Joined
1 Mar 2016
Messages
650
The one at the Busby end doesn’t look as if a period of closure would present that much of a problem, leading to housing with other ways in. Clarkston Road would be a difficult matter with no easy diversion around it. Like others, I’m surprised that there’s been little information out there as yet.
Clarkston Road is probably off-line construction, move to new bridge and then demolish old one.
 

Southsider

Member
Joined
10 Aug 2015
Messages
937
There's not really the space to move to a new one while the old one is still there.
It depends on the alignment that is used. A diagonal from before the existing bridge to the roundabout seems feasible. It would also make it easier for buses and HGVs to negotiate.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
We seem to have had this discussion about Clarkston Road several times in the history of this thread. To me it seems obvious that there's plenty of room to build a new bridge clear of the existing one and improving the alignment of the road. You might have to take a bit of land from the adjacent car park, and once the new bridge is in structurally complete there might need to be road closures while you divert first mains services and then traffic onto it.

Of course this doesn't prove it will be done that way. The local authority may be unable to contribute money on the scale needed.


Link is to Google satellite view of the area.
 

nlogax

Established Member
Joined
29 May 2011
Messages
6,035
Location
Mostly Glasgow-ish. Mostly.
The short term parking bay that was used for the Rail Replacement Bus is now fenced in and in use as a temporary compound. Apparently, the bus contractor was not informed of this decision and so they need to change their pick up and drop off point, otherwise their coaches obstruct the road.

Discovered this on Saturday when I went to use the RRB, and this appeared to be a surprise to the assistants on the ground. The Glasgow-bound fast bus had to park at bottom of the ramp to the recycling centre and they had to marshal us across the street to board it.
 

snowball

Established Member
Joined
4 Mar 2013
Messages
8,144
Location
Leeds
A web search found this video, "Glasgow to Barrhead Electrification - Week 1 Update", dated today.

 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
So they are reopening the underpass as a replacement for the footbridge? Nitshill isn’t the nicest area, which might give a clue as to why the underpass was closed in the first place.
 

380101

Member
Joined
18 Feb 2015
Messages
1,141
So they are reopening the underpass as a replacement for the footbridge? Nitshill isn’t the nicest area, which might give a clue as to why the underpass was closed in the first place.

I believe they are still installing a new, OHLE compliant, footbridge. The underpass re-opening will allow the Up side platform to be fully accessible again for all users.
 

clc

Established Member
Joined
31 Oct 2011
Messages
1,326
I believe they are still installing a new, OHLE compliant, footbridge. The underpass re-opening will allow the Up side platform to be fully accessible again for all users.
Thanks, that’s good go hear.
 
Joined
14 Mar 2021
Messages
211
Location
Glasgow
The stone masons have been working on-site at the Moray Place footbridge building the stone cladding on the footbridge abutments.


Moray Place footbridge 1.jpgMoray Place footbridge 2.jpgMoray Place footbridge 4.jpg
 

OB23Gone

Member
Joined
22 Aug 2022
Messages
186
Location
Glasgow

Attachments

  • 1.jpg
    1.jpg
    633.6 KB · Views: 74
  • 2.jpg
    2.jpg
    492.1 KB · Views: 74

Rick1984

Member
Joined
23 Aug 2012
Messages
1,145
Moray Place footbridge 1.jpg
Space looks very tight between front of steps and railings
 

OB23Gone

Member
Joined
22 Aug 2022
Messages
186
Location
Glasgow
I believe they are still installing a new, OHLE compliant, footbridge. The underpass re-opening will allow the Up side platform to be fully accessible again for all users.
NO NEW Footbridge. Went along to the Drop In. Asked NR Rep that very question answer was A NO. Met a Surveyor today just coming of Nitshill Station and his answer about a new bridge and got a NO again.
So looks like the locals will only have the Under pass as their option. Post #1429 has the Layouts
 

Attachments

  • 1.jpg
    1.jpg
    589.9 KB · Views: 89
  • 2 A Good Amount Of Landscapin Required.jpg
    2 A Good Amount Of Landscapin Required.jpg
    672.6 KB · Views: 88

N1

Member
Joined
10 Aug 2022
Messages
385
NO NEW Footbridge. Went along to the Drop In. Asked NR Rep that very question answer was A NO. Met a Surveyor today just coming of Nitshill Station and his answer about a new bridge and got a NO again.
So looks like the locals will only have the Under pass as their option. Post #1429 has the Layouts
As a local user of the station I think that is fine as long as there are some improvements to the pavement around the underbridge. Also, they do something to move the pigeons, it is a good few inches of leavings around the underside of the bridge beams.
 

yorkie

Forum Staff
Staff Member
Administrator
Joined
6 Jun 2005
Messages
78,379
Location
Yorkshire
Just a gentle reminder to stick to infrastructure updates in this thread please.

To discuss rolling stock provision, timetabling, staffing or any other topic, please create a new thread (or use an existing thread, if there is one), thanks :)
 

JModulo

Member
Joined
17 Nov 2013
Messages
588
Location
67A
Being directly affected by this pretty much every day of the week, I can say the bus service has been reliable.

On the passing in the bus, I see the wires are up till (atleast) Nitshill.
 
Joined
14 Mar 2021
Messages
211
Location
Glasgow
On the passing in the bus, I see the wires are up till (atleast) Nitshill.
The wire run on the Down Barrhead from Crossmyloof Gardens to Kennishead hasn't been done.

At Priesthill & Darnley station the contractors are renewing the platform surfaces. I don't know if this work was needed for gauge clearance for the EMUs or the blockade is a convenient opportunity to deliver this improvement. The pedestrian overbridge (a redundant masonry arch road bridge) is closed while they build new parapets of engineer's bricks inside the old stone parapets.

So they are reopening the underpass as a replacement for the footbridge? Nitshill isn’t the nicest area, which might give a clue as to why the underpass was closed in the first place.
The old pedestrian footbridge has gone. The pedestrian underpass is beside the road underpass (see photo).

At Barrhead, beside the short stay car park they built a new brick column as a foundation for a mast. On the other side of the main entrance to the station, they have poured a concrete column.
 

Attachments

  • Barrhead brick column.jpg
    Barrhead brick column.jpg
    1.6 MB · Views: 115
  • Barrhead concrete column.jpg
    Barrhead concrete column.jpg
    1.3 MB · Views: 113
  • Barrhead platform extension.jpg
    Barrhead platform extension.jpg
    1.8 MB · Views: 113
  • Nitshill mining disaster.jpg
    Nitshill mining disaster.jpg
    2.2 MB · Views: 111
  • Nitshill underpass.jpg
    Nitshill underpass.jpg
    1.5 MB · Views: 104
  • Nitshill VC memorial.jpg
    Nitshill VC memorial.jpg
    1.7 MB · Views: 111

nlogax

Established Member
Joined
29 May 2011
Messages
6,035
Location
Mostly Glasgow-ish. Mostly.
At Barrhead, beside the short stay car park they built a new brick column as a foundation for a mast. On the other side of the main entrance to the station, they have poured a concrete column.

Great photos, thank you. Certainly answers my question of 'is anything visible from the e/b Barrhead ramp? '.. quite rightly the entire thing is closed!
 