• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Double Slips

Status
Not open for further replies.

ABB125

Established Member
Joined
23 Jul 2016
Messages
4,331
Location
University of Birmingham
Normally when two tracks cross you'll have a fixed diamond, with 4 gaps at the corners for the flanges. A switched diamond eliminates the gaps allowing higher-speed running but at the cost of essentially being two sets of stub-ended points adjacent to each other, requiring interlocking and point motors. https://upload.wikimedia.org/wikipedia/commons/f/f0/Switchdiamond.jpg

A double slip allows trains on one track to switch to the track crossing at the diamond. Because of the amount of extra metalwork involved (point blades and curved rails), a switched diamond would be very difficult to maintain and inspect. Here's a photo of a double slip with normal diamond: https://upload.wikimedia.org/wikipedia/commons/7/78/Double_slip_at_Munich_central.jpg
Here's a photo of a double slip with swtiched diamond: https://www.pinterest.co.uk/pin/328129522830439800/
Ah ok, thanks!
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,897
Normally when two tracks cross you'll have a fixed diamond, with 4 gaps at the corners for the flanges. A switched diamond eliminates the gaps allowing higher-speed running but at the cost of essentially being two sets of stub-ended points adjacent to each other, requiring interlocking and point motors. https://upload.wikimedia.org/wikipedia/commons/f/f0/Switchdiamond.jpg

A double slip allows trains on one track to switch to the track crossing at the diamond. Because of the amount of extra metalwork involved (point blades and curved rails), a switched diamond would be very difficult to maintain and inspect. Here's a photo of a double slip with normal diamond: https://upload.wikimedia.org/wikipedia/commons/7/78/Double_slip_at_Munich_central.jpg
Here's a photo of a double slip with swtiched diamond: https://www.pinterest.co.uk/pin/328129522830439800/
On the face of it, the angle of the obtuse doesn't seem to be shallow enough to demand the installation of a switch diamond, so why have they gone to all the extra expense and maintenance problems of installing one?
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
On the face of it, the angle of the obtuse doesn't seem to be shallow enough to demand the installation of a switch diamond, so why have they gone to all the extra expense and maintenance problems of installing one?
I'd love to know, but it's a handy photo to find!
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,549
Location
Torbay
Normally when two tracks cross you'll have a fixed diamond, with 4 gaps at the corners for the flanges. A switched diamond eliminates the gaps allowing higher-speed running but at the cost of essentially being two sets of stub-ended points adjacent to each other, requiring interlocking and point motors.
As the crossing angles reduce in faster layouts, the flange gaps in preferred fixed diamond crossings get larger and eventually exceed safety limits, necessitating provision of the complex switched variety instead. Unfortunately, those short stub switches are notoriously difficult to maintain in adjustment, with the slightest bit of heat expansion often causing detection failure. Hence they were some of the first bits of infrastructure to receive the white rail painting treatment, which reflects sunlight and limits heat gain.
 

zwk500

Veteran Member
Joined
20 Jan 2020
Messages
18,401
Location
Northampton
As the crossing angles reduce in faster layouts, the flange gaps in preferred fixed diamond crossings get larger and eventually exceed safety limits, necessitating provision of the complex switched variety instead. Unfortunately, those short stub switches are notoriously difficult to maintain in adjustment, with the slightest bit of heat expansion often causing detection failure. Hence they were some of the first bits of infrastructure to receive the white rail painting treatment, which reflects sunlight and limits heat gain.
Indeed. I assume that's also why they're being progressively replaced with pairs of crossovers?
 

Big Jumby 74

Established Member
Joined
12 Feb 2022
Messages
2,217
Location
UK
This is for one of you good people who understands the engineering side of track work/maintenance better than I. I appreciate the basics, but more from an operational (train planning angle), as in what could one achieve to maximise train movements with the infrastructure in situ (past tense, now retired, so purely out of interest now).

During the planning stages of the 10 car suburban railway on the South Western (SWT as it was), back in 2014, the lack of stabling capacity (at that time) required some alternative thinking, as in how could certain ECS trains be re-routed to form their a.m. peak start up services, without a complete timetable re-write.
It became clear very early on that the various implications of running 10 car vice 8 car, ECS paths Westbound down the Windsor lines, early morning out of Clapham Yard, were all but utilised. Consequently a revision of ECS Westbound services out of Wimbledon Park was looked in to.
The aim of the latter, specifically, was to find a path for a new ECS out of Wimbledon Park, down via Surbiton and round to Staines to form a morning peak Staines to Waterloo, that had previously been provided from elsewhere.

Now to the crux of the matter: this proposed move would be via the Down Main Fast to Weybridge thence the diamond crossing in the Up Main Fast at Weybridge, to gain access to the Chertsey branch. At this point in time (2014 etc) the said diamond crossing was failing routinely resulting in what seemed like a near permanent TSR (Temporary Speed Restriction) usually about 50 mph, which was recognised as causing enough of a delay to the stream of Up Main Fast trains to have a very real negative impact on the a.m. peak arrivals at Waterloo.

The question was posed, when exactly I do not remember, but to the effect that can the said diamond crossing be done away with altogether (to improve peak train running on the UMFL). The answer from the planners was definite NO, as the new 10 car train service would without doubt need the same in place and working for every SX (week) day part of the service, if not for engineering diversions at weekends.

Consequently the TSR often remained in place thereafter.

Back to the present, and I have no idea what the situation is now, but am curious as to the reasons this diamond could seemingly never be 'gold plated' (maintenance wise), a phrase that may be known to some in relation to the Waterloo-Clapham Jn corridor some years ago. In the planning side it was often jested it was down to poor grade (non UK) steel, but who knows? Never heard or told anything remotely truthful about this from above.
 

MarkyT

Established Member
Joined
20 May 2012
Messages
7,549
Location
Torbay
Indeed. I assume that's also why they're being progressively replaced with pairs of crossovers?
Where the longer junction layout fits, that's an option, or sometimes it might be worth sacrificing junction speed and settling for a fixed diamond. Switched diamonds can still make sense in some new layouts, such as the Bacon Factory curve junctions at Ipswich.
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,897
Indeed. I assume that's also why they're being progressively replaced with pairs of crossovers?
Years ago, 1 in 8 was considered the shallowest safe angle for an obtuse crossing so many double junctions were laid out incorporating these and avoiding switch diamonds. Along came diesels and it was discovered some were not happy with 1 in 8 and 1 in 7.5 was the shallowest safe angle.

Since then, only the most essential double junctions have received switch diamonds. All the others have been relaid with permutations of using 1 in 7.5, or differing uses of single leads in ladders etc.
 

nlogax

Established Member
Joined
29 May 2011
Messages
6,007
Location
Mostly Glasgow-ish. Mostly.

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,897
Must be a maintenance nightmare, not just for PW but the OLE too!
Almost reaching the stage where the dodgem cars OHLE is the answer. ( A large steel net suspended above the area so that dodgem cars can wander around freely).
 

matchmaker

Established Member
Joined
8 Mar 2009
Messages
1,868
Location
Central Scotland
As the crossing angles reduce in faster layouts, the flange gaps in preferred fixed diamond crossings get larger and eventually exceed safety limits, necessitating provision of the complex switched variety instead. Unfortunately, those short stub switches are notoriously difficult to maintain in adjustment, with the slightest bit of heat expansion often causing detection failure. Hence they were some of the first bits of infrastructure to receive the white rail painting treatment, which reflects sunlight and limits heat gain.
I was on an official visit to Dalmuir Park signal box (North Clyde) one hot summer afternoon in the 1970s when the switched diamonds failed due to the heat. It took the combined efforts of the signalman, the district inspector and yours truly to get them cooled down and operating properly. If the DI and myself hadn't been there the signalman would have been on his own! Goodness knows what delays would have been like.
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
Some switch diamonds were equipped with water sprinklers, which the signalman would turn on during hot weather.
 

Annetts key

Established Member
Joined
13 Feb 2021
Messages
3,788
Location
West is best
Some comments from me…

Heat can affect any S&C/point work, especially where there is CWR/LWR one side or surrounding the junction.

With respect to S&C/point work in Network Rail land being unreliable, part of the problem is that there is insufficient maintenance of the ballast formation. When large heavy duty bolts and nuts vibrate off (even though they were done up to the correct torque specification), you know that the track is voiding (excessive vertical movement as a train passes over).

Unfortunately as the S&C/point work becomes more complex, tamping machines (see more details here) find it harder to maintain the ballast formation. So it has to be done with actual people using the appropriate ‘portable’ tools (normally powered these days). But there is difficulty getting them in during most of the day due to the number of trains. And they are needed everywhere else at night/weekends.

The other problem is not following up and dealing with problems that have been found. Minor problems get noted, but not actioned. Some get worse, and then contribute to the cause of a failure.

And wear is proportional to the amount and type of traffic. But it’s harder to deal with on busy lines… so gets left until it gets to the “it has to done” stage.

And lastly, anything other than bog standard parts are not kept in stock. So when something is discovered to have a problem, if it cannot be repaired, the lead time before a replacement can be made is measured in weeks. Then it has to be planned in to replace it. Which often means other work has to be postponed.
 
Last edited:

Big Jumby 74

Established Member
Joined
12 Feb 2022
Messages
2,217
Location
UK
And lastly, anything other than bog standard parts are not kept in stock. So when something is discovered to have a problem, if it cannot be repaired, the lead time before a replacement can be made is measured in weeks. Then it has to be planned in to replace it. Which often means other work has to be postponed.
I concur with not only your comments here, but also your overall reply. I always found it a shame that those in charge of the purse strings overall often did not understand how in some cases, certain often perceived minor parts of the infrastructure, could, if not maintained correctly, have such an adverse effect on very large parts of the network.
 

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,583
What's the difference between a double slip and a switch diamond?

ones a nightmare to maintain, and the other is 3 times harder.


This is for one of you good people who understands the engineering side of track work/maintenance better than I. I appreciate the basics, but more from an operational (train planning angle), as in what could one achieve to maximise train movements with the infrastructure in situ (past tense, now retired, so purely out of interest now).

During the planning stages of the 10 car suburban railway on the South Western (SWT as it was), back in 2014, the lack of stabling capacity (at that time) required some alternative thinking, as in how could certain ECS trains be re-routed to form their a.m. peak start up services, without a complete timetable re-write.
It became clear very early on that the various implications of running 10 car vice 8 car, ECS paths Westbound down the Windsor lines, early morning out of Clapham Yard, were all but utilised. Consequently a revision of ECS Westbound services out of Wimbledon Park was looked in to.
The aim of the latter, specifically, was to find a path for a new ECS out of Wimbledon Park, down via Surbiton and round to Staines to form a morning peak Staines to Waterloo, that had previously been provided from elsewhere.

Now to the crux of the matter: this proposed move would be via the Down Main Fast to Weybridge thence the diamond crossing in the Up Main Fast at Weybridge, to gain access to the Chertsey branch. At this point in time (2014 etc) the said diamond crossing was failing routinely resulting in what seemed like a near permanent TSR (Temporary Speed Restriction) usually about 50 mph, which was recognised as causing enough of a delay to the stream of Up Main Fast trains to have a very real negative impact on the a.m. peak arrivals at Waterloo.

The question was posed, when exactly I do not remember, but to the effect that can the said diamond crossing be done away with altogether (to improve peak train running on the UMFL). The answer from the planners was definite NO, as the new 10 car train service would without doubt need the same in place and working for every SX (week) day part of the service, if not for engineering diversions at weekends.

Consequently the TSR often remained in place thereafter.

Back to the present, and I have no idea what the situation is now, but am curious as to the reasons this diamond could seemingly never be 'gold plated' (maintenance wise), a phrase that may be known to some in relation to the Waterloo-Clapham Jn corridor some years ago. In the planning side it was often jested it was down to poor grade (non UK) steel, but who knows? Never heard or told anything remotely truthful about this from above.

that’s another pig of a junction. Hammered by heavy Siemens trains all day (to a much greater extent than anything beforehand). very difficult to keep in line, and has to be done by hand. All on timber -IIRC a concrete solution (which is much more stable) simply couldn’t be designed.


If you're really into slips... This is Zurich. The telephoto makes it even more dramatic.


that will give a track maintenance engineer nightmares!
 

mr_moo

Member
Joined
7 Sep 2009
Messages
647
Location
Cambridgeshire
If you're really into slips... This is Zurich. The telephoto makes it even more dramatic.

Wow. that is definately impressive. As others have said, a sure nightmare to maintain but the operational flexibility that will offer is great, and that photo is awesome!

== Doublepost prevention - post automatically merged: ==

Strange - only yesterday I watched a video on YouTube about three-way points; going from a single line to three lines at the same point. Are there any of these in the UK network?
Quite often you'll find these are three directional points, but they aren't quite all going from the same point. They are essentially interlaced points. The above references one from southampton is this type - if you follow the switch rails you'll essentially see two 'toes' a short distance apart:
1646696467019.png



This one in Acton yard is similar:

Again, you can see it's essentially two sets of S&C on top of each other, with two distinctly separate toes:

1646696770410.png

There certainly used to be proper 3-throws around, where all three routes do converge pretty much at the toe, although I'm not aware of any left in operational areas, not that my knowledge of sidings etc is particularly comprehensive!
 
Last edited:

AlbertBeale

Established Member
Joined
16 Jun 2019
Messages
3,188
Location
London
Wow. that is definately impressive. As others have said, a sure nightmare to maintain but the operational flexibility that will offer is great, and that photo is awesome!

== Doublepost prevention - post automatically merged: ==


Quite often you'll find these are three directional points, but they aren't quite all going from the same point. They are essentially interlaced points. The above references one from southampton is this type - if you follow the switch rails you'll essentially see two 'toes' a short distance apart:
View attachment 111151



This one in Acton yard is similar:

Again, you can see it's essentially two sets of S&C on top of each other, with two distinctly separate toes:

View attachment 111152

There certainly used to be proper 3-throws around, where all three routes do converge pretty much at the toe, although I'm not aware of any left in operational areas, not that my knowledge of sidings etc is particularly comprehensive!

The 2nd and 9th photos here (https://www.rmweb.co.uk/community/index.php?/topic/42395-train-ferry-at-messina-sicily/) seem to show genuine 3-way points, on the ramp to the train ferry on the way to Sicily.
 

bspahh

Established Member
Joined
5 Jan 2017
Messages
2,414
If you're really into slips... This is Zurich. The telephoto makes it even more dramatic.


I couldn't see the buildings in the image in the aerial photographs on Google Maps. I stayed in the 25 Hours hotel near there a couple of years ago, and it was all fairly new then.
This is a schematic diagram of the tracks into Zürich HB from
Schematic Track Diagram of Zürich HB
 
Last edited:

buz33

Member
Joined
21 Nov 2009
Messages
35
Double slips, I don't think Kings Cross had any three way points did it?
No, I just thought it was possibly worth asking, in case that was your real question…
The old KGX layout is still shown on Google Maps and that suggests that there were 3 way points on the entrance to Gasworks tunnel (also 5 double slips).
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
The old KGX layout is still shown on Google Maps and that suggests that there were 3 way points on the entrance to Gasworks tunnel (also 5 double slips).
Yes, I was originally trying to establish what the question in post #82 was definitely asking about. The 3 way interlaced points at Kings Cross seem to have been relatively unknown, all the “improvements in maintenance” PR and discussions never seem to mention them.

Is it possibly because although they’re fairly unusual, (and pretty complex looking), they aren‘t such a maintenance nightmare?
 
Last edited:

Bald Rick

Veteran Member
Joined
28 Sep 2010
Messages
35,583
Yes, I was originally trying to establish what the question in post #82 was definitely asking about. The 3 way interlaced points at Kings Cross seem to have been relatively unknown, all the “improvements in maintenance” PR and discussions never seem to mention them.

Is it possibly because although they’re fairly unusual, (and pretty complex looking), they aren‘t such a maintenance nightmare?

Three throw points are less of a maintenance liability than switch diamonds. The issue with three throws is that they are all bespoke, so any failures of crossing components usually means a rapid phone call to Beeston and an emergency order for a special casting.
 

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,227
Three throw points are less of a maintenance liability than switch diamonds. The issue with three throws is that they are all bespoke, so any failures of crossing components usually means a rapid phone call to Beeston and an emergency order for a special casting.
Thanks Bald Rick, that‘s what I was thinking but I thought I’d await an expert…
 

TSG

Member
Joined
10 Aug 2020
Messages
207
Location
Somewhere in the South of England
This is for one of you good people who understands the engineering side of track work/maintenance better than I. I appreciate the basics, but more from an operational (train planning angle), as in what could one achieve to maximise train movements with the infrastructure in situ (past tense, now retired, so purely out of interest now).

During the planning stages of the 10 car suburban railway on the South Western (SWT as it was), back in 2014, the lack of stabling capacity (at that time) required some alternative thinking, as in how could certain ECS trains be re-routed to form their a.m. peak start up services, without a complete timetable re-write.
It became clear very early on that the various implications of running 10 car vice 8 car, ECS paths Westbound down the Windsor lines, early morning out of Clapham Yard, were all but utilised. Consequently a revision of ECS Westbound services out of Wimbledon Park was looked in to.
The aim of the latter, specifically, was to find a path for a new ECS out of Wimbledon Park, down via Surbiton and round to Staines to form a morning peak Staines to Waterloo, that had previously been provided from elsewhere.

Now to the crux of the matter: this proposed move would be via the Down Main Fast to Weybridge thence the diamond crossing in the Up Main Fast at Weybridge, to gain access to the Chertsey branch. At this point in time (2014 etc) the said diamond crossing was failing routinely resulting in what seemed like a near permanent TSR (Temporary Speed Restriction) usually about 50 mph, which was recognised as causing enough of a delay to the stream of Up Main Fast trains to have a very real negative impact on the a.m. peak arrivals at Waterloo.

The question was posed, when exactly I do not remember, but to the effect that can the said diamond crossing be done away with altogether (to improve peak train running on the UMFL). The answer from the planners was definite NO, as the new 10 car train service would without doubt need the same in place and working for every SX (week) day part of the service, if not for engineering diversions at weekends.

Consequently the TSR often remained in place thereafter.

Back to the present, and I have no idea what the situation is now, but am curious as to the reasons this diamond could seemingly never be 'gold plated' (maintenance wise), a phrase that may be known to some in relation to the Waterloo-Clapham Jn corridor some years ago. In the planning side it was often jested it was down to poor grade (non UK) steel, but who knows? Never heard or told anything remotely truthful about this from above.
I'm afraid I don't know the reason why the crossing was so problematic, although I think the angle of a crossing can limit your options in terms of construction and it did look an odd angle. I don't know the details but I think they may have tweaked the layout a bit to use a different part (presumably something more maintainable) a few months ago when they changed it. Quite a big possession with a lot of work going on. I know the work was brought forward to get rid of the TSR.
 
Joined
18 Oct 2017
Messages
215
Quite often you'll find these are three directional points, but they aren't quite all going from the same point. They are essentially interlaced points. The above references one from southampton is this type - if you follow the switch rails you'll essentially see two 'toes' a short distance apart:

Aren't they called "tandem" switches in UK parlance...? As opposed to "true" three-throw switches with common toe points.
 

furnessvale

Established Member
Joined
14 Jul 2015
Messages
4,897
Aren't they called "tandem" switches in UK parlance...? As opposed to "true" three-throw switches with common toe points.
Correct in both cases. "Three throw" switches are even more frowned upon as, according to "British Railway Track", it is impossible to maintain gauge through the switches when they are set for the middle road.

Never having had the need to design such switches, I will take their word for it.
 
Status
Not open for further replies.

Top