No, but after certain milage they won't be allowed to run without a heavy overhaul. And nobody is going to approv and pay for that in case of trains which are about to be scrapped.
A savvy contract would then have "we will deduct the cost of any additional heavy overhauls needed to keep full service running in the event of delivery later than <X>" written into it. Because otherwise, you're effectively a hostage to the builders of the new stock.
 

Wolfie

Established Member
Joined
17 Aug 2010
Messages
7,428
A savvy contract would then have "we will deduct the cost of any additional heavy overhauls needed to keep full service running in the event of delivery later than <X>" written into it. Because otherwise, you're effectively a hostage to the builders of the new stock.
The new stock has been delivered though.
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,297
The new stock has been delivered though.
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
 

Thirteen

Established Member
Joined
3 Oct 2021
Messages
1,899
Location
London
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
You're complaining for the sake for complaining again
 

boiledbeans2

Member
Joined
15 Oct 2020
Messages
971
Location
UK
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
Is CAF at fault in this scenario? Or is it TfL?
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,486
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
That depends on the terms of the contract, and the acceptance schedule is likely to consider how responsibilities are balanced where there are changes involving both rolling stock manufacturer and customer, as here.

On the little we know, it’s plausible that, as defined in the contract(s), the trains are absolutely fine and that the issue is with the signalling. Just as it’s plausible that the problem is with the trains on perfectly serviceable signalling.

Integration is hard, and shouting the odds about fault tends to make it harder
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,297
Is CAF at fault in this scenario? Or is it TfL?
I think the real answer is that we don't know, because there has been no meaningful statement from TfL while all this drags on stating what the issue(s) actually are. It does seem that given the DLR signalling has worked straightforwardly for the last 30 years, over multiple batches of new trains being delivered.

Given the continuing silence and lack of resolution one wonders if this is going to end up in court.
 
Joined
2 Jun 2023
Messages
1,096
Location
Richmond
Given the continuing silence and lack of resolution one wonders if this is going to end up in court.
When it comes to railway procurement, the legal proceedings all happen behind the scenes. It can look all positive from a public POV but behind closed doors they’re engaged in an intense legal battle.
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,486
When it comes to railway procurement, the legal proceedings all happen behind the scenes. It can look all positive from a public POV but behind closed doors they’re engaged in an intense legal battle.
Having had experience (non-rail) of a couple of "troubled" projects, it's also often difficult to see how much work is required to fix "obvious" problems - and how any dispute can affect that.

While I'm entirely willing to think the worst of CAF (their "Cheap as F..." nickname speaks volumes), it's impossible to know without detailed knowledge of both contracts and the underlying infrastructure. The nature of the fault that stopped the B23s running seems niche enough that isolating, fixing and then proving the fix may well take a while - but once done, be quickly applied across the fleet.
 

ijmad

Established Member
Joined
7 Jan 2016
Messages
1,856
Location
UK
Is it fair to say the 'fix' is likely to be a software change rather than hardware modification anyway?

So yes I understand the contract arrangements but from a practical point of view it doesn't really matter where particular trains are.
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,486
From (Modern Railways) Roger Ford's "Informed Sources Laws". Number 9:
Indeed. But do we know that the shortcoming is to do with physical design? After all, these are trains whose control systems are software based
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,156
Location
West Wiltshire
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
I understand TfL asked for delivery to be delayed, and it stems back to their choice of contractor to build the sidings for the trains, who didn't because they went bust. The subsequently got someone to complete the build work.

My hunch is CAF would probably not have wanted them stored either, as much easier to arrange delivery at standard intervals after each one is tested and passed, than be asked for whole batch close together. Don't forget it takes the specialist delivery trailers nearly a week to load, drive to Becton, unload, and return for next one.
 

Taunton

Veteran Member
Joined
1 Aug 2013
Messages
12,297
I understand TfL asked for delivery to be delayed, and it stems back to their choice of contractor to build the sidings for the trains, who didn't because they went bust. They subsequently got someone to complete the build work.
I'm afraid, as I have written before, that I can't accept this one. The contractor, Buckingham Group, went bust in August 2023. It's now 2026, and not even one train has been got to run reliably. TfL have continued to milk this one for years as a cause of delay. The sidings were not an Apollo moonshot project, they were ... sidings. All designed with the drawings, all the bills of quantity done, etc. That's pretty straightforward stuff. Oh, and TfL did require the contractor to have taken out a Completion Bond - didn't they?
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,486
I'm afraid, as I have written before, that I can't accept this one. The contractor, Buckingham Group, went bust in August 2023. It's now 2026, and not even one train has been got to run reliably. TfL have continued to milk this one for years as a cause of delay. The sidings were not an Apollo moonshot project, they were ... sidings. All designed with the drawings, all the bills of quantity done, etc. That's pretty straightforward stuff. Oh, and TfL did require the contractor to have taken out a Completion Bond - didn't they?
I have no view on whether TfL are or are not justified in claiming this one. But I do know from long experience that delays in one part of a project can ripple through in unexpected ways, and that delays can be magnified as a result.
 

bahnause

Member
Joined
30 Dec 2016
Messages
1,037
Location
bülach (switzerland)
This can be included in contracts. However, it will affect the price and the number of offers. No manufacturer will take on additional risks without financial reinsurance.
Therefore, there is always a 'sweet spot' where the interests of suppliers and customers align. There will be no unlimited liability. A financially ruined manufacturer would also make operating a fleet difficult.
Added to this is the problem of assigning responsibility in complex projects. This is often anything but clear-cut.
 

35B

Established Member
Joined
19 Dec 2011
Messages
5,486
This can be included in contracts. However, it will affect the price and the number of offers. No manufacturer will take on additional risks without financial reinsurance.
Therefore, there is always a 'sweet spot' where the interests of suppliers and customers align. There will be no unlimited liability. A financially ruined manufacturer would also make operating a fleet difficult.
Added to this is the problem of assigning responsibility in complex projects. This is often anything but clear-cut.
Absolutely, on all points.
 

Geogregor

Member
Joined
16 Sep 2016
Messages
458
Location
London
The way things are going we might see new Piccadilly Line trains in service before B23 carrying passengers again...
 

Starmill

Veteran Member
Joined
18 May 2012
Messages
27,285
Location
Bolton
Can someone recap the current position please? Based on my reading of the above it's that the new units are currently all stood down from passenger service, is that still correct?
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,156
Location
West Wiltshire
Can someone recap the current position please? Based on my reading of the above it's that the new units are currently all stood down from passenger service, is that still correct?
Yes correct, the testing discovered some locations where signalling (the block sections, there are no physical signals, just junction indicators) were slightly out for speed limit, so a speed limit cut was applied in these sections.

It subsequently was found that in the wet when adhesion was lower, in certain circumstance an overshoot happened, and the new trains were all taken out of passenger service until a fix could be implemented.

TfL have never said exactly what problem is, or how it will be resolved, even in their Board papers. (next TfL Board papers due middle of coming week, which may or may not give update)
 

Snow1964

Established Member
Joined
7 Oct 2019
Messages
11,156
Location
West Wiltshire
TfL has uploaded the papers for next weeks TfL Board meeting


Page 103 has table with DLR new trains
2025-26 actuals. £196m
2026-27 (April- March) plan £120m
2027-28 plan £106m
2028-29 plan £18m

gives some sort of indication of amount being spent in each financial year on the new trains, and expecting to still pay over £220m. It also shows that they have actually paid nearly £200m for trains not yet in use.

Same table also has plan for new trams
2026-27 plan £9m
2027-28 plan £29m
2028-29 plan £48m
2029-30 plan £50m

So expecting to spend over £130m on new trams, and delivery timescale will run to at least 2030
 

JCO1406

Member
Joined
28 May 2024
Messages
190
Location
London
TfL has uploaded the papers for next weeks TfL Board meeting


Page 103 has table with DLR new trains
2025-26 actuals. £196m
2026-27 (April- March) plan £120m
2027-28 plan £106m
2028-29 plan £18m

gives some sort of indication of amount being spent in each financial year on the new trains, and expecting to still pay over £220m. It also shows that they have actually paid nearly £200m for trains not yet in use.

Same table also has plan for new trams
2026-27 plan £9m
2027-28 plan £29m
2028-29 plan £48m
2029-30 plan £50m

So expecting to spend over £130m on new trams, and delivery timescale will run to at least 2030
And still no updates on when they will return to service...
 

JCO1406

Member
Joined
28 May 2024
Messages
190
Location
London
A 3 coach B90 unit has broken down between Cyrpus and Gallions Reach. Could really do with having the B23s in service now!!!
 