A savvy contract would then have "we will deduct the cost of any additional heavy overhauls needed to keep full service running in the event of delivery later than <X>" written into it. Because otherwise, you're effectively a hostage to the builders of the new stock.No, but after certain milage they won't be allowed to run without a heavy overhaul. And nobody is going to approv and pay for that in case of trains which are about to be scrapped.
The new stock has been delivered though.A savvy contract would then have "we will deduct the cost of any additional heavy overhauls needed to keep full service running in the event of delivery later than <X>" written into it. Because otherwise, you're effectively a hostage to the builders of the new stock.
Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.The new stock has been delivered though.
You're complaining for the sake for complaining againWell it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
Is CAF at fault in this scenario? Or is it TfL?Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
That depends on the terms of the contract, and the acceptance schedule is likely to consider how responsibilities are balanced where there are changes involving both rolling stock manufacturer and customer, as here.Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
I think the real answer is that we don't know, because there has been no meaningful statement from TfL while all this drags on stating what the issue(s) actually are. It does seem that given the DLR signalling has worked straightforwardly for the last 30 years, over multiple batches of new trains being delivered.Is CAF at fault in this scenario? Or is it TfL?
When it comes to railway procurement, the legal proceedings all happen behind the scenes. It can look all positive from a public POV but behind closed doors they’re engaged in an intense legal battle.Given the continuing silence and lack of resolution one wonders if this is going to end up in court.
It does seem that given the DLR signalling has worked straightforwardly for the last 30 years, over multiple batches of new trains being delivered.
Having had experience (non-rail) of a couple of "troubled" projects, it's also often difficult to see how much work is required to fix "obvious" problems - and how any dispute can affect that.When it comes to railway procurement, the legal proceedings all happen behind the scenes. It can look all positive from a public POV but behind closed doors they’re engaged in an intense legal battle.
From (Modern Railways) Roger Ford's "Informed Sources Laws". Number 9:Is it fair to say the 'fix' is likely to be a software change rather than hardware modification anyway?
Ninth Law
- Do not try to solve physical design shortcomings with software.
Indeed. But do we know that the shortcoming is to do with physical design? After all, these are trains whose control systems are software basedFrom (Modern Railways) Roger Ford's "Informed Sources Laws". Number 9:
I understand TfL asked for delivery to be delayed, and it stems back to their choice of contractor to build the sidings for the trains, who didn't because they went bust. The subsequently got someone to complete the build work.Well it shouldn't have been. Delivery is to the buyers premises (which they are not on) in full working order (which they are not), and demonstrated same to an agreed acceptance schedule.
I'm afraid, as I have written before, that I can't accept this one. The contractor, Buckingham Group, went bust in August 2023. It's now 2026, and not even one train has been got to run reliably. TfL have continued to milk this one for years as a cause of delay. The sidings were not an Apollo moonshot project, they were ... sidings. All designed with the drawings, all the bills of quantity done, etc. That's pretty straightforward stuff. Oh, and TfL did require the contractor to have taken out a Completion Bond - didn't they?I understand TfL asked for delivery to be delayed, and it stems back to their choice of contractor to build the sidings for the trains, who didn't because they went bust. They subsequently got someone to complete the build work.
I have no view on whether TfL are or are not justified in claiming this one. But I do know from long experience that delays in one part of a project can ripple through in unexpected ways, and that delays can be magnified as a result.I'm afraid, as I have written before, that I can't accept this one. The contractor, Buckingham Group, went bust in August 2023. It's now 2026, and not even one train has been got to run reliably. TfL have continued to milk this one for years as a cause of delay. The sidings were not an Apollo moonshot project, they were ... sidings. All designed with the drawings, all the bills of quantity done, etc. That's pretty straightforward stuff. Oh, and TfL did require the contractor to have taken out a Completion Bond - didn't they?
Absolutely, on all points.This can be included in contracts. However, it will affect the price and the number of offers. No manufacturer will take on additional risks without financial reinsurance.
Therefore, there is always a 'sweet spot' where the interests of suppliers and customers align. There will be no unlimited liability. A financially ruined manufacturer would also make operating a fleet difficult.
Added to this is the problem of assigning responsibility in complex projects. This is often anything but clear-cut.
Yes correct, the testing discovered some locations where signalling (the block sections, there are no physical signals, just junction indicators) were slightly out for speed limit, so a speed limit cut was applied in these sections.Can someone recap the current position please? Based on my reading of the above it's that the new units are currently all stood down from passenger service, is that still correct?
B23 testing is due to re-start in the very near future.Yes, no B23s in service or testing. And it doesn’t seem like they will be back any time soon.
They're the same length as a 3-car B2007Could the B23s being longer be part of the problem?
And still no updates on when they will return to service...TfL has uploaded the papers for next weeks TfL Board meeting
Page 103 has table with DLR new trains
2025-26 actuals. £196m
2026-27 (April- March) plan £120m
2027-28 plan £106m
2028-29 plan £18m
gives some sort of indication of amount being spent in each financial year on the new trains, and expecting to still pay over £220m. It also shows that they have actually paid nearly £200m for trains not yet in use.
Same table also has plan for new trams
2026-27 plan £9m
2027-28 plan £29m
2028-29 plan £48m
2029-30 plan £50m
So expecting to spend over £130m on new trams, and delivery timescale will run to at least 2030