You think the old trains will suddenly stop working at a given date ?But eventually they run out of mileage on the old trains. What then? Shutting some branches?
Can someone just get a grip of the whole badly run process?
You think the old trains will suddenly stop working at a given date ?
It's a shame they didn't think to reduce unit usage and mileage all through lockdown, when maximum length 3-car trains were run throughout, with virtually no passengers (and sometimes genuinely none) in them. Yes, it is doubtless mileage-driven in some ISO document that up to a given odometer reading they can run all day, and once that moment is reached the diktat says they can't be used at all.They're no longer viable to run (without overhaul) after a given mileage, not date, hence the thinning out of services / short forming to preserve stock levels.
Maybe that has been done, but I question whether the people at Alstom would wish to become involved. After all, it does not directly involve their trains - and their involvement might void a warrenty. Also, maybe CAF would not like it in case it results in one of their commercial rivals discovering a commercial secret.Has anyone thought to ask if the longer-serving engineers at Alstom, once Bombardier, who put all the current trains, and their braking systems, together, can come over and tell the DLR and CAF teams how to do it?
No, but after certain milage they won't be allowed to run without a heavy overhaul. And nobody is going to approv and pay for that in case of trains which are about to be scrapped.You think the old trains will suddenly stop working at a given date ?
Because I'm neither engineer nor a programmer. Also, nobody pays me to solve their mess.I assume that between the TfL and CAF there should be enough highly paid talent to solve the problem. They might need to kick some backsides for motivation though.Why don’t you go and give them a hand if you know best ?
Bombardier, the traditional rolling stock supplier, no longer build trains. Alstom bought that part of the business, and presumably gave a higher price than CAF.One does wonder how much this developing fiasco is costing, and whether it has already squandered far more than the difference in quotations between the traditional rolling stock supplier and this new one.
I presume CAF was largely chosen as the winning bidder due to offering a cheaper option to Stadler/Siemens or Alstom. Now we're stuck with trains of lower quality than what the other bidders could've built, with this fiasco ending up costing potentially more than it would've if they had picked a more expensive but higher quality bid, which would've had less problems on introduction. CAF have really earned their nickname (if you know, you know.)
I presume CAF was largely chosen as the winning bidder due to offering a cheaper option to Stadler/Siemens or Alstom. Now we're stuck with trains of lower quality than what the other bidders could've built, with this fiasco ending up costing potentially more than it would've if they had picked a more expensive but higher quality bid, which would've had less problems on introduction. CAF have really earned their nickname (if you know, you know.)
Yup… since the Class 701 débâcle, everyone suddenly forgot most train introductions have not really been that smooth…All new rolling stocks has teething issues, the way people on here go on, you would think the B23s will never enter service
Wasn't the Newcastle Metro and Mersey rail stock introductions also the victim of numerous issues and delays? They're Stadler aren't they?
And as for Ansaldo Breda… we’re just lucky nobody ever dipped their toes down that route.It's a thing everywhere. Bombardier even managed to build a fleet of trains for OBB which were never accepted and they ordered from Siemens instead.
Guess who was running the italian Hitachi factory before the Japanese company bought out AnsaldoBreda ?And as for Ansaldo Breda… we’re just lucky nobody ever dipped their toes down that route.
Indeed. I’ve previously highlighted some of the lessor quality construction on the GWR IETs…. Noticeable around the door frames for example.Guess who was running the italian Hitachi factory before the Japanese company bought out AnsaldoBreda ?
All new rolling stocks has teething issues, the way people on here go on, you would think the B23s will never enter service
Yes, quite a few issues on IETs are basically AnsaldoBreda-signed if you will…Indeed. I’ve previously highlighted some of the lessor quality construction on the GWR IETs…. Noticeable around the door frames for example.
Back on topic the situation has now reached the Evening Standard here:
https://www.msn.com/en-gb/news/ukne...S&cvid=6930a7bc6ffb409fb10e9a69927551fe&ei=13
There are a few curiosities in that article.
- TfL Commissioner Andy Lord saying he "wanted to keep the reason for the failure secret". How strange. This is public money.
- It's described as "a very unique set of circumstances". Yet is used to withdraw the trains, presumably because of the risk of happening again.
- The trains are described as "18 months late". Actually it's 3 years now since the train in question arrived.
Thank you. I'm used to reading EFC (Estimated Final Costs) reporting, but hope the Committee are all likewise as that looks a real gloss-over. Nowhere is the loss of revenue from all the additional weekend closures put into the equation. And they continue to milk the bankruptcy of contractor Buckingham Group on the depot sidings extension, massaging that, the additional scope of extra trains, and the rolling stock problems all into one. Did nobody think to take out a completion bond on that contract ...?The TfL Board papers for Programmes and Investment committee meeting next week are now published.
The new DLR trains are in section 8.2
...
But in my experience if all is going well, the Board praises itself with lots of wording about well managed and success etc, not a list of cryptically and carefully worded events. So my hunch is not going well, and more problems than they want to talk about
www.londonreconnections.com
The TfL Board papers for Programmes and Investment committee meeting next week are now published.
The new DLR trains are in section 8.2
https://board.tfl.gov.uk/documents/s25521/pic-20251211-item05a-part1-investment-programme-report.pdf
There is something not right, looks like details are being deliberately covered up or hidden.
eg 8.2.2 says figures not being updated due to commercial sensitivity
8.2.3 refers to completion date has moved later (no revised date given)
8.2.5 says review a range of solutions (in response to temporary withdrawal apparently due to braking performance), doesn't sound like one solution for one problem
Some of the answers may be in the non-public part 2 papers.
But in my experience if all is going well, the Board praises itself with lots of wording about well managed and success etc, not a list of cryptically and carefully worded events. So my hunch is not going well, and more problems than they want to talk about