More than a year has now passed since London Road bridge was closed to all road traffic for renewal. The bridge carries the A6 road over the Birmingham lines between the old PSB and the new control centre.
It surprised many when it was originally estimated to take up to a year but it's still nowhere near completion and the latest estimate is December which is by no means certain.
As far as I'm aware there havn't been any inherent problems or complications, it was a plate girder bridge which was removed and then required new abutments before the new steelwork can be lifted into position. From observation, it seems that minimum manpower has been used from the start with some days only three or four workers being present.
But how long is reasonable? Most bridge renewals are prepared and carried out in a big weekend possession or perhaps a Bank Holiday. The new bridge into Pride Park at the north end of Derby Station (I think a much larger project) was constructed in far less time. And hasn't the Shaftholme flyover been built in less time also?
Isn't a year and four months (and counting) rather excessive for a standard bridge renewal?
It surprised many when it was originally estimated to take up to a year but it's still nowhere near completion and the latest estimate is December which is by no means certain.
As far as I'm aware there havn't been any inherent problems or complications, it was a plate girder bridge which was removed and then required new abutments before the new steelwork can be lifted into position. From observation, it seems that minimum manpower has been used from the start with some days only three or four workers being present.
But how long is reasonable? Most bridge renewals are prepared and carried out in a big weekend possession or perhaps a Bank Holiday. The new bridge into Pride Park at the north end of Derby Station (I think a much larger project) was constructed in far less time. And hasn't the Shaftholme flyover been built in less time also?
Isn't a year and four months (and counting) rather excessive for a standard bridge renewal?