Crossrail shenfield

Status
Not open for further replies.

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,906
So interesting times ahead, well for the next 5 months! with TFL turning at Brentwood, and a bus shuttle to Shenfield (10 mins allowed for the run)
No OHL in place until May, and of course some of the connections twixt the old 'E' lines and 'M' lines out of use, at least until May, so 2 track railway, Shenfield - Gidea (minimum)
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

321446

Member
Joined
15 Nov 2008
Messages
223
Location
Southend Stations
Already been trial runs of late night GA Southend up and down services stopping at Brentwood additionally. Also had trial runs of failures jamming up the entire service because of the lack of cross overs. So now those bugs have been ironed out, contingency plans will be in place and it will all be fine. Don't know what you are worrying about. ;)
 

alholmes

Member
Joined
4 Jun 2012
Messages
477
Location
London E3
Can't wait for the first container train to get stuck at the bottom of Brentwood bank, with no way of getting past it...
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
Can't wait for the first container train to get stuck at the bottom of Brentwood bank, with no way of getting past it...

Which is why there is a Freightliner standby loco at Shenfield. It has been there for the past couple of months, as the junctions at the London end of Shenfield have been out of use for a while already.
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,906
Which is why there is a Freightliner standby loco at Shenfield. It has been there for the past couple of months, as the junctions at the London end of Shenfield have been out of use for a while already.

Even with that loco there, you are looking at 45 mins minimum before the 'failure' would be anywhere near moving off again !
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
Quicker than normal then ;)

Of course it's not ideal, but the London End of Shenfield is being completely rebuilt to a totally different layout. A huge task.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,595
Location
Scotland
Of course it's not ideal, but the London End of Shenfield is being completely rebuilt to a totally different layout. A huge task.
Indeed. A popular saying involving omelettes and eggs comes to mind. :)
 

LAX54

Established Member
Joined
15 Jan 2008
Messages
3,906
of course the major part of the work is CROSSRAIL work, so really passengers that are being 'diverted' should not have a pop at NR, its the 'new' build railway line that is the cause surely ?
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
Whilst undoubtedly nothing would have happened without Crossrail, everyone benefits from the final layout. All GA trains to Southend can run to platform 4 at 50 mph without conflicting with the Shenfield terminators, which should help the evening peak particularly flow much better through Shenfield.

Watching a freightliner run up main to the up electric line at 50 mph will be entertaining too, if you like watching that sort of thing.
 

AlanFry1

Member
Joined
17 Nov 2011
Messages
662
Cant some 315s be moved elsewhere now? as less will be required if only running to brentwood rather than shenfield
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Already been trial runs of late night GA Southend up and down services stopping at Brentwood additionally. Also had trial runs of failures jamming up the entire service because of the lack of cross overs. So now those bugs have been ironed out, contingency plans will be in place and it will all be fine. Don't know what you are worrying about. ;)

That was for Gidea Park Junction OLE Renewal. As I recall there were two fatalities (suicides) whilst this was going on which virtually closed the GEML and certainly split it in two.
 

ginger

Member
Joined
20 Oct 2011
Messages
276
QUOTE FROM NETWORK RAIL - 3pm Monday
As we stand the OLE works at Gidea are finished and all on plan for the Shenfield works. But more welding and we then run some proving trains. Last check to re-energise from 2200.
My area director is in our control at Romford from 1600 to ensure a good hand vet from the projects teams.
 

EssexGonzo

Member
Joined
9 May 2012
Messages
637
The class 66 is normally being given a warm up at about 8.20am when I arrive at platform 1 of a weekday morning. I wondered what is was there for, now I know.

Re stopping at Brentwood - will the GA mainline Southend and Ipswich direction trains be stopping at Brentwood until May?
 

captainbigun

Member
Joined
3 May 2009
Messages
977
Anyone have a diagram for the final layout at Shenfield, I've looked and failed to find one.

I assume the majority of the track work was completed over Christmas.

The double failure that occurred back in Nov/Dec was a complete fiasco. Delays amounted to several hours for many, one guy I know got back to Ipswich after 10, usually he'd be there 7ish! Dealing with a sandwich of trains with incompatible couplings is always going to be a fiasco. I am surprised that the level of risk was agreed, not withstanding longer term benefits.
 
Last edited:

Alfie1014

Established Member
Joined
27 Jun 2012
Messages
1,205
Location
Essex
I had a look as my train stopped yesterday, not as much progress as I imagined but I suppose these things take time. Platforms 4 & 5 have been cordoned off (discrete worksite) with the OLE removed country end and on to the down Southend dive-under. At the London end both sets of EL to ML crossovers have either been completely removed or taken out of use. Some new single line connections from the UE (plat 4) to the DM have been installed but are not yet commisioned. Most (if not all) of the OLE on the open running lines has been replaced with the new F&F style. Operationally the stations is (except the closure of plats 4 & 5 and the ELs to Brentwood) the same as before Christmas; i.e. only MLs (plats 1,2 & 3) in use with down Southend services using 3 then crossing over to the Southend line on the flat. There are lots of track panels and new switches around the site to be installed over the coming weeks.
 

dave75

Member
Joined
29 Apr 2016
Messages
13
Does anyone know how long the GEML will be shut at weekends for this work? It is a pain and some travelling via Ingatestone every weekend. It's a poor enough service on Sundays as it is when running! Let alone the wait at Newbury park 4 half hour, to get a coach which then makes you wait 15m @ Ingatestone!
 

Alfie1014

Established Member
Joined
27 Jun 2012
Messages
1,205
Location
Essex
This is not the old NR plan but my version based upon what's going in on the ground at the moment, the new S&C that is being installed but not yet commissioned. The old double crossings at the London end have been removed and new single leads have started to be installed. I admit it may not be perfect but unless NR are going to be taking up much of the track laid over the Christmas shutdown I think it's pretty close.
--- old post above --- --- new post below ---
Does anyone know how long the GEML will be shut at weekends for this work? It is a pain and some travelling via Ingatestone every weekend. It's a poor enough service on Sundays as it is when running! Let alone the wait at Newbury park 4 half hour, to get a coach which then makes you wait 15m @ Ingatestone!

At least until the late May Bank Holiday (though not every weekend) which is when TfL say their services will be restored to Shenfield.
 

Class 170101

On Moderation
Joined
1 Mar 2014
Messages
8,661
Layout not due to be commissioned until May Bank Holiday. (1st one but more works following).
 

306024

Established Member
Joined
23 Jan 2013
Messages
3,974
Location
East Anglia
I managed to get back to Shenfield today and had a closer look this is how I think the final layout will be, don't shoot the messenger if I've got any of the detail wrong!

http://www.railforums.co.uk/attachment.php?attachmentid=30090&stc=1&d=1483635976

Good try, but not quite.

The main difference is Platforms 5 and 6 will have access to and from the main lines. Move some of your pointwork around and you'll achieve that.

All the planned work was achieved in the Christmas blockade. About 10 switches and a fixed diamond were installed, others taken out and some big steel structures for the OLE erected. A good effort.
 
Last edited:

321446

Member
Joined
15 Nov 2008
Messages
223
Location
Southend Stations
Just the same platform extensions as up and down the rest of the line. Other stations are getting lifts where none existed and bridges upgraded but I think Romford has a good ramp system already in place from the tunnels.

Of course they've had the ROC, so they're already far ahead for imposing erections anyway.
 

HowardGWR

Established Member
Joined
30 Jan 2013
Messages
4,981
Just the same platform extensions as up and down the rest of the line. Other stations are getting lifts where none existed and bridges upgraded but I think Romford has a good ramp system already in place from the tunnels.

Of course they've had the ROC, so they're already far ahead for imposing erections anyway.

Somewhat unfortunate last part of final sentence?:D
 

colchesterken

Member
Joined
12 Oct 2010
Messages
768
When I have to stray to the east end. I find the footbridge at Forest Gate a bit tiring ( old fella ) Anyone know how long the work will take
They have been at it a year and only seem to have demolished the staircases
 