Things change. Stop assuming that info a month old is always set in stone.
It happened at Clapham where the unit was stored overnight. I have now been reliably informed it's been moved into the shed at Clapham Yard no doubt so it can be cleaned up away from prying eyes. Speaking bluntly, this is what of should of happened in the first place when the unit arrived. The area around Clapham is notorious for graffiti and much of the trackside equipment and bridges on the way to Waterloo have been tagged. Using that siding which is outside of the Clapham Yard boundary fence was just asking for trouble.
So are you actually saying it's definite that they are all being introduced by 20 August or are you just trying to make some sort of point that plans can change?.
I'd not read this thread for a day or two and didn't know it'd be at CJ (hauled by 20142 looking very fine in maroon LT livery) just as I was passing through. Was gobsmacked to see the silvery sprawl down one side of a brand new unit.
I've seen some very bad graffiti on SWT recently. Given that silver paint is relatively easy to remove I hope there won't be any residual damage, although I suspect some of the vinyls may need to be replaced.
How does someone do that without being caught. Are there times when Clapham Junction doesn't have anyone around much? How would they get there?
Sent from my SM-T810 using Tapatalk
I also noticed 37800 with a long mixed freight was occupying a road close to the Windsor lines (presumably having been 'put away' for some reason)...
That's one of the locos (perhaps both), the brake force consist, and the translator wagons, that the 707 was delivered between surely?
How do do people get away with graffiti-daubing almost every inch of railway between New Cross and London Bridge, or Clapham Junction to Waterloo/Victoria? Or anywhere else? Staff either do not notice in the dark, are not there, or will not put themselves at risk bounding along the railway to try to catch/be assaulted by the vandals. The railway has been out of control for decades regarding this issue and this is nothing new. It just happens to be a new train, but the vandals probably didn't know that. However, presumably something has to use that siding, and it doesn't matter whether it was a 707 or 455 that was hit, the outcome is the same (probably actually less with the 707 because it won't be in service for months).
707001 was tucked at the back of 7 road in the shed this morning, and the maroon class 20 was at the end of a open air road. I also noticed 37800 with a long mixed freight was occupying a road close to the Windsor lines (presumably having been 'put away' for some reason), so a mixed bag at Clapham today!
That's one of the locos (perhaps both), the brake force consist, and the translator wagons, that the 707 was delivered between surely?
Does it really take such a huge use of stock just to deliver a five car unit?! The unit was delivered by 20142, the maroon-liveried example. Did 37800 and what looks like at least 20 vehicles really have to accompany the 707 and 20142? Amazing.
Well it will probably save altering the consist between trips with 707s, and 8 or 12 car 700s. This delivery was supposed to be two 707s together as originally posted. A number of 700 delivery videos exist that suggest these are the exact same vehicles.Does it really take such a huge use of stock just to deliver a five car unit?!
The unit was delivered by 20142, the maroon-liveried example. Did 37800 and what looks like at least 20 vehicles really have to accompany the 707 and 20142? Amazing.
Trains are quite heavy, and the 707 wouldnt have had any brakes during the delivery.
Quite a lot of wagons would be required to replace the brakes on that 707
Thanks. As a matter of interest, why can't the brakes on units being delivered
be operable?
As mentioned on here earlier, the units haven't been commissioned as yet, and as such the brakes are not yet set up.
Interesting. I would suggest that it might be beneficial to 'set up' the brakes before delivery, as presumably there is only one overall setting required for service. Why not do this at the construction plant, rather than on delivery? It seems to me that there is huge energy wastage in having to use a medium-length freight consist to move a unit just because its brakes are inoperable!
As a matter of interest (again) do all manufacturers follow this regime?
Because EMUs need power to get the brakes off, try delivering unis through multiple countries. And that's without the fact you'd then need to ensure the units are compatible with signalling etc.
Of course you could decided to generate power on a wagon but then you have issues with going through the Channel Tunnel so it's not a good idea.
It's easier, cheaper and quick to haul the unit dead as happens with most deliveries.
Worth noting the 377/387 from Bombardier out of Derby and all Siemens units have been hauled on delivery.
Why couldn't they have been commissioned at Dollands Moor then gone to Clapham on their own power? The 66s when they came over were commisioned at the dockside then moved off on their own power
Why couldn't they have been commissioned at Dollands Moor then gone to Clapham on their own power? The 66s when they came over were commisioned at the dockside then moved off on their own power
The consist of brake force wagons etc went back to Dollands (and I'm guessing on through the chunnel) this afternoon. Not sure when the next delivery is due.
No one would have been trained to drive them
When asked whether taking delivery of 250 locos would be a challenge, Fisk said 'I don't believe it is. I believe it's like buying an automobile'. He underlined the point by explaining what will be required when the locos are lifted off the boat at Newport. 'We just need to unblock the suspension, hook up the batteries, and take off the tarpaulin. They'll even be shipped with water and fuel.' Similarly there should be no major problem with retraining staff. Drivers should have no difficulty as the PBL brakes are in widespread use, and the locos will generally behave in the same way as the Class 59.
Ever heard of a thing called a test track?![]()
A test track doesn't give you mainline certification.
A test track doesn't give you mainline certification.
All of them? No one would have been trained to drive them, and they wouldn't have been tested and certified for use on NR infrastructure initially.
Ever heard of a thing called a test track?