Some updates are in the Elizabeth line committee Board papers
page 30
page 30
Fleet Readiness – Further detailed evidence is required from Alstom of their plans to improve fleet reliability over and above the planned software update later in the year. We also need an understanding of the risk/impact if Siemens are unable to provide the 24/7 support cover requested by Alstom.
Alstom’s detailed reliability growth plan was provided and updated in July 2022.
Units cannot be returned to service in Stage 5b minus with any communications-based train control (CBTC) operating restrictions (unlike Stage 3 where units with a CBTC restriction can be used on Great Western Main Line-only diagrams while CBTC fault diagnosis is done).
Alstom and Siemens have now reached an agreement on the level of Siemens support- which includes extending Siemens’ on-site cover to 24/7. Provision of Siemens’ support to Alstom would enable the prompt diagnosis of suspected CBTC defects, including overnight and at weekends. This should mitigate the potential risk to fleet availability at start of service if the number of units with an undiagnosed / unfixed CBTC defect was to exceed four at any one time.