Now that would make sense as I imagine they will want to dispense with the older (7-car) version of the software asap. But it depends how much of a new version of the 9-car software will be required to cater for two missing cars !.
The presentation linked somewhere up thread would appear to imply that there is only one version of the 7-car software - the units that were converted from 9-car to 7-car would have the same software as the units which have only ever been 7-car.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

rebmcr

Established Member
Joined
15 Nov 2011
Messages
4,005
Location
St Neots
They will want to make sure that any conversions are aligned with major exam intervals, otherwise the spare carriages (after eventual re-insertion) would end up forcing early maintenance on the rest of their train.
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,755
Location
Worcester
Would anyone be able to tell me if 001 or 037 will serve Reading today, as I believe they’re the only two serviceable units I haven’t been on.

I’m specifically asking here and not the TOPS thread because I’m sure one of you will be able to tell me if it’s on East, on West, waiting for FLU extension, in the core on test, etc.

Many thanks
 

Gulf1159

Member
Joined
14 Jul 2018
Messages
176
The presentation linked somewhere up thread would appear to imply that there is only one version of the 7-car software - the units that were converted from 9-car to 7-car would have the same software as the units which have only ever been 7-car.
That‘s correct there are two versions of the software one for 7 cars and one for 9 cars
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Reading 20/12

0922 345042 7
5N04 345052
5G74/75 345022
0952 345004
5G50/51 345011 7
1122 345056 7
1152 345042 7
5G56/57 345017 7

21/12
0903 345016 7
0922 345064 7
5N04 345011 7
5G74/75 345022
0952 345042 7
5G50/51 345013 7
5G56/57 345056 7

22/12
0922 345011 7
5N04 345013 7
5G74/75 345022
5G50/51 345038 7
1122 345014 7

23/12
0922 345009 7
5N04 345010
5G74/75 345022
0952 345004
5G50/51 345046
1122 345062
5G56/57 345011 7

24/12
0903 345055
0922 345015 7
5N04 345009 7
5G74/75 345013 7
0952 345058
5G50/51 345011 7
5G56/57 345004
 
Last edited:

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,589
Location
Croydon
The presentation linked somewhere up thread would appear to imply that there is only one version of the 7-car software - the units that were converted from 9-car to 7-car would have the same software as the units which have only ever been 7-car.
I agree that seems to be the case. I was wondering if there might be a new development... An adaptation of the 9-car software would mean the 7-car units could go anywhere signalling wise. But I suspect it would be a big change to the 9-car software for a notional advantage. Leave it alone in other words and that probably extends to not shortening existing 9-car 345s.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
I agree that seems to be the case. I was wondering if there might be a new development... An adaptation of the 9-car software would mean the 7-car units could go anywhere signalling wise. But I suspect it would be a big change to the 9-car software for a notional advantage. Leave it alone in other words and that probably extends to not shortening existing 9-car 345s.
I suggest you watch the relevant part of this presentation which explains the difference between 7-car and 9-car software and how it interacts with the signalling set up. The investment in updating the 7-car software to 'go anywhere' would never have been justified. Even less so now with the 7-car fleet in the process of being removed forever, albeit slightly delayed by the extra services using Paddington platform 14.
https://www.railforums.co.uk/threads/class-345-progress.120221/page-145#post-5238153
 

hwl

Established Member
Joined
5 Feb 2012
Messages
8,243
I agree that seems to be the case. I was wondering if there might be a new development... An adaptation of the 9-car software would mean the 7-car units could go anywhere signalling wise. But I suspect it would be a big change to the 9-car software for a notional advantage. Leave it alone in other words and that probably extends to not shortening existing 9-car 345s.
The Paddington P14 requirement for 7 car will only probably last till September 2022 at the earliest so it really isn't worth it.
 
Last edited:

Peter Sarf

Established Member
Joined
12 Oct 2010
Messages
9,589
Location
Croydon
I suggest you watch the relevant part of this presentation which explains the difference between 7-car and 9-car software and how it interacts with the signalling set up. The investment in updating the 7-car software to 'go anywhere' would never have been justified. Even less so now with the 7-car fleet in the process of being removed forever, albeit slightly delayed by the extra services using Paddington platform 14.
https://www.railforums.co.uk/threads/class-345-progress.120221/page-145#post-5238153
Oh I know. I was originally wondering if a NEW 7-car version of the (go anywhere) 9-car software was an easy route. Rather than keeping and supporting the existing OLD 7-car software (which I seem to recall reading is rather out of date signalling wise). Would that result in less support being required overall for the software ?. It is only for less than a year though so not really necessary - fingers crossed.
 
Last edited:

Gulf1159

Member
Joined
14 Jul 2018
Messages
176
Oh I know. I was originally wondering if a NEW 7-car version of the (go anywhere) 9-car software was an easy route. Rather than keeping and supporting the existing OLD 7-car software (which I seem to recall reading is rather out of date signalling wise). Would that result in less support being required overall for the software ?. It is only for less than a year though so not really necessary - fingers crossed.
No that isn’t an option. Its far move cost effective to update the current software for the 7 car units ( the software is currently stable) The 7 car units only have TPWS signalling software installed where as the 9 cars have TPWS/ETCS and CBTC installed
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
4,005
Location
St Neots
No that isn’t an option. Its far move cost effective to update the current software for the 7 car units ( the software is currently stable) The 7 car units only have TPWS signalling software installed where as the 9 cars have TPWS/ETCS and CBTC installed
Yes, @Peter Sarf already knows that, it's the starting point of his entire line of reasoning, so there's no need to tell him again.

He is specifically theorising about adapting the ETCS software so that it can run on 7-carriage trains. This would bring the benefit of simplifying lengthening/shortening trains; ending maintenance for the 'legacy' software; allowing 7-carriage trains to use the tunnel; while keeping service to short Paddington High Level platforms.

That could either be:
  • a simple task of trimming some lines of code that expect the extra carriages, or
  • a complex task involving a full rebuild of the 9-carriage ETCS software.
Nobody here knows which is true, so your claim about what is or isn't "far move cost effective" lacks credibility.
 

Gulf1159

Member
Joined
14 Jul 2018
Messages
176
Yes, @Peter Sarf already knows that, it's the starting point of his entire line of reasoning, so there's no need to tell him again.

He is specifically theorising about adapting the ETCS software so that it can run on 7-carriage trains. This would bring the benefit of simplifying lengthening/shortening trains; ending maintenance for the 'legacy' software; allowing 7-carriage trains to use the tunnel; while keeping service to short Paddington High Level platforms.

That could either be:
  • a simple task of trimming some lines of code that expect the extra carriages, or
  • a complex task involving a full rebuild of the 9-carriage ETCS software.
Nobody here knows which is true, so your claim about what is or isn't "far move cost effective" lacks credibility.
As I said it isn’t an option and won’t happen. The 7 cars will only be around for another 10-12 months.

I speak from working within the company
 

345 050

Member
Joined
12 Aug 2021
Messages
252
Location
London
Would anyone be able to tell me if 001 or 037 will serve Reading today, as I believe they’re the only two serviceable units I haven’t been on.

I’m specifically asking here and not the TOPS thread because I’m sure one of you will be able to tell me if it’s on East, on West, waiting for FLU extension, in the core on test, etc.

Many thanks
Sorry for late reply. 001 was in West on 8 December. 037 I think is a test unit in the core. I have not seen it out West recently and I haven't seen any reports of it being out West in the last year at least.
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,755
Location
Worcester
Sorry for late reply. 001 was in West on 8 December. 037 I think is a test unit in the core. I have not seen it out West recently and I haven't seen any reports of it being out West in the last year at least.
Thanks! I guess 001 is the only one I can get atm, with 037 and 018, 019, 032, 041, 050, 067, 069 on test duties.
 

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
Reports elsewhere of 345050 in service today out of Liverpool Street so presumably it has had the internal equipment referred to in post 4306 removed.
 

345 050

Member
Joined
12 Aug 2021
Messages
252
Location
London
Reports elsewhere of 345050 in service today out of Liverpool Street so presumably it has had the internal equipment referred to in post 4306 removed.
Travelled on 345 050 this afternoon (East side), can confirm this unit is now in public service. It had a 'new train' smell!
 

TT-ONR-NRN

Veteran Member
Joined
30 Dec 2016
Messages
12,755
Location
Worcester
345032 a further unit in service today on the east side of London.
Rather exciting that only five more remain unserviceable, considering it was closer to half the fleet at the start of the year. I had expected it to stay that way until the shamefully delayed core opened.
 

3973EXL

Established Member
Joined
2 Feb 2017
Messages
2,741
Reading
04/01
5G50 Caped
5G56/57 345012 7
1152 345038 7
1222 345056 7
1252 345064 7

05/01
5G50/51 345032
1122 345012 7
1152 345011 7
5G56/57 345062
1222 345055

06/01
0822 345014 7
0833 345023
0852 345056 7
0903 345038 7
0922 Caped
 
Last edited:

JonathanH

Veteran Member
Joined
29 May 2011
Messages
23,264
Does anyone know if 345003 is a 7 or 9 car?
Thanks
It appears that 345003 has finally broken cover, having seemingly been out of circulation since the start of December.

It appears to have done the move out to the first signal berth outside the depot on Friday. This has been the first sign of units being extended to 9-car in the past. Unusually, there was some time between the unit moving to signal berth 0142 and returning to the depot.
1641656414811.png
1641656447789.png
[Pictures show a screen shot of output from TrackIt! with headcode '5I03' cancelled at signal berth C313 having travelled to signal berth 0142 during the early afternoon on 7 January].

345009 next by all accounts, but I guess it will be a while before we see it. I don't think 345006/07/22 have done passenger work yet since their conversion.
 

kevin_roche

Member
Joined
26 Feb 2019
Messages
997
Is there any news of the software updates on the trains which was due to begin over Christmas? Have any been done?
 

Gulf1159

Member
Joined
14 Jul 2018
Messages
176
Is there any news of the software updates on the trains which was due to begin over Christmas? Have any been done?
Yes ELR110 software update did happen just after the Christmas period.

West portal transition is being tested on Sunday 9 January 2022 between Abbey Wood and Acton Main line. Trains then run ecs to west Ealing loop before returning back to Acton Main line for the next departure back to Abbey wood
 
Last edited: