Bridge lifting

Status
Not open for further replies.

CdBrux

Member
Joined
4 Mar 2014
Messages
919
Location
Munich
An alternative to knocking down and rebuilding bridges, or track lowering, has been trialled. If it works then the time the lines need to be closed is much reduced so a cost reduction thanks to the rail lines remaining open much longer. It would be interesting to know the cost implications for the bridge itself when not counting the cost of closing the lines.

http://www.railwaygazette.com/news/.../view/bridge-lift-to-increase-clearances.html

some quotes from the article:

The ElevArch technique has been developed by Freyssinet under the RSSB-sponsored ‘Avoidance of Bridge Reconstruction’ competition. This was launched in 2014 to find cost-effective ways of increasing clearances under fixed structures to accommodate overhead electrification. According to the safety and standards body, around 500 masonry arch bridges in the UK need to be raised or rebuilt as part of Network Rail’s electrification programme.

....

The patented technique involves cutting the arch free from its abutments and wing walls so it can be jacked up to increase clearances. According to Freyssinet, ‘the sequence of operations is key to maintaining the all-important thrust line’. A horizontal saw cut is made through each abutment, just below the arch springing, and five holes cored horizontally into each abutment. Vertical lifting jacks are inserted into the holes to support the weight of the bridge.

.....

Whereas a full bridge reconstruction or track lowering can require the railway to be closed for several days, Freyssinet believes that ElevArch could reduce this to a matter of hours, with many of the preparatory and completion tasks taking place behind protective barriers while the line is operational.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,588
Location
Scotland
Very interesting - as they say the key is controlling the lateral thrust. Would be nice to see more photos of the slip joint that they mention.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,588
Location
Scotland
looking at the demo pix confirms my instinct that it needs a complete possession
The actual lift would require a possession, but much of the prep work could be done without needing one, depending on access.
 

The Planner

Veteran Member
Joined
15 Apr 2008
Messages
19,624
But it still depends on how close they think they can work to a running railway.
 

Tio Terry

Member
Joined
2 May 2014
Messages
1,197
Location
Spain
The actual lift would require a possession, but much of the prep work could be done without needing one, depending on access.

How long would the road need to be closed? It's great that this technology can be developed and used to reduce significantly the costs of providing adequate clearances but a sudden, say, 500mm step rise in the roadway would be likely to cause a few problems to road and pathway users and, of course, many bridges also have other services in the roadways like telephony, water, gas and electrical services which would need to be catered for.
 

najaB

Veteran Member
Joined
28 Aug 2011
Messages
33,588
Location
Scotland
How long would the road need to be closed? It's great that this technology can be developed and used to reduce significantly the costs of providing adequate clearances but a sudden, say, 500mm step rise in the roadway would be likely to cause a few problems to road and pathway users and, of course, many bridges also have other services in the roadways like telephony, water, gas and electrical services which would need to be catered for.
I would imagine that the road closure would be of similar duration as with conventional methods.
 

pdeaves

Established Member
Joined
14 Sep 2014
Messages
5,932
Location
Gateway to the South West
If it's the bridge lift method I think it is, then the actual lift requires a full possession, not least because of the temporary rods used to tie the two sides of the bridge together.
 

rebmcr

Established Member
Joined
15 Nov 2011
Messages
4,005
Location
St Neots
The Merseyrail Loop had its ceiling re-done from behind barriers, with trains passing underneath the workers and plant.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,586
Location
Nottingham
The Merseyrail Loop had its ceiling re-done from behind barriers, with trains passing underneath the workers and plant.

Not the Loop, the old tunnel southwards from Liverpool Central. The tracks have been lowered to form part of the Link, so there is plenty of headroom to insert a deck above them. This is also featured in the Rail Engineer magazine.
 