• Our new ticketing site is now live! Using either this or the original site (both powered by TrainSplit) helps support the running of the forum with every ticket purchase! Find out more and ask any questions/give us feedback in this thread!

Borders Railway - Now Open

Status
Not open for further replies.

TheKnightWho

Established Member
Joined
17 Oct 2012
Messages
3,183
Location
Oxford
There's a brand new footbridge on the Bicester curve on Evergreen 3 that doesn't have ramps. I don't believe there is a 100% requirement for access ramps in England either.

It has to have passive provision for a lift doesn't it? Could be wrong.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

swt_passenger

Veteran Member
Joined
7 Apr 2010
Messages
34,240
It has to have passive provision for a lift doesn't it? Could be wrong.

No, this is the footpath crossing on the chord itself. It's basically in the middle of a field, i.e. not the massive steel one with all the ramps that resulted in complaints from an adjacent school after it had been erected.

I suspect the rules for stations are different to the rules for footpaths elsewhere, and perhaps the new one being discussed in Galshiels didn't replace an existing level access, so wouldn't need to provide a new one?
 

fegguk

Member
Joined
11 Sep 2012
Messages
181
Location
Hawick
‘Reasonable provision shall be made for people to gain access to and use the
building and its facilities’

Neither the existing foot bridge at Low Buckholmside nor the path that leads to the new one had disabled access before. There is a steep uneven cobbled surface that leads to the new bridge which is quite close to the Ladhope Tunnel (bridge). Its a similar story for the ones at Netherdale. The Pumbtree Brae road was very steep had no pavement, the new bridge there is 4-5 feet higher, I think a ramp would have been impracticable here.

Disabled provision might have been deemed unreasonable given the cost and benefits. This might not have been the case if they were required to access stations and platforms all of which have ramps where required.
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,608
Location
Nottingham
Footbridges for footpaths don't have to have ramps unless the path itself is actually a bridleway or is suitable for use by wheelchairs. However I thought all new stations would need step-free access to all platforms. Is there an alternative route to the platforms here?
 

NotATrainspott

Established Member
Joined
2 Feb 2013
Messages
3,304
This footbridge isn't near the station. Just east of it the railway passes under the A7 through the concrete box that was built a while ago. The single platform at Galashiels is then on the side of the track near the road, so anyone from the footbridge area would be able to access the platform just by walking down the road.

Step-free access to new stations is mandatory across the whole of Europe, I believe. When you're building something from scratch it is never really that difficult to implement. Any works at underground stations (e.g. the Crossrail works at existing tube stations) will likely involve the construction of a shaft to get materials and equipment down to the work level, so step-free access there just makes use of what must be built anyway.
 

fegguk

Member
Joined
11 Sep 2012
Messages
181
Location
Hawick
The track laying train making its way through Gala on Tuesday as the rails are laid before it. Track laying reached Glenfield road that day. They will be crossing the Tweed today.

http://youtu.be/dXedfLdIygI
 
Last edited:

L&Y Robert

Member
Joined
22 Apr 2012
Messages
585
Location
Banbury 3m South
Footbridges for footpaths don't have to have ramps unless the path itself is actually a bridleway or is suitable for use by wheelchairs. However I thought all new stations would need step-free access to all platforms. Is there an alternative route to the platforms here?

Ramps are a requirement of part K of the Building Regulations which apply only in England and Wales. They apply to buildings, not roads and footpaths. There is (was, maybe? My copy is 1998!) a "Limitation on Requirements" such that they: "Do not require anything to be done except for the purpose of securing reasonable standards of health and safety for persons in or about the building"
 

edwin_m

Veteran Member
Joined
21 Apr 2013
Messages
28,608
Location
Nottingham
Ramps are a requirement of part K of the Building Regulations which apply only in England and Wales. They apply to buildings, not roads and footpaths. There is (was, maybe? My copy is 1998!) a "Limitation on Requirements" such that they: "Do not require anything to be done except for the purpose of securing reasonable standards of health and safety for persons in or about the building"

I think the governing legislation in this case is the Accessibility Act.
 

fgwrich

Established Member
Joined
15 Apr 2009
Messages
10,615
Location
Hampshire
In other news, The rails have reached the first platform of Tweedbank Station today, and will probably have the second in place this afternoon. So rails have finally reached the Tweedbank and the end of the line for now.
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
Another video from the "Borders Railway from Start to Finish" people:
https://www.youtube.com/watch?v=zbhcLCqCc6I

On Thursday 5th February 2015, the track laying crew reached its final destination at Tweedbank, around 30 miles after the process began. Here's a flavour of events on that day starting at Winston Road Bridge, crossing Redbridge and onto the new Tweedbank Station, which is still under construction. It was an historic event, and plenty were there to watch a magical moment.
 

DaveNewcastle

Established Member
Joined
21 Dec 2007
Messages
7,387
Location
Newcastle (unless I'm out)
A big smile appeared on my face watching that video of a railway locomotive moving though Galashiels town centre, along the stone retaining wall on Ladhope, almost exactly where trains passed 50 years ago.
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
It certainly goes a long way to offset all those dismal images of track being lifted in the early 1970s.
 

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
In other news, The rails have reached the first platform of Tweedbank Station today, and will probably have the second in place this afternoon. So rails have finally reached the Tweedbank and the end of the line for now.

Onwards to Hawick!

It'll happen in the next 10 years.

Penicuik first though once they see how well Eskbank performs.
 

deltic08

On Moderation
Joined
26 Aug 2013
Messages
2,903
Location
North
What? All the way to the buffers?

I am afraid not. No buffers yet. I was there all day and watched as the most westerly platform face was completed about 15-30 by sliding the rails about 6 inches beyond the last sleeper. This was taken as the completion of the tracklaying to Tweedbank and resulted in raised arms from the tracklaying team and cheers and clapping from spectators and local residents. The team assembled for an official group photograph standing on the end of the track. The camera teams there also took this as completion of tracklaying by asking views of the public now rails have reached the end of the line.

After cutting off the excess rail, the train retreated to north of the switch and the team laid the last two pairs of rails into the eastern most platform face. Unfortunately the last pair were about 60 yards short of the end. An orange suit told me the team will have to return tomorrow to finish the job so they have not completed a day early.

The official completion ceremony and champagne buffet for VIPs is next Thursday morning but the machine and operatives will be back in Holland by then.
 
Joined
24 Nov 2014
Messages
24
I can't wait to get a run up the Borders once the driver training starts. You might be interested to learn that the initial signal sighting work was done using videos made by sending out a lad on a quad bike with a video camera cable tied to the front to drive up and down the old solum!
 

PaxVobiscum

Established Member
Joined
4 Feb 2012
Messages
2,410
Location
Glasgow
Short video of today's ceremony and interviews from the "Borders Railway from Start to Finish" people:
https://www.youtube.com/watch?v=YLArRM8RhHg&feature=youtu.be

I usually slag off their minimalist music unders but this time it's actually quite clever stuff and might even have taken longer to sequence than it does to play. :)

EDIT: Also a News update from Borders Railway - photos and article but no video.
 
Last edited:

Altnabreac

Established Member
Joined
20 Apr 2013
Messages
2,424
Location
Salt & Vinegar
Short video of today's ceremony and interviews from the "Borders Railway from Start to Finish" people:
https://www.youtube.com/watch?v=YLArRM8RhHg&feature=youtu.be

I usually slag off their minimalist music unders but this time it's actually quite clever stuff and might even have taken longer to sequence than it does to play. :)

EDIT: Also a News update from Borders Railway - photos and article but no video.

Good to see Christine Grahame MSP there. She takes a lot of the credit for championing the scheme within the SNP and ensuring it didn't follow EARL and GARL into cancellation after 2007.

She also deserves a lot of the credit for championing Stow station as well.
 

Railsigns

Established Member
Joined
15 Feb 2010
Messages
2,754
Good to see Christine Grahame MSP there. She takes a lot of the credit for championing the scheme within the SNP and ensuring it didn't follow EARL and GARL into cancellation after 2007.

One of life's certainties is that the SNP will claim the credit for this project when it opens, just as they did with the Airdrie-Bathgate reopening, despite both projects having completed their passage through Holyrood under the former Labour-Libdem coalition.
 
Status
Not open for further replies.

Top