Highest power draw of all the units that are likely to be cleared for that route. IIRC, 2 Pendolini (11 cars each) tested the power draw of the Manc-Liverpool section by passing each other at a critical point.

I forgot about that test.
 
Sponsor Post - registered members do not see these adverts; click here to register, or click here to log in
R

RailUK Forums

30907

Veteran Member
Joined
30 Sep 2012
Messages
21,922
Location
Airedale
The through train I took to Buxton was am.
The question about via BLACKBURN ( can't prevent the Bburn capitals) to the S&C referred to the days when Chorley to BLACKBURN was open and passenger trains ran from Wigan to Blackburn via Chorley. In those days I easily got to Hellifield from Preston via Blackburn - and to Skipton from time to time. It was the late 1950s long after the L&Y / Midland trains from Liverpool and Manchester to Scotland ran via Hellifield !

In the 1958 timetable there was a reasonable connection at 8.30 from Chorley, 9.2-9.17 Blackburn, 10.10 Hellifield, after which nothing till the afternoon except Saturday lunchtime. I've not checked the returns, but assume you got back!
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
Highest power draw of all the units that are likely to be cleared for that route. IIRC, 2 Pendolini (11 cars each) tested the power draw of the Manc-Liverpool section by passing each other at a critical point.

Yes, that's what happened. The trains were due to pass around Broad Green, where we feared we might not be able to film, so Paul and I went to Earlestown for passes later in the sequence of tests. The elements joined in to make the tests very real, with horizontal rain to add to the fun.

Here's some of the action:

https://www.flickr.com/photos/127646831@N03/albums/72157673098211848
 

Elecman

Established Member
Joined
31 Dec 2013
Messages
3,569
Location
Lancashire
There is one potential fly in the ointment that I have just seen today. The M61 overbridge between Horwich and Horwich Parkway has had zero work done to its parapet walls. Indeed it doesn’t even have a solid parapet merely a more solid version of a post and wire fence with big gaps in between the horizontals .
 

Karl

On Moderation
Joined
16 Aug 2011
Messages
710
Location
Bamber Bridge
There is one potential fly in the ointment that I have just seen today. The M61 overbridge between Horwich and Horwich Parkway has had zero work done to its parapet walls. Indeed it doesn’t even have a solid parapet merely a more solid version of a post and wire fence with big gaps in between the horizontals .

Is this the one seen here https://goo.gl/maps/etPriFXLkPB2

EDIT: Yikes! Elecman beat me to it :)
 

The_Engineer

Member
Joined
24 Mar 2018
Messages
524
There is one potential fly in the ointment that I have just seen today. The M61 overbridge between Horwich and Horwich Parkway has had zero work done to its parapet walls. Indeed it doesn’t even have a solid parapet merely a more solid version of a post and wire fence with big gaps in between the horizontals .
Does it need any work doing, seeing as a motorway is pedestrian-free??
 

IanXC

Emeritus Moderator
Joined
18 Dec 2009
Messages
6,609
And if they need something really "dirty" in terms of power spikes/signal interference don't they use a Class 92?

And presumably diversion of Caledonian Sleepers via Bolton in the future is not beyond the realms of possiblity...
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,662
There is one potential fly in the ointment that I have just seen today. The M61 overbridge between Horwich and Horwich Parkway has had zero work done to its parapet walls. Indeed it doesn’t even have a solid parapet merely a more solid version of a post and wire fence with big gaps in between the horizontals .

It has not been overlooked, I believe it is on the list for construction in the near future, interaction with Highways England would always be one way of slowing things down. (not a dig just the way it is when 2 big organisations try talking to each other!)
 

Joseph_Locke

Established Member
Joined
14 Apr 2012
Messages
1,878
Location
Within earshot of trains passing the one and half
It has not been overlooked, I believe it is on the list for construction in the near future, interaction with Highways England would always be one way of slowing things down. (not a dig just the way it is when 2 big organisations try talking to each other!)

The part of the design team that did the electrification was assured that the part covering the advance bridge reconstructions had ALL overbridge parapet works in hand. The complete lack of activity at Lever Street footbridge and at other locations does make me wonder ...
 

YorkshireBear

Established Member
Joined
23 Jul 2010
Messages
9,662
The part of the design team that did the electrification was assured that the part covering the advance bridge reconstructions had ALL overbridge parapet works in hand. The complete lack of activity at Lever Street footbridge and at other locations does make me wonder ...
At my last count there were 5 parapet extensions schemes to construct. I just know that work is planned, don't know when. Was trying to reassure that someone isn't going to suddenly realise we need to do some work!
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,463
Location
Preston Lancs
Won't this mean turning on the electricity will be delayed?

I don't see why. I have seen many bridge parapets etc increased in height after electrification on other lines. They will probably put up concrete barriers on the M61 and maybe close the inside lane on one side only. Raise the parapet (or what ever) then rinse and repeat on the other side. I don't see why the switch on can still not happen on time. My 2 penneth
 

DJH1971

Established Member
Joined
10 Jun 2012
Messages
1,751
Location
St Helens, Merseyside
I don't see why. I have seen many bridge parapets etc increased in height after electrification on other lines. They will probably put up concrete barriers on the M61 and maybe close the inside lane on one side only. Raise the parapet (or what ever) then rinse and repeat on the other side. I don't see why the switch on can still not happen on time. My 2 penneth
One bridge in particular being the 'skew' bridge at Rainhill
 

Moonshot

Established Member
Joined
10 Nov 2013
Messages
3,806
Open question to everyone on this thread, on what date do you reckon everything will be done and the whole shooting match ready for electric trains between Blackpool and Manchester?
 

LDECRexile

Established Member
Joined
30 Jan 2014
Messages
2,149
Location
Southport, UK
I had a quick whizz down to the Salfords today, via Bolton.

I couldn't see any wiring changes since Monday, but:

1. The buffet at Bolton was open and doing business
2. Work was in progress on the unfamiliar structures near Squeeze Belly and Balustraded bridges
3. The lift to the westbound platform at Salford Central was back in action after a long closure

I reckon Salford Central looks wire-ready.

Handful of photos added to the Combined Volume here:

https://www.flickr.com/photos/127646831@N03/albums/72157661069863633

We're away again from tomorrow morning to Sunday pm. Please send images as usual. I should be able to process any received before 21:00 today today and owt after than on Sunday evening.
 

a_c_skinner

Established Member
Joined
21 Jun 2013
Messages
1,699
I have seen many bridge parapets etc increased in height after electrification on other lines.

Expressing surprise, not disagreement, but I thought the parapet hight was a safety issue, so are we happy with managing risk by not having it last very long?
 

GRALISTAIR

Established Member
Joined
11 Apr 2012
Messages
10,463
Location
Preston Lancs
Expressing surprise, not disagreement, but I thought the parapet hight was a safety issue, so are we happy with managing risk by not having it last very long?
Well if it was a road over especially with a pedestrian footpath that would be different. This case is a motorway with -in theory - next to zero foot traffic. I can show photos of roads and footpaths over busy motorways with very low barriers indeed. It is a different set of rules (unfairly imho) for roads.
 

td97

Established Member
Joined
26 Jul 2017
Messages
1,556

td97

Established Member
Joined
26 Jul 2017
Messages
1,556
Open question to everyone on this thread, on what date do you reckon everything will be done and the whole shooting match ready for electric trains between Blackpool and Manchester?
Pendolino testing at the start of next month sounds too optimistic. I think the wiring (as in OLE) will be completed before the source of electricity for the wires is ready.
 

superkev

Established Member
Joined
1 Mar 2015
Messages
2,856
Location
west yorkshire
Pendolino testing at the start of next month sounds too optimistic. I think the wiring (as in OLE) will be completed before the source of electricity for the wires is ready.
Don't forget that even after it all goes live there's all the approvals and paperwork to do which in the GW seems to have taken months. I don't think there yet using electric mode beyond Didcot despite the wires being live for several months.