According to Real time trains both 4 and 5 are in use. Whether that reflects reality I have no idea! I was thinking we would have an Airport style situation with no trains using the platform for months on end! Impressive.
According to Real time trains both 4 and 5 are in use. Whether that reflects reality I have no idea! I was thinking we would have an Airport style situation with no trains using the platform for months on end! Impressive.
Yes, but to a track alignment that was compromised by an unfortunate incident involving a retaining wall just south of the overline bridge - I would guess that the removal of said retaining wall, following the second flood, may have opened up the opportunity to address this compromise.
Thanks, when was the first flood? During the works two years ago or earlier?
I took this photo in July from the bridge at Poulton showing the severed connection. I think any dream of connecting Fleetwood to the network is dead and buried.
https://www.instagram.com/p/BW4goAylgos/
IIRC there used to be a cattle dock or similar on that side so, unless more recent works have impinged on the space, there should indeed be room on that side for a line and even a platform.I think there is room alongside the up line for a single line from the branch, if it were an extension of Blackpool Tram operations then it would need a separate platform at Poulton anyway![]()
I travelled Southport-Bolton-Salford Crescent-Bolton-Salford Central-Bolton-Southport today.
Bolton Platform 4 closed, with evidence of edging work in hand. All except the northern end of Platform 5 is in use instead, at least 8 carriages could be accommodated. Platforms 1 and 3 in use, Platform 2 seemed to be open, but rail head not shiny. I'm not sure when a train is due there.
I had hoped to see clear leaps forward south of Bolton, but progress is patchy, perhaps the Moses Gate incident threw a spanner in the works.
There are no masts up between Agecroft Road and Squeeze Belly Entry footbridge, getting on for 5.5 miles apart. I could see no evidence of work at the foot crossings either side of the M60 bridge. There are gaps in bases near Dixon Fold and south of Cock Robin bridge. There has been progress with signalling, but there are still stretches with either bare wires at trackside or wires threaded through temporary tubing. I have no idea if progressing these is hard or easy.
There is an extra sprinkling of danglies across the masts which are up, notably Salford Crescent to Central, but even there there remains several mastless bases.
There is clear evidence that all hands have put their backs into getting traffic moving through Moses Gate, warm thanks to all concerned. The edging on the southbound platform at MG appears to have been replaced, work is in hand on the northbound platform.
The extra piling at the northern portal of Farnworth tunnel appears to be complete, but what appear to be stainless steel rods are protruding above, suggesting some sort of Bayko-like capping is to be added.
Lots of Orange in evidence working on the base for the electrical mega-thingy at Lostock Junction, but the thingy itself is not yet in place.
Bolton looks like a nice job, but I've seen nothing today to make me change my prediction for electric services starting in March-April 2018.
Photos later (including one from Reg).
by Chris Davis, on Flickr
by Chris Davis, on Flickr
by Chris Davis, on Flickr
by Chris Davis, on Flickr
by Chris Davis, on Flickr
by Chris Davis, on FlickrReg kindly sent a photo for publication.
I've added it to his album here:
https://www.flickr.com/photos/127646831@N03/albums/72157671732263863
I've added it and my shots from today to the Combined Volume here:
https://www.flickr.com/photos/127646831@N03/albums/72157661069863633
Thank you Reg.
PS: I took a 60 second film of a train arriving at Platform 5, but it refuses to load. I'll keep trying.
Great news for those of us using the Clitheroe line, on Platform 1 the signal has been replaced and moved to beyond the lift, which should allow longer trains to use the platform!
Great news for those of us using the Clitheroe line, on Platform 1 the signal has been replaced and moved to beyond the lift, which should allow longer trains to use the platform!
Passengers can travel by train between Bolton and Manchester again after the line reopened early following emergency repairs to a bridge which was badly damaged by a burst water main.
The Moses Gate railway bridge, near Bolton, was damaged on 17 August when the burst pipe caused a section of it to collapse onto the railway below and created a hole in the road above.
The line through the area fully reopened today (6 September) however, due to recent wet weather which has delayed some work, Moses Gate station will be closed until later in the week while work continues to complete upgrades as part of the electrification of the line.
Andy Morgan, senior sponsor for Network Rail, said: This has been an extremely challenging repair programme and we have been working 24/7 to get passengers moving between Bolton and Manchester. To repair the bridge, we have rebuilt a large section of wall which supports the bridge and make it stronger.
We have been working at Moses Gate station to make sure it is ready for electric trains to run. However, due to the recent wet weather, it has slowed progress meaning the station will be temporarily closed until later in the week.
I would like to thank all passengers for their patience during this complex situation.
Liam Sumpter, Northern regional director, said: We look forward to welcoming customers back to Bolton from Wednesday as we restart our full train service for journeys into Manchester.
We want to thank all of our customers for their help and understanding over the last week.
Before the water main burst, the railway through the area was already closed because of upgrade work at Bolton station as part of the Great North Rail Project. The station and railway between Bolton and Manchester was due to open on Monday 28 August. The work at the station which included remodelling of the tracks, station platforms and signalling systems was completed on time as planned and is part of plans to upgrade and electrify the railway to provide passengers with better, more reliable trains.
Although a completion date for work to the road is yet to be confirmed it is expected reopen within the original six week estimate.
Nineteen weeks of work to upgrade Blackpools railway from 11 November
Buses replacing trains during railway closures
Network Rail and Northern working together to deliver the Great North Rail Project
Train passengers were today advised to prepare for a major railway transformation in Blackpool.
The purpose of the work is to make the railway bigger and better to carry the increased numbers of people forecast to want to travel by train in the future.
From 11 November the Great North Rail Project, part of Britains Railway Upgrade Plan, is embarking on 19 weeks of work which will affect travel to and from the seaside town.
During this time Network Rail will carry out vital upgrades to track and platforms at Blackpool North and Kirkham & Wesham stations. We are also upgrading the signalling system on both lines to Blackpool which includes installing 84 new modern signals which will help to make journeys more reliable.
For Network Rail to do this work sections of the railway will need to close to Northern train services. Buses will replace trains during these closures.
Between Saturday 11 November and Sunday 28 January 2018 the railway will be completely closed between Preston and Blackpool North and Blackpool South stations.
Between Monday 29 January 2018 and Sunday 25 March 2018 the railway between Preston and Blackpool South will reopen but the railway between Kirkham & Wesham and Blackpool North will remain closed.
The upgrade forms part of the Great North Rail Project to improve journeys between Blackpool and Preston and across the north of England.
When the upgrades is complete Blackpool-to-Preston passengers will benefit from a cleaner, greener, quieter and more reliable railway.
Martin Frobisher, Network Rails London North Western route managing director, said: The upgrade of the line between Preston and Blackpool is the largest rail investment in the area since the 19th century. It will enable greener, quieter and more reliable train services, providing passengers and Blackpool with a railway to be proud of.
As Blackpools economy grows, the railway is growing too and we are working with the wider industry and our Blackpool region partners to keep the people of Blackpool and the Fylde on the move throughout the closure. There is never a good time to carry out this type of work but we have planned it to take place outside of the main holiday season so it causes the least impact.
I am confident the short-term pain will certainly be worth the long-term gain of transformed train travel in future.
Sharon Keith, regional director at Northern, said: The upgrade of the line between Preston and Blackpool is a key phase of the modernisation of the railway in the north of England.
The work will pave the way for further improvements for our customers who, in the future, will benefit from brand new or fully refurbished electric trains resulting in better journeys and, thanks to further investment, better stations.
Id like to thank our customers in advance for their understanding and patience whilst this essential work takes place.
Transport Minister Jesse Norman, said: This vital upgrade is part of the governments biggest investment in the network since Victorian times and will mean more seats, better connections, and more reliable journeys for rail passengers.
We recognise there will be temporary disruption, but the benefits for passengers will be significant when complete. We are investing billions of pounds in transport across the region and I am delighted that this project is on track to deliver what passengers have told us they want to see.
For more information please visit www.networkrail.co.uk/blackpool
It's insurance, to make sure the driver understands that they are taking the turnout route. That way, all turnout moves look the same and all look different from a move forward on the main line. You could also (in theory) have a had a shunt route forward from MP9239 to behind MP638 on the Up (to an LOS and then shunt to 4) but I'm suspecting that even Ops couldn't justify it.
Please see Trackworker's comment on Photo 8276k
Can anyone corroborate, refute or otherwise?
141trackworker said:so iv been told the platform 3 and 4 has been scrapped
You can add that GMPTE, Salford and Manchester Councils will be once again having to put the begging bowl out. The errant OHLE/ signalling that sits in the way somewhere and the fact that TPE's new trains no longer fit in the station also doesn't help either. Not sure if they ever wanted to stop in the first place.
The original sum now only covers the adjustments and upgrades to platform 1 and 2.
So if I understand local authorities wanted something (platforms 3 & 4) that NR had no plans for and TOC's don't seem to want. Local authorities secured the funding.
Meanwhile NR designs other upgrade work (electrification & signalling) that does not provide passive permission for the two platforms? A case of 'not my idea' vs listen to (one of) your customers?
After the first trip round the works today for 6 weeks, I can only echo LDECRexile's comments on progress.
Preston-Blackpool continues to impress, with a lot of steelwork now up, much of it with registration gear.
The gap between Salwick and Kirkham is pretty much closed, leaving just the extended Kirkham station area to do.
Euxton-Salford is a real curate's egg of progress.
When a landslip like the one at Moses Gate railway bridge occurs, do Network Rail take-off the opportunity to improve (cut back) the slope or do they reinstate at the original profile?