re
rlando St Bridge
A bigger crane is on site on the west side, on the station car park. They have lifted in two cill beams on to the west side abutment. There are two more to go in on the east side, but I couldn’t se them anywhere.
There is a new hard standing on the east side near the bridge which can be accessed from the retail park, I don’t know if they can access it by crossing the tracks. They may have to move the crane to this area to lift the other cills as I was told that they weigh approx. 50 tons each and it’s a long reach from where it is now. If they have to go through the retail park with the crane and the cills, they may not move it until tonight or early tomorrow, but that’s only my guess.
The engineer told me that the bridge will be lifted in next Friday night/Saturday morning, she will email the times to me later. It will be a 1000 ton capacity crane as I was told by another orangeman that the two lifts are about 100 tons each.
There’s also another small bridge to replace over the roadway behind the retail park, it’s on the general arrangement drawing that Bolton MBC have. Orlando Street runs over both bridges.
re: Farnworth Tunnel
She also works on the tunnel, they are making good progress, as they are now in clay and the expect good ground under St Peter’s Way. They have some professional photos from the tunnel and we may be able to get copies, but I think we would have to get permission to publish them.