There is no activity directly related to electrification equipment between Salford and Euxton yet as far as I am aware - the design isn't signed off yet, AFAIK.
I did a run from Manchester to Preston today, and there is no sign of any electrification activity, at least on the Up (Manchester-bound) line.
The only activity seems to be bridge rebuilding and preparation for the Chorley blockade, none of it involving mast bases.
All there is to see is the work around Salford Central, where Balfour Beatty have their local depot.
This includes stockpiles of the big concrete slabs that go to make up the pancake-type mast foundations on the viaducts west of Victoria.
I think they look particularly ugly, especially the 5-high ones used for mast stays (the masts themselves use slightly less obtrusive 2-high sets of slabs).
Yesterday,after studying the TPE temporary timetable booklet,I went to Euxton Balshaw Lane for the 12.31 TPE to Blackpool North only to see it fly through the station at around 50mph.There isnt that many extra trains anyway but this is pathetic and on Saturday the 12.14 Northern to BPN was already full to bursting point when it arrived at Euxton,where about 30 people were waiting compared with the usual 5 or 6.I would say over 50% of passengers are going to use this service instead of the replacement buses from Chorley.More seats and more stopping trains would have been nice.
Delay from Summer 2016 to Winter 2016?
Theyve had stick from the current Chorley closure reducing capacity during Blackpools busy season.
As a result of this additional investment, the Blackpool line work programme has been rescheduled, with the main works starting in mid-December 2016 and lasting approximately three months, avoiding the key holiday period for the resort
The completion date was already Feb 2017 in the latest update to the CP5 Enhancements Delivery Plan.
I found this on the Network rail website:-
http://www.networkrailmediacentre.c...l-investment-in-Blackpool-continues-2112.aspx
Blackpool North will be closed from mid Dec 2016 for around three months.
This delay isn't new news. It's been known about for several months now. It also makes sense as Manchester-Preston will be opened for December 2016 and Blackpool March 2017 as electrifying to Blackpool before via Chorley was open didn't make great sense.
Are you sure ?
Looking at the CP5 Enhancements Delivery Plan dated 30 June 2014 on Page 127 it still has May 2016 listed as the delivery date for Preston-Blackpool electrification.
Are you sure ?
Looking at the CP5 Enhancements Delivery Plan dated 30 June 2014 on Page 127 it still has May 2016 listed as the delivery date for Preston-Blackpool electrification.
Indeed. However, is was evident today that there has been no direct electrification work (mast bases etc) on the Euxton Jn-Chorley section during the blockade.
Apart from the flying arches, the track has been lowered through the tunnel and several bridges, and there is still a lot of site work going on.
Apart from the flying arches, the track has been lowered through the tunnel and several bridges, and there is still a lot of site work going on.
Is there any similarity in engineering work requirements for track-lowering inside the Chorley tunnel and the Farnworth tunnels, or do the Farnworth tunnels require somewhat of a different planning strategy ?
I think the work at Chorley involved the installation of slab track as well as lowering the track height.
At Farnworth, I think this is also what is planned for the larger tunnel (which will become double-tracked once more).
The small one will be abandoned when the larger one is finished.
Chorley tunnel is 124 yards, Farnworth 295.
PS I bought some Chorley Cakes in Chorley Market yesterday to mark my first visit. Made in Burnley...![]()
That should be interesting as the A666 dual carriageway goes over it.